Hush Street is tracking what’s being built in Downtown Jamaica, around Jamaica Station, the AirTrain and the Jamaica and Archer Avenue corridors.
The City Council approved the Jamaica Neighborhood Plan on Oct. 29, 2025, rezoning about 230 blocks and mapping the city’s largest mandatory inclusionary housing area. The approved framework projects 11,829 new homes, and the Council said nearly 4,200 would be permanently affordable, along with $413 million in negotiated community investments.
Large towers were already arriving at the transit hub before the rezoning, and the filings have grown since: a 37-story, 600-unit plan at Jamaica Station, nine buildings with 863 apartments on 95th Avenue and six 12-story buildings on the 165th Street mall. Public projects are reshaping the area too, from the MTA’s rebuilt electric bus depot to a new public high school that opened in September 2026.
Where DOB records and press reports disagree on heights or unit counts, both are given. A permit is not treated as proof that construction has started.
| Project | Location | Status |
|---|---|---|
| 1Jamaica Neighborhