Development Tracker — Fordham, Belmont & Bedford Park
What's Being Built in Fordham, Belmont & Bedford Park? A Stalled 927-Unit Waterfront Plan, Webster Avenue Towers & Phipps in West Farms
Hush Street tracks what's changing in Fordham, Belmont, Bedford Park, Norwood and East Tremont: a 927-unit waterfront plan stalled by its developer's bankruptcy, a 510-unit building and Fordham dorm on Webster Avenue, Phipps Houses' plans in West Farms and a wave of 99-unit buildings.
16
Projects Tracked
~927
Affordable Homes Planned at Fordham Landing
41 of 169
Recent Filings at 90-99 Units
6
Under Construction
Oct. 2026
Updated
Watch →Developer in Chapter 11 at Fordham LandingRezoning Approved Over Board's Objection
By Hush Street Editorial
What’s Changing
→
The City Council approved the 457-unit Sojourner Truth–Mapes rezoning.Oct. 2026
→
A DOB inspection recorded 2868 Webster Avenue as topped out.Oct. 2026
→
Fordham Landing South's commercial rezoning went to Community Board 7.Oct. 2026
Development here mixes a few very large affordable campuses with a dense wave of mid-rise infill. The biggest plan, Fordham Landing South on the Harlem River, would bring about 927 affordable apartments, but its developer’s Chapter 11 filings have kept it in limbo. In West Farms, Phipps Houses won City Council approval in October for 457 affordable apartments over Community Board 6’s unanimous objection, and is starting the third phase of its Lambert Houses rebuild.
Webster Avenue, rezoned for housing in 2011, is filling in next to Fordham University, with a 510-unit building and a 12-story dormitory filed side by side. Smaller buildings dominate the pipeline: of 169 new-building applications filed in Community Districts 5 through 7 since January 2025, 41 propose 90 to 99 apartments and only five propose 100 or more, according to Hush Street’s count of DOB filings. That pattern matches developers staying under the 100-unit threshold that triggers the 485-x tax program’s wage requirements.
Where DOB records and press reports disagree on heights or unit counts, both are given. A permit is not treated as proof that construction has started.
Developer/ApplicantDynamic Star LLC; Perkins Eastman (YIMBY)
ProjectA fully affordable waterfront complex of about 927 apartments in a revised four-tower design, one 33 stories and three 18 stories, YIMBY reported in October 2026. City Planning’s latest application cites 921 units; the two DOB filings total 835 units in buildings of 34 and 19 stories.
StatusApproved; Financing in Doubt
Latest UpdateA separate rezoning to add commercial space was certified on Sept. 23, 2026 and sent to Community Board 7 on Oct. 2. No DOB work permits have been issued for either building, and YIMBY reported no start date.
Two Chapter 11 Filings
The developer filed for Chapter 11 in December 2025 and again in March 2026, and a $55 million state award has not been paid out, Norwood News reported in August. A ceremonial Phase I kickoff was held in September 2025. The waterfront approval dates to 2024.
Developer/ApplicantMaddd Equities and Stagg Group (YIMBY); Aufgang Architects
ProjectA 13-story mixed-use building with 510 apartments (YIMBY; DOB lists 515), the largest private residential filing in the area.
StatusFiled (Plan Review)
Latest UpdateThe new-building application has been in DOB objections since March 2026, with no work permits. YIMBY re-reported the plan in July alongside the companion Fordham dormitory on the same lot.
The Area's Biggest Private Filing
YIMBY reported 672 total dwellings planned across the lot, counting the dormitory.
Sources: New York YIMBY (Nov. 2025); NYC DOB NOW job X01298990 (Mar. 2026)
3
2740 Webster Avenue (Fordham Dormitory)
2740 Webster Avenue (Fordham Dormitory), via Google Street View. —
Imagery: Google Street View
Developer/ApplicantMaddd Equities and Stagg Group, for Fordham University; Aufgang Architects
ProjectA 12-story dormitory with 162 units for Fordham’s Rose Hill campus (YIMBY); DOB lists it as a college dormitory of about 252,000 square feet.
