What's Being Built in Richmond Hill, Ozone Park & Howard Beach? A Casino Expansion at Aqueduct, the Jewel Streets Plan & a Flood Study for Hamilton Beach
Hush Street tracks what's changing in Richmond Hill, Ozone Park, Lindenwood and Howard Beach: Resorts World's expansion and the Aqueduct site's future, the Jewel Streets plan and two approved rezonings, Jamaica Hospital's new emergency department and Howard Beach's flood study.
12
Projects Tracked
~100
Acres of Aqueduct Land Being Planned
~540
Apartments in 2026 Lindenwood Rezonings
3
Under Construction
Oct. 2026
Updated
Watch →Hamilton Beach Buyouts ProposedCasino Work on State Land
By Hush Street Editorial
What’s Changing
→
Jamaica Hospital opened the first phase of its emergency department expansion.Oct. 2026
→
City Council review of the 135-27 Sapphire Street rezoning closed with approval.Oct. 2026
→
The Army Corps released a draft flood study proposing Hamilton Beach buyouts.Sep. 2026
South Queens is mostly low-rise and changes slowly, so its biggest projects are concentrated in two places. At Aqueduct, Resorts World New York City won state approval for a full casino in December 2025 and in July 2026 began the next phase of an expansion that includes a second hotel tower and a 7,000-seat arena, the New York Post reported. Next door, horse racing has ended and the state is drawing up a plan for about 100 acres of its land.
In Lindenwood’s low-lying Jewel Streets, the city’s neighborhood plan calls for new sewers and up to 5,000 homes, and the City Council approved two private rezonings in 2026 for about 540 apartments. Along Jamaica Avenue, Jamaica Hospital opened the first phase of its emergency department expansion in October 2026. In Howard Beach, flooding dominates: an Army Corps draft study released in September proposes voluntary buyouts in Hamilton Beach as a first step.
Where DOB records and press reports disagree on sizes, costs or dates, both are given. A permit is not treated as proof that construction has started.
Developer/ApplicantGenting Americas (Resorts World New York City)
ProjectAn expansion of the casino at the former Aqueduct grandstand into a full resort, including a second 400-room Hyatt tower, a Crockfords hotel and a 7,000-seat arena (New York Post). The New York Post reported a roughly $5 billion plan; the company describes $5.5 billion of physical investment within a $7.5 billion proposal.
StatusUnder Construction
Latest UpdateThe state’s casino siting board approved the bid on Dec. 1, 2025 (Resorts World), live table games opened in April 2026, and the company launched the next construction phase on July 22, 2026 (New York Post).
A Casino on State Land
The license fee is given as $600 million by the company and $500 million by the New York Post. Because the site is state land, the work does not appear in city building records; milestones here come from the company and press.
ProjectA master plan for about 100 acres of state land at Aqueduct, now that racing has moved to the rebuilt Belmont Park; options include housing, retail, community facilities and open space (amNewYork).
StatusIn Planning
Latest UpdateGov. Kathy Hochul launched the planning process on May 5, 2026, with workshops through the end of 2026 and a master plan expected in early 2027. Environmental review, approvals and a request for proposals would follow before any construction (amNewYork).
After the Last Race
The New York Racing Association says live racing has ended at Aqueduct.
Developer/ApplicantNYC Department of Housing Preservation and Development, with DEP, DOT and DDC
ProjectA plan for the low-lying area known as ‘The Hole’ calling for up to 5,000 homes, about 3,600 through an area-wide rezoning and up to 1,400 on a 17-acre city-owned site, plus new sewers, a pump station and bluebelts (Mayor’s Office). The area straddles Queens and Brooklyn’s East New York.
StatusIn Planning
Latest UpdateThe city released the final plan on Oct. 21, 2025, with over $146 million in infrastructure and the area-wide rezoning’s public review expected to begin in 2026 (Mayor’s Office).
Fixing 'The Hole'
The city first announced about $75 million for the area’s infrastructure in 2023, Gothamist reported; the 2025 plan raised that to over $146 million. Which side of the borough line the 17-acre city site is on has not been confirmed.
ProjectAffordable and senior housing on a shopping-center site. City Planning’s description is one 11-story building with 273 apartments; the Queens Chronicle reported two buildings of six and 12 stories with 267 income-restricted apartments, 97 of them for seniors, financed by HPD as 100 percent affordable.
