Development Tracker — SoHo, NoHo & Hudson Square

What's Being Built in SoHo, NoHo & Hudson Square? The 2021 Rezoning's First Towers, the End of the Elizabeth Street Garden Fight & a Tenantless Office Tower

Hush Street tracks what's changing in SoHo, NoHo and Hudson Square: the first towers approved under the 2021 rezoning at 277 Canal, 375 Lafayette, 257 Canal and 56 Great Jones, the end of the Elizabeth Street Garden fight, the 156-166 Bowery rezoning and Hudson Square's Trinity Church sites.
15
Projects Tracked
~3,000
Homes Projected by the 2021 Rezoning
4
Landmarks Approvals in 2026
2
Under Construction
Oct. 2026
Updated
Watch → 3 Open DOB Violations 1 Housing Plan Canceled
What’s Changing
→
A foundation filing for a 25-story building followed the garage conversion application at 360 West Broadway.Oct. 2026
→
Landmarks unanimously approved 257 Canal Street, with 88 permanently affordable apartments.Sep. 2026
→
The Haven Green developers dropped their lawsuit, leaving the Elizabeth Street Garden in place.Aug. 2026
Under Construction2
Pre-Construction8
Proposed or In Review3
Built, Not Yet Open1
Canceled1
See full project list →

Hush Street is tracking what’s being built in Manhattan’s SoHo, NoHo and Hudson Square.

The SoHo/NoHo rezoning adopted in December 2021 replaced 1970s manufacturing rules with mixed-use zoning and mandatory affordable housing; the city projected about 3,000 new homes, roughly 900 of them permanently affordable (6sqft). More than three years later, Village Preservation counted no new homes completed. 2026 is when approvals finally arrived: the Landmarks Preservation Commission cleared towers at 277 Canal Street, 375 Lafayette Street and 257 Canal Street and a cantilever for 56 Great Jones Street, and The Marq at 126 Lafayette Street topped out.

On the Bowery, the decade-long fight over the Elizabeth Street Garden ended in August when the Haven Green developers dropped their lawsuit and moved their project to the Lower East Side, while a related rezoning at 156-166 Bowery entered city review. In Hudson Square, Trinity Church ground-lease sites are moving toward housing, and the speculative One Grand office tower still has no tenant.

Where DOB records and press reports disagree on heights or unit counts, both are given. A permit is not treated as proof that construction has started.

Project Location Status
1277 Canal Street Canal St. at Broadway Landmarks-Approved
2375 Lafayette Street Lafayette St. at Great Jones St. Landmarks-Approved
3257 Canal Street Canal St., Lafayette–Broadway Landmarks-Approved
456 Great Jones Street Great Jones St. at the Bowery Demolition Filed
5The Marq (126 Lafayette Street) Lafayette St. at Howard St. Topped Out
6360 West Broadway / 30-32 Thompson Street West Broadway at Grand St. Filed (Plan Review)
7298 Bowery Bowery near Houston St. Filed (Plan Review)
827 East 4th Street E. 4th St., Lafayette–Bowery Landmarks Review
9156-166 Bowery Rezoning Bowery at Delancey St. Rezoning Filed
10Elizabeth Street Garden Elizabeth St., Prince–Spring Housing Plan Canceled
11Chobani House (360 Bowery) Bowery at Great Jones St. Built; Not Yet Open
12One Grand (76 Varick Street) Varick St. at Canal St. Filed; Not Yet Permitted
13122 Varick Street Varick St. at Dominick St. Announced
1468 King Street (185 Varick Street) Varick St. at King St. Demolition in Review
15Canal Street Pumping Station Reconstruction Canal St. at Duarte Square Under Construction

The Rezoning's First Towers

Most of these sites are in landmark districts, so the 2021 rezoning’s housing has had to pass Landmarks review one building at a time.