StatusFiled (Plan Review)
Latest UpdateYIMBY published a rendering in July 2026 and reported a July 2028 completion target. The DOB application has been in objections since March.
Privately Built Student Housing
It shares a lot with 2768 Webster Avenue.
Sources: New York YIMBY (July 2026); NYC DOB NOW job X01298988 (Mar. 2026)
4
2868 Webster Avenue
2868 Webster Avenue, via Google Street View. —
Imagery: Google Street View
Developer/ApplicantDouglaston Development with the Jericho Project; Stephen B. Jacobs Group
ProjectA 12-story affordable building with 279 apartments (DOB, City Planning; YIMBY reported 277, 60 of them supportive), the second phase next to the New York Botanical Garden.
StatusTopped Out
Latest UpdateA DOB inspection on Oct. 17, 2026 recorded the 12-story building as topped off, and DOB issued a plumbing permit on Oct. 13. YIMBY reported a 2027 completion target.
Phase II Beside the Garden
The first phase, 188 senior apartments at 2850 Webster Avenue, was finished in fall 2023, YIMBY reported.
ProjectA science building of more than 200,000 square feet on campus surface parking facing the Botanical Garden, backed by a $100 million gift from Maurice and Carolyn Dursi Cunniffe, the largest in Fordham’s history.
StatusIn Planning
Latest UpdateFordham described the building as in planning in November 2025. No DOB filing for it had been made as of late October 2026, and no architect or schedule has been published.
Fordham's Largest Gift
The university’s other current construction filings are alterations, including the Green Jobs Center in the next card.
Developer/ApplicantFordham University; Matiz Architecture and Design
ProjectConversion of a vacant Fordham Road storefront building into a green-economy training center of more than 12,000 square feet with classrooms and a cafe.
StatusUnder Construction
Latest UpdateFordham broke ground in July 2025, and the $4.1 million DOB alteration is fully permitted. Its builder lists a fall 2026 opening.
Training on Fordham Road
The site was formerly a billiard hall and carpet store.
ProjectTwo fully affordable buildings with 457 apartments in all, of 8 to 15 and 6 to 14 stories, across from the Bronx Zoo (ZAP, Bronx Times).
StatusRezoning Approved
Latest UpdateThe City Council approved the rezoning on Oct. 8, 2026, after City Planning’s August vote. No DOB new-building application has been filed.
Approved Over the Board's 'No'
Community Board 6 voted unanimously against the plan in May 2026, citing infrastructure, outreach and conditions at the existing Mapes Court, the Bronx Times reported. The board argued the district already leads the city in new affordable construction.
ProjectTwo new buildings of 13 and 10 stories with 452 apartments in all (DOB), the third phase of rebuilding the 1970s Lambert Houses. News 12 reported the five-phase program takes the complex from about 700 apartments to about 1,600.
StatusFiled (Plan Review)
Latest UpdatePhipps filed both new-building applications in March 2026, after demolition permits were issued in fall 2025. The 2075 Boston Road application was back in plan review on Oct. 13.
Rebuilding a 1970s Complex
News 12 reported Phase 3 is targeted around 2029. The affordability split has not been published.
Sources: News 12 Bronx (Jan. 2026); The Real Deal (Mar. 2026); NYC DOB NOW jobs X01369931 and X01356168 (Oct. 2026)
9
521 East Tremont Avenue
521 East Tremont Avenue, via Google Street View. —
Imagery: Google Street View
Developer/ApplicantMega Contracting Group and Community Access; SLCE Architects
ProjectA 14-story building with 213 affordable apartments, ground-floor retail and a health-care floor (DOB, SLCE); the 2020 rezoning described 205 units.
StatusUnder Construction
Latest UpdateA DOB inspector on Aug. 16, 2026 found the structure at the second floor with no work going on. Inspectors issued site-safety violations for scaffold netting and the sidewalk shed on Oct. 17 and 19, indicating the site was active again; no stop-work order was issued.
Paused, Then Active Again
Construction permits were issued between December 2025 and March 2026.
Developer/ApplicantRBA Developers; Fred Geremia, Architects & Planners
ProjectThree adjacent 15-story buildings with 99, 97 and 98 apartments (DOB), each kept just under 100 units.
StatusFiled (Plan Review)
Latest UpdateAll three applications have been in DOB objections since late 2025, with no permits. YIMBY and the Bronx Times reported the 4137 Third Avenue filing in October 2025.
Just Under 100
The trio is a clear example of the 90-to-99-unit pattern in the area’s filings.
Sources: New York YIMBY (Oct. 2025); Bronx Times (Oct. 2025); NYC DOB NOW jobs X01223350, X01228107 and X01223342 (Oct. 2025)
11
Zeta Tremont Park School (4263 Third Avenue)
Zeta Tremont Park School (4263 Third Avenue), via Google Street View. —
Imagery: Google Street View
Developer/ApplicantZeta Charter Schools; Michael Graves Architecture & Design
ProjectA six-story, 85-foot charter school building of about 80,000 square feet (DOB), described in the City Record as a school for about 630 students.
StatusUnder Construction
Latest UpdateDOB inspectors described exterior work under way in July 2026, and DOB issued standpipe and sprinkler permits on Oct. 19.
ProjectA rezoning of a manufacturing site for two buildings of 14 and 9 stories with 308 apartments and ground-floor commercial space, with mandatory affordable housing (ZAP).
StatusIn Public Review
Latest UpdateCity Planning certified the application on Sept. 9, 2026 and sent it to Community Board 6 on Sept. 18. The affordable share has not been published.
Developer/ApplicantNew York Botanical Garden; Weiss/Manfredi
ProjectA redesign of the Garden’s museum complex, the Mosholu entrance and welcome center, and a new education center (The Architect’s Newspaper).
StatusIn Design
Latest UpdateThe Garden selected Weiss/Manfredi in December 2025; no cost or timeline has been announced. Current DOB work is smaller: a new elevator shaft and a retaining wall.
A New Front Door for the Garden
The Garden’s grounds are a designated city landmark.
ProjectA rebuild of the Williams Bridge station with elevators and longer platforms, and elevator, platform and canopy work at Botanical Garden, part of a three-station Harlem Line package (MTA).
StatusUnder Construction
Latest UpdateThe MTA began work in June 2025. This is railroad work with no city building filing. The MTA’s 2025-29 plan separately prioritizes accessibility upgrades at the Fordham Road, 182-183 Streets, Norwood-205 Street and West Farms Square subway stations, which have not started.
Elevators on the Harlem Line
The third station in the package, Woodlawn, is outside this area.
NYCHA Northwest Bronx Renovations, via Google Street View. —
Imagery: Google Street View
Address/Location2070 Clinton Avenue, Twin Parks East, one of eight developments
Developer/ApplicantNYCHA, with the Arker Companies, Dabar Development Partners and SBV RE Investments
ProjectA $593.7 million renovation of 1,669 apartments in 14 buildings across eight developments: new heating and hot water, elevators, façades, kitchens and bathrooms (NYCHA).
StatusUnder Construction
Latest UpdateNYCHA announced in June 2025 that the private partners had taken over with about two years of construction ahead. The work is not tied to a single DOB filing.
1,669 Apartments Renovated
The bundle includes two sites in Kingsbridge Heights.
Fordham Landing South’s financing and its commercial rezoning, building filings for Sojourner Truth–Mapes, permits for 2768 Webster Avenue and the Fordham dormitory, the opening of the Green Jobs Center and public review of 4506 Park Avenue are next. Smaller items include a rezoning application at 3210 Webster Avenue in Norwood and a new aviary building filed at the Bronx Zoo.
The Kingsbridge Armory and Kingsbridge Heights west of the Jerome Park Reservoir are covered on Hush Street’s Kingsbridge & Riverdale tracker, and 1959 Jerome Avenue on the Melrose, Concourse & Highbridge tracker.
Header photo: the Metro-North station entrance at Fordham Plaza, 2020, by Beyond My Ken, via Wikimedia Commons, CC BY-SA 4.0.