Hush Street is tracking what’s being built on Manhattan’s Upper East Side.
For decades the Upper East Side changed slowly, inside landmark districts and contextual zoning. That is shifting at both ends of the neighborhood. At East 60th Street, Extell has begun excavating 655 Madison Avenue, a 1,162-foot condo-and-office tower that New York YIMBY calls the neighborhood’s first supertall. Near the river, Memorial Sloan Kettering and Lenox Hill Hospital have both won approval for major new buildings, and the Met broke ground on its new modern art wing in September.
In between, condo and rental towers are rising along the Second and Third Avenue corridors, which CityRealty ties to the Q train’s arrival. Several depend on air rights bought from neighboring buildings or landmarks, and a proposed rezoning at First Avenue and East 60th Street would allow a 39-story building with about 89 affordable apartments.
Where DOB records and press reports disagree on heights or unit counts, both are given. A permit is not treated as proof that construction has started.
| Project | Location | Status |
|---|---|---|
| 1655 Madison Avenue | Madison Ave. at E. 60th St. | Under Construction |
| 2Kenneth C. Griffin Pavilion at Memorial Sloan Kettering | York Ave. at E. 66th St. | Under Construction |
| 3Lenox Hill Hospital Redevelopment | E. 76th–77th Sts., Park–Lexington | Approved |
| 4Goldman Health Care Pavilion (1345 Third Avenue) | Third Ave. at E. 76th St. | Enclosed; Opening 2027 |
| 5The Met's Tang Wing for Modern and Contemporary Art | 1000 Fifth Ave. (Central Park) | Under Construction |
| 6East River Esplanade Reopening & Reconstruction | FDR Drive, E. 59th–81st Sts. | Reopening Nov. 23 (E. 72nd–78th) |
| 7175 East 82nd Street | Third Ave. at E. 82nd St. | Nearing Completion |
| 8185 East 80th Street | Third Ave. at E. 80th St. | Demolished; In Plan Review |
| 91491 Third Avenue | Third Ave. at E. 84th St. | Demolition Permitted |
| 101482 First Avenue | First Ave. at E. 77th St. | Under Construction |
| 111655 First Avenue and 355 East 86th Street | First Ave. at E. 86th St. | Nearing Completion |
| 12Maison171 (171 East 86th Street) | Third Ave. at E. 86th St. | Topped Out |
| 13260 East 72nd Street | Second Ave. at E. 72nd St. | Under Construction |
| 14242 East 71st Street | Second Ave. at E. 71st St. | Under Construction |
| 151352-1354 First Avenue | First Ave. at E. 73rd St. | Approved |
| 16301 East 71st Street | Second Ave. at E. 71st St. | Permitted |
| 17150 East 79th Street | Lexington Ave. at E. 79th St. | Demolition Permitted; Air Rights Filed |
| 181097 First Avenue Rezoning | First Ave. at E. 60th St. | Rezoning Filed |
| 191122 Madison Avenue | Madison Ave. at E. 84th St. | Under Construction |
| 20985 Fifth Avenue | Fifth Ave. at E. 80th St. | Landmarks-Approved |
| 21800 Fifth Avenue | Fifth Ave. at E. 61st St. | Landmarks-Approved |
| 22809 Madison Avenue | Madison Ave. at E. 68th St. | Permitted |
| 23309 East 94th Street (Former Iron Horse Labs Site) | E. 94th St., First–Second Aves. | Stalled |
| 241643-1651 First Avenue | First Ave., E. 85th–86th Sts. | Demolition Permitted |
| 25New York Blood Center "Center East" | E. 67th St., First–Second Aves. | Stalled |
A Supertall, Two Hospitals, the Met & the Esplanade
The largest projects here are institutional, plus one tower that brings Billionaires’ Row-scale height to the Upper East Side.
1
655 Madison Avenue
The Upper East Side's First Supertall
Extell bought about 135,000 square feet of unused development rights from the landmark at 790 Fifth Avenue, a transfer City Planning certified in May 2026 (ZAP 2025M0376). A separate City Planning application for the transit-improvement bonus behind the 1,162-foot design (ZAP 2025M0265) still shows as filed rather than approved, and the DOB new-building application is still in objections, even though foundation work is permitted.
YIMBY reported a $1.13 billion construction loan from Tyko Capital and a 65,000-square-foot Chanel flagship, with completion posted on site for spring 2030. Hush Street separately tracks 625 Madison Avenue, a block south.
Sources: New York YIMBY (July 2026); NYC Planning ZAP 2025M0376; NYC Planning ZAP 2025M0265; NYC DOB NOW job M01139026 and permits for BIN 1091953 (accessed Oct. 2026)
2
Kenneth C. Griffin Pavilion at Memorial Sloan Kettering
A 594-Foot Hospital Tower
The City Council approved the rezoning for the pavilion in 2024 despite community opposition to its height, according to Friends of the Upper East Side Historic Districts (ZAP 2022M0359). It replaces MSK’s former Sloan House residence towers.
Sources: Memorial Sloan Kettering; Friends of the Upper East Side Historic Districts (Sept. 2024); NYC Planning ZAP 2022M0359; NYC DOB NOW job M01205691-I1 and permits for BIN 1045571 (accessed Oct. 2026)
3
Lenox Hill Hospital Redevelopment
Cut Down From 516 Feet
Northwell first proposed a 516-foot medical tower and a 490-foot, 200-unit apartment tower; the plan was cut to 436 feet, then 395, then the approved 370 feet, according to YIMBY. Construction is expected to take about nine years.
Northwell’s separate outpatient building at 1345 Third Avenue, below, is already enclosed.
Sources: New York YIMBY (Aug. 2025); Northwell Health; NYC Planning ZAP P2017M0299
4
Goldman Health Care Pavilion (1345 Third Avenue)
Northwell's Outpatient Hub
The Victoria and Lloyd Goldman Health Care Pavilion is the first piece of Northwell’s Upper East Side expansion to near completion, a block from the hospital rebuild.
Sources: Northwell Health; New York YIMBY (Oct. 2025); NYC DOB NOW job M08013299-I1 (accessed Oct. 2026)
5
The Met's Tang Wing for Modern and Contemporary Art
Frida Escobedo's Wing
The Art Newspaper reported a cost of about $550 million and said the Met has raised $670 million for building and operating the wing, including a $125 million gift from Oscar L. Tang and H.M. Agnes Hsu-Tang. DOB’s estimated job cost is $153.6 million.
Sources: The Art Newspaper (Sept. 2026); The Metropolitan Museum of Art; NYC DOB NOW job M01289549-I1 (accessed Oct. 2026)
6
East River Esplanade Reopening & Reconstruction
A Long-Closed Waterfront Path Returns
The East 70s stretch has been closed for years while HSS built Kellen Tower, a 12-story, 94,000-square-foot facility over the highway that has since opened. For runners and cyclists, the reopening is the most immediately useful item on this page.
Sources: Hospital for Special Surgery; NYC Parks Capital Project Tracker; Hospital for Special Surgery (Kellen Tower)
Condo and Rental Towers on the Avenues
Most new homes are rising on Second, Third and First Avenues, often on sites assembled with air rights, plus two Fifth Avenue rebuilds.
7
175 East 82nd Street
The Tallest New Tower on Third Avenue
Douglaston’s tower had topped out its residential floors by February, CityRealty reported, and is the most advanced of the Third Avenue condo towers on this page.
Sources: New York YIMBY (Oct. 2026); NYC DOB NOW job M00995463-I1 (accessed Oct. 2026)
8
185 East 80th Street
Built on $19.2 Million of Air Rights
Skyline bought nearly 57,000 square feet of air rights from the Brodsky Organization for $19.2 million, CityRealty reported. CityRealty’s 2027 completion estimate looks early given that the new building is not yet approved.
Sources: New York YIMBY (Jan. 2026); CityRealty (Feb. 2026); NYC DOB NOW jobs M01189399-I1 and M01164570-I1 (accessed Oct. 2026)
9
1491 Third Avenue
Another Third Avenue Tower
CityRealty estimates completion in 2028. The gap between the DOB and YIMBY unit counts has not been explained.
Sources: New York YIMBY (Jan. 2026); NYC DOB NOW jobs M01325392-I1 and M01331393-I1 (accessed Oct. 2026)
10
1482 First Avenue
Rising Fast on First Avenue
The project has a $127 million two-part construction loan, according to YIMBY, which expects completion by the end of 2027.
Sources: New York YIMBY (Oct. 2026); NYC DOB NOW job M01128646-I1 (accessed Oct. 2026)
11
1655 First Avenue and 355 East 86th Street
Twin Rentals in Yorkville
At 198 apartments, the pair is the largest rental addition on this page that is close to opening.
Sources: New York YIMBY (Sept. 2026); NYC DOB NOW jobs M01142990-I1 and M01146211-I1 (accessed Oct. 2026)
12
Maison171 (171 East 86th Street)
Rising Where Papaya King Stood
Units run two per floor up to the 11th story and full floors above, YIMBY reported.
Sources: New York YIMBY (Apr. 2026); CityRealty; NYC DOB NOW job M01025480-I1 (Sept. 2026)
13
260 East 72nd Street
Next to the Second Avenue Subway
City Planning certified a transit easement for the site in connection with the subway (ZAP 2022M0310). The developer attribution differs by source and is given both ways here.
Sources: New York YIMBY (Oct. 2026); CityRealty (Mar. 2026); NYC DOB NOW job M00785688-I1 (accessed Oct. 2026)
14
242 East 71st Street
A RAMSA Tower on Second Avenue
It is a block from the 260 East 72nd Street and 301 East 71st Street projects on this page.