1

277 Canal Street

Google Street View of 277 Canal Street, New York, NY
277 Canal Street, via Google Street View. — Imagery: Google Street View
Address/Location277 Canal Street, northeast corner of Broadway
Developer/ApplicantUnited American Land; Morris Adjmi Architects
ProjectA 21-story, roughly 220-foot rental tower with 159 apartments, 31 of them affordable, built over the landmarked 1927 Oltarsh Building (YIMBY, Tribeca Citizen). The DOB filing still shows the earlier 13-story, 100-unit design.
StatusLandmarks-Approved
Latest UpdateLandmarks approved the revised design on July 28, 2026 and issued its letter on Aug. 5. The DOB application has been in objections since 2023.

Extra Height for a Subway Elevator

The added floors come from a Zoning for Accessibility bonus in exchange for rebuilding the Canal Street N/Q/R entrance with an elevator, Tribeca Citizen reported. The earlier 13-story version, approved in 2023, was the first Landmarks approval under the 2021 rezoning, according to YIMBY. The same owner is rebuilding the low buildings across Broadway at 419-423 Broadway.

Sources: Tribeca Citizen (Aug. 2026); New York YIMBY (July 2026); NYC Landmarks, LPC-26-01951 (Aug. 2026); NYC DOB NOW job M00820605-I1 (accessed Oct. 2026)

2

375 Lafayette Street

Google Street View of 375 Lafayette Street, New York, NY
375 Lafayette Street, via Google Street View. — Imagery: Google Street View
Address/Location375 Lafayette Street, a NoHo parking lot
Developer/ApplicantEdward J. Minskoff Equities with Edison Properties (YIMBY); Skidmore, Owings & Merrill
ProjectTwo rental buildings of 19 and 18 floors with up to 210 apartments, 55 to 65 of them affordable, on a parking lot in the NoHo Historic District Extension (6sqft).
StatusLandmarks-Approved
Latest UpdateLandmarks approved the revised two-building design on Aug. 18, 2026 by a 6-2 vote with one abstention. No DOB filing has been made yet.

Housing on a Parking Lot, After Two Tries

The 2021 rezoning allowed housing here for the first time. Community Board 2 voted against the plan, and Landmarks tabled it in March before approving the split design, which 6sqft reported keeps each building under the 485-x wage thresholds.

Sources: 6sqft (Aug. 2026); New York YIMBY (Feb. 2026); Village Preservation (Feb. 2026)

3

257 Canal Street

Google Street View of 257 Canal Street, New York, NY
257 Canal Street, via Google Street View. — Imagery: Google Street View
Address/Location257 Canal Street
Developer/ApplicantAlembic Community Development and The Children’s Village; BKSK Architects
ProjectA 20-story building with 88 permanently affordable apartments, about 60% of them supportive housing for young adults aging out of foster care, plus retail and a social services floor (YIMBY).
StatusLandmarks-Approved
Latest UpdateLandmarks unanimously approved the building on Sept. 15, 2026 (6sqft, The Real Deal). No DOB filing has been made yet.

All-Affordable Housing in SoHo

The project is funded through HPD’s supportive housing loan program with city rental vouchers, according to YIMBY, and replaces a 1925 two-story commercial building.

Sources: New York YIMBY (Sept. 2026); The Real Deal (Sept. 2026); 6sqft (Sept. 2026)

4

56 Great Jones Street

Google Street View of 56 Great Jones Street, New York, NY
56 Great Jones Street, via Google Street View. — Imagery: Google Street View
Address/Location56 Great Jones Street
Developer/ApplicantLonicera Partners (YIMBY, PincusCo); Fogarty Finger
ProjectA 25-story, 275-foot condo tower with up to 94 apartments, including about 30 affordable under mandatory inclusionary housing, replacing the former Bowery Market site and two Bowery buildings (YIMBY). DOB lists 26 stories and 88 units.
StatusDemolition Filed
Latest UpdateLandmarks approved an 8-foot cantilever over 354 Bowery on April 7, 2026 (PincusCo). Demolition applications for the existing buildings were filed July 31, 2026 and are in plan review; the new building is in DOB objections.

An As-of-Right Tower With One Landmarks Question

The tower itself is allowed under the 2021 rezoning; Landmarks only had to rule on the cantilever over the neighboring historic building. Village Preservation, which opposed it, describes a 300-foot tower.

Sources: New York YIMBY (Feb. 2026); PincusCo (Apr. 2026); NYC DOB NOW jobs M01335408-I1 and M01426874-I1 (accessed Oct. 2026)

5

The Marq (126 Lafayette Street)

Google Street View of 126 Lafayette Street, New York, NY
The Marq (126 Lafayette Street), via Google Street View. — Imagery: Google Street View
Address/Location126 Lafayette Street
Developer/ApplicantHigh Street Residential (Trammell Crow Company); Marvel
ProjectA 25-story, 275-foot rental building with 99 apartments, 25 of them affordable at a blended 60% of area median income, and ground-floor retail.
StatusTopped Out
Latest UpdateThe building topped out in September 2026, with completion targeted for late 2027 (YIMBY). City inspectors issued three serious safety violations on Sept. 25, 2026, which remain open.

The First New Rental to Rise

Trammell Crow’s residential arm took a 99-year ground lease on the site, paying $14.7 million, YIMBY reported. No stop-work order has been issued.

Sources: New York YIMBY (Sept. 2026); NYC DOB NOW job M08022114-I1 and ECB records (accessed Oct. 2026)

6

360 West Broadway / 30-32 Thompson Street

Google Street View of 360 West Broadway, New York, NY
360 West Broadway / 30-32 Thompson Street, via Google Street View. — Imagery: Google Street View
Address/Location360 West Broadway
Developer/ApplicantMadigan Development; Hill West Architects
ProjectConversion and enlargement of a two-story parking garage into a 24-story residential building with 80 apartments, on a lot merged with 30-32 Thompson Street (DOB). Earlier filings for the Thompson Street buildings, still open, show different heights and unit counts.
StatusFiled (Plan Review)
Latest UpdateThe conversion application filed in July 2026 is in DOB plan review, and a foundation filing for a 25-story concrete building followed on Oct. 23.

Rent-Regulated Apartments Lost

DOB vacated the garage in October 2024 over spalling concrete. Village Preservation reported that the walk-ups at 30-32 Thompson Street held rent-regulated apartments that were demolished after the rezoning.

Sources: NYC DOB NOW job M01409218 (Oct. 2026); Commercial Observer (Dec. 2024); Village Preservation (May 2025)

7

298 Bowery

Google Street View of 298 Bowery, New York, NY
298 Bowery, via Google Street View. — Imagery: Google Street View
Address/Location298 Bowery
Developer/ApplicantPaul Yam; A&T Engineering
ProjectA vertical enlargement of a four-story building to 12 stories with 31 apartments (DOB; YIMBY and Crain’s reported 42).
StatusFiled (Plan Review)
Latest UpdateThe application has been in DOB objections since July 2, 2025, with no permits issued.

Twelve Stories on the Bowery

The existing building’s lower floors would stay, so no demolition is planned, YIMBY reported.

Sources: New York YIMBY (June 2025); NYC DOB NOW job M01200710-I1 (accessed Oct. 2026)

8

27 East 4th Street

Google Street View of 27 East 4th Street, New York, NY
27 East 4th Street, via Google Street View. — Imagery: Google Street View
Address/Location27 East 4th Street, next to the Merchant’s House Museum
Developer/ApplicantKalodop II Park Corp.; DXA Studio
ProjectA nine-story mixed-use building of about 105 feet with community facility and retail space, replacing a one-story garage next to the 1832 Merchant’s House Museum (6sqft, Village Preservation).
StatusLandmarks Review
Latest UpdateLandmarks took up the proposal again on Sept. 29, 2026 but deferred its vote until an engineering review is complete (6sqft).

A Fight Next to a House Museum

The Merchant’s House Museum says construction could permanently damage the landmark, and Community Board 2 opposed the plan.

Sources: 6sqft (Sept. 2026); Village Preservation (Sept. 2026); NYC DOB NOW job M01355281-I1 (accessed Oct. 2026)

The Bowery & the Elizabeth Street Garden

A garden saved, the housing it would have held moved elsewhere, and a rezoning on the Bowery that was part of the deal.

9

156-166 Bowery Rezoning

Google Street View of 160 Bowery, New York, NY
156-166 Bowery Rezoning, via Google Street View. — Imagery: Google Street View
Address/Location156-166 Bowery
Developer/ApplicantKinsmen Property Group; Kohn Pedersen Fox and Beyer Blinder Belle (YIMBY)
ProjectA rezoning for mixed-income housing including at least 123 affordable apartments for seniors. City Planning’s description is one 27-story building with 357 units, 89 of them income-restricted; YIMBY described three buildings with 322 homes, including 124 senior affordable apartments.
StatusRezoning Filed
Latest UpdateThe application has been at the pre-certification stage at City Planning since Sept. 4, 2026, with a milestone on Oct. 15 (ZAP 2026M0108). YIMBY said formal public review should start by the end of 2026.

Part of the Garden Deal

The site was the first named in the June 2025 agreement between the city and Council Member Christopher Marte that set aside the Elizabeth Street Garden housing plan in exchange for housing elsewhere, according to the Mayor’s Office. The seven buildings on the site were demolished in 2024.

Sources: NYC Planning ZAP 2026M0108; New York YIMBY (Sept. 2026); NYC Mayor's Office (June 2025)

10

Elizabeth Street Garden

Google Maps of Elizabeth Street Garden, Elizabeth Street, New York, NY
The Elizabeth Street Garden, via Google Maps. — Imagery: Google Maps
Developer/ApplicantFormerly Pennrose, RiseBoro Community Partnership and Habitat for Humanity (Haven Green), on HPD-owned land
ProjectHaven Green, a seven-story building of 123 affordable apartments for seniors approved in 2019, will not be built on the garden. The garden is to remain public green space.
StatusHousing Plan Canceled
Latest UpdateIn August 2026 the Haven Green developers dropped their lawsuit under a settlement that moves the project to a city-owned lot at 22 Suffolk Street on the Lower East Side (NY1, YIMBY).

A Decade-Long Fight Ends

Under the June 2025 agreement, the garden must stay open from 8 a.m. to 8 p.m. daily and could become NYC Parks property, the Mayor’s Office said. Sources differ on which administration ended the plan: NY1 says the Adams administration did so shortly before leaving office, while a New York Times headline credits Mayor Zohran Mamdani. YIMBY reported that land-use review for 22 Suffolk Street, planned for more than 180 homes, is expected to begin in mid-2027.

Sources: Spectrum News NY1 (Aug. 2026); New York YIMBY (Sept. 2026); The New York Times (Aug. 2026); NYC Planning ZAP P2018M0251

11

Chobani House (360 Bowery)

Google Street View of 360 Bowery, New York, NY
Chobani House (360 Bowery), via Google Street View. — Imagery: Google Street View
Address/Location360 Bowery
Developer/ApplicantCBSK Ironstate with AECOM-Canyon Partners; Morris Adjmi Architects
ProjectA finished 22-story, roughly 121,000-square-foot office building leased in full to Chobani as its headquarters.
StatusBuilt; Not Yet Open
Latest UpdateThe Real Deal reported in August 2026 that Chobani House had not opened. DOB issued interior fit-out permits on Sept. 11 and 15, 2026.

A Headquarters Still Waiting

Chobani’s lease announced in fall 2024 targeted an opening in late 2025. The new fit-out permits cover several floors, but no report has confirmed that work has resumed.

Sources: The Real Deal (Aug. 2026); NYC DOB NOW jobs M01299086-I1, M01299130-I1, M01299136-I1 (Sept. 2026)

Hudson Square

West of Sixth Avenue, a tenantless office tower, Trinity Church ground-lease sites turning to housing, and a pump station rebuild under Canal Street.

12

One Grand (76 Varick Street)

Google Street View of 76 Varick Street, New York, NY
One Grand (76 Varick Street), via Google Street View. — Imagery: Google Street View
Address/Location76 Varick Street
Developer/ApplicantTaconic Partners and Nuveen Real Estate, on a Trinity Church ground lease; SHoP Architects
ProjectA 27-to-28-story, roughly 430,000-square-foot office tower with a 444-seat public elementary school in its base, required by the 2013 Hudson Square rezoning.
StatusFiled; Not Yet Permitted
Latest UpdateTaconic said in August 2026 that it does not need an anchor tenant to start construction, which would take about 36 months, according to Hoodline citing the New York Post. The DOB application has been in objections since 2022.

Speculative Office, Built Around a School

The tower would fill the triangular block next to Duarte Square. No tenant has been announced after a year of marketing.

Sources: New York Post (Aug. 2026); Hoodline (Aug. 2026); NYC DOB NOW job M00749905-I1 (accessed Oct. 2026)

13

122 Varick Street

Google Street View of 122 Varick Street, New York, NY
122 Varick Street, via Google Street View. — Imagery: Google Street View
Address/Location122 Varick Street
Developer/ApplicantGlobal Holdings and MAG Partners, on a Trinity Church ground lease
ProjectA 149-unit rental building of about 192,000 square feet, with roughly 25% permanently affordable under 485-x and more than 5,000 square feet of retail, on an open parking lot (YIMBY, Commercial Observer).
StatusAnnounced
Latest UpdateThe partners announced the project in spring 2026. No DOB filing has been made yet.

Trinity Land Turns to Housing

Global Holdings’ own page describes a 23-story tower; neither YIMBY nor Commercial Observer has published a height.

Sources: New York YIMBY (May 2026); Commercial Observer (Apr. 2026)

14

68 King Street (185 Varick Street)

Google Street View of 185 Varick Street, New York, NY
68 King Street (185 Varick Street), via Google Street View. — Imagery: Google Street View
Address/Location68 King Street, filed as 185 Varick Street
Developer/ApplicantAvdoo & Partners Development
ProjectA planned luxury residential building of about 200,000 square feet replacing a six-story office building, with design team not yet announced (6sqft).
StatusDemolition in Review
Latest UpdateThe application to demolish the existing building returned to DOB objections on Oct. 2, 2026, after a sidewalk shed and a related demolition permit were issued in August.

A $63 Million Site

Avdoo closed on the site for $63 million in December 2025, The Real Deal reported, and plans to add purchased development rights and a transit-improvement bonus, according to 6sqft.

Sources: 6sqft (Jan. 2026); The Real Deal (Dec. 2025); NYC DOB NOW job M01359182 (accessed Oct. 2026)

15

Canal Street Pumping Station Reconstruction

Google Maps of Duarte Square, Canal Street, New York, NY
Duarte Square on Canal Street, where the pump station is being rebuilt, via Google Maps. — Imagery: Google Maps
Address/LocationCanal Street at Sullivan Street, Duarte Square
Developer/ApplicantNYC Department of Environmental Protection
ProjectReconstruction of the 1930 pump station that sends SoHo and Hudson Square wastewater and stormwater toward the Newtown Creek treatment plant, to improve its resiliency and end lane closures on Canal Street during maintenance.
StatusUnder Construction
Latest UpdateThe city’s capital projects dashboard keeps the project in construction and has pushed completion to Sept. 15, 2028, citing pending permits and unforeseen site conditions; DEP had earlier estimated August 2026.

Infrastructure Under Canal Street

DOB has permitted about $22.7 million of sewer and utility work and $4.1 million of below-grade structures for the project.

Sources: NYC capital projects data (via NYC Databook) (May 2026); Hudson Square BID (information from DEP) (Oct. 2024)

What We're Watching Next

DOB filings for 375 Lafayette Street and 257 Canal Street, an amended filing for 277 Canal Street, the start of public review for 156-166 Bowery, and the Landmarks vote on 27 East 4th Street are next. Smaller projects include a 10-story building planned at 285 Hudson Street and the rebuilding of the corner buildings at 419-423 Broadway, where demolition was nearly finished in July.

Hush Street also tracks Tribeca south of Canal Street, the Lower East Side, where the Haven Green housing is moving, and the East Village.

Header photo: cast-iron buildings at Spring Street in SoHo, August 2025, by Kidfly182, via Wikimedia Commons, CC BY 4.0.

By Updated Built from city filings and published reporting. About Hush Street