StatusRezoning Approved
Latest UpdateThe City Council approved the rezoning after a Feb. 3, 2026 hearing, where the applicant said it was in line for HPD financing (Queens Chronicle; ZAP). No building application has been filed.
A Walgreens Lot Becomes Housing
It is on the same block as the 135-27 Sapphire Street site.
Developer/ApplicantSam Zirkiev (135 Sapphire LLC); Dan Russo (architect)
ProjectA six-story, 65-foot rental building with 268 apartments, 67 of them income-restricted, and a 118-car garage on a vacant lot (ZAP, YIMBY).
StatusRezoning Approved
Latest UpdateCity Council review ran from Sept. 22 to Oct. 22, 2026, and City Planning’s records now list the rezoning as approved (ZAP). YIMBY published a new rendering in September and described the site as rezoned in June. No building application has been filed.
A Garage in a Flood Zone
The design is meant to work with the city’s plan to raise Sapphire Street, YIMBY reported.
Developer/ApplicantJamaica Hospital Medical Center; RBSD Architects; Barr & Barr
ProjectA $150 million expansion of the emergency department and critical care, funded by a state grant (Governor’s Office). The state and press describe a three-story, 48,534-square-foot addition; the DOB filing lists a five-story enlargement and renovation covering 111,504 square feet.
StatusUnder Construction
Latest UpdateThe hospital opened the first phase, about 15,000 square feet with 22 critical-care beds, in October 2026, and the full expansion is due in early 2027 (QNS).
A Bigger Trauma Center
DOB has also approved, but not permitted, a separate filing for a cancer treatment center with a rooftop addition at the hospital’s 90-28 Van Wyck building.
Sources: QNS (Oct. 2026); Office of the Governor (June 2023); NYC DOB NOW jobs Q08033272-I1 and Q01238257-I1 (2026)
8
New School at 120-30 Jamaica Avenue
New School at 120-30 Jamaica Avenue, via Google Street View. —
Imagery: Google Street View
Developer/ApplicantNYC School Construction Authority; Dattner Architects
ProjectA four-story, 108,865-square-foot school building that keeps parts of the existing structures (DOB). The authority bought the site for a new elementary school.
StatusApproved
Latest UpdateDOB approved the authority’s filing; no work permit has been issued as of the latest status in March 2026.
Developer/ApplicantGunnveet Sandhu (owner of record); Michael Kang Architect
ProjectA five-story community-facility building with sleeping accommodations and 129 units in DOB records.
StatusUnder Construction
Latest UpdateDOB issued foundation, excavation, structural and construction permits in August and September 2026, and an Oct. 13 inspection found an active excavation site with a pile drill.
Excavation Under Way
In April 2026 DOB cited the removal of a two-story building on the lot without a demolition permit.
Sources: NYC DOB NOW job Q01160326-I1 and permits (Sept. 2026); NYC DOB/ECB records (BIN 4618450) (Oct. 2026)
10
114-20 Jamaica Avenue
114-20 Jamaica Avenue, via Google Street View. —
Imagery: Google Street View
Developer/ApplicantU.S. Army Corps of Engineers, with New York State DEC
ProjectA coastal storm risk study for the northern shore of Jamaica Bay (Army Corps).
StatusDraft Study
Latest UpdateThe Army Corps released a draft study on Sept. 17, 2026. Its first proposed step is voluntary buyouts of vulnerable Hamilton Beach homes, with flood walls and barriers left for further study (Queens Chronicle).
Buyouts Before Walls
The study has no construction funding. A nor’easter on Sept. 26, 2026 flooded Hamilton Beach and Howard Beach again, the Queens Chronicle reported.
ProjectA rezoning to allow a four-story hotel and spa and a five-story residential building beside the catering hall on Shellbank Basin (ZAP). The New York Business Journal described three buildings.
StatusPre-Certification
Latest UpdateThe application is still in early review at City Planning; the environmental assessment was refiled through June 2026 and new special-permit actions were added (ZAP).
Construction at Resorts World, the Aqueduct master plan in early 2027, the Jewel Streets rezoning’s public review, building applications for the two Lindenwood rezonings, the full opening of Jamaica Hospital’s emergency department and the final Army Corps study are next.