Sources: New York YIMBY (June 2026); NYC DOB NOW job M00665110-I1 (Aug. 2026)
15
1352-1354 First Avenue
A Family Site Assembled Over Decades
The family has owned 1354 First Avenue for 59 years and added the neighboring lots in 2019 and 2020, YIMBY reported.
Sources: New York YIMBY (Nov. 2025); NYC DOB NOW job M01140296-I1 (Oct. 2026)
16
301 East 71st Street
Using City of Yes's Affordability Bonus
The 18 affordable apartments come through the Universal Affordability Preference, the City of Yes density bonus for buildings that include income-restricted homes. The new-building application itself is still in plan review.
Sources: New York YIMBY (June 2026); NYC Planning ZAP 2026M0366; NYC DOB NOW job M01361353-I1 and permits for BIN 1091918 (accessed Oct. 2026)
17
150 East 79th Street
Landmark Air Rights at Lexington
Closer Properties is asking to transfer development rights from landmarks on this block and a nearby one. No new-building plan has been filed yet.
Sources: NYC Planning ZAP 2026M0250; New York YIMBY (Oct. 2025); NYC DOB NOW job M01362983-I1 (accessed Oct. 2026)
18
1097 First Avenue Rezoning
A Rezoning by the Bridge
The application would change the site’s commercial zoning to allow a much larger mixed-use residential building, with affordable housing required under mandatory inclusionary housing. Who is behind it differs by source and has not been clarified.
Sources: NYC Planning ZAP 2023M0316; East Side Feed (Apr. 2026); Crain's New York Business (Apr. 2026)
19
1122 Madison Avenue
Limestone on Madison
CityRealty describes it as a limestone condominium at the corner of East 84th Street.
Sources: New York YIMBY (Aug. 2025); CityRealty; NYC DOB NOW job M00952569-I1 (Aug. 2026)
20
985 Fifth Avenue
Replacing a 1969 Rental on Fifth
The design was revised in 2025 to add about 12,500 square feet under the City of Yes zoning changes, YIMBY reported. The DOB application predates that redesign and remains in objections.
Sources: New York YIMBY (Nov. 2025); NYC Landmarks permit LPC-26-03160 (Feb. 2026); NYC DOB NOW job M08011563-I1 (accessed Oct. 2026)
21
800 Fifth Avenue
A Tower Made Shorter
Unusually, the redesign makes the building shorter, rebuilding a 1979 tower on Fifth Avenue as a 26-story condo designed by Robert A.M. Stern Architects.
Sources: New York YIMBY (Nov. 2025); NYC Landmarks permit LPC-26-11317 (June 2026); NYC Planning ZAP 2026M0136
22
809 Madison Avenue
Fewer, Larger Apartments on the Gold Coast
Macklowe bought the building for $49 million in September 2025, The Real Deal reported. It is inside the Upper East Side Historic District.
Sources: The Real Deal (Oct. 2026); NYC DOB NOW job M01262427-I1 (Sept. 2026)
Sites Waiting for a Plan
A lab site sold to a housing developer, a long-held Extell block and a rezoned expansion that never started.
23
309 East 94th Street (Former Iron Horse Labs Site)
From Labs to an Open Question
The lab enlargement permitted in 2024 was never built. LCOR has not said what it plans for the site.
Sources: Commercial Observer (Sept. 2026); The Real Deal (Sept. 2026); NYC DOB NOW job M00799130-I1 (May 2026)
24
1643-1651 First Avenue
Extell Clears Its Corner
Extell bought the buildings in 2014, Patch reported. The site is across East 86th Street from the separate 1655 First Avenue towers on this page.
Sources: Patch; NYC DOB NOW jobs M00625489-I1, M01366994-I1 and M01475289-I1 (Oct. 2026)
25
New York Blood Center "Center East"
Rezoned, Then Nothing
The rezoning was one of the most contested Upper East Side land-use fights of recent years.
Sources: NYC Planning ZAP 2019M0430; The Real Deal (June 2025); New York YIMBY (Oct. 2020)
What We're Watching Next
Whether City Planning grants 655 Madison Avenue’s transit bonus, when Lenox Hill Hospital files its new building with DOB, and whether the East River Esplanade actually reopens on Nov. 23 are the next milestones. Smaller projects to watch include a 20-story, 28-unit condo planned for 1527 York Avenue, with construction slated for early 2027, and Rybak’s 21-story condo at 248 East 62nd Street, which received its permit in September. Also next: permits for 1352-1354 First Avenue, LCOR’s plans for 309 East 94th Street and Extell’s next filing on First Avenue.
Hush Street also tracks Midtown East to the south and the Upper West Side across Central Park.
Header photo: residential towers on the Upper East Side, November 2025, by Kidfly182, via Wikimedia Commons, CC BY 4.0, resized.
By Hush Street Editorial Updated Built from city filings and published reporting. About Hush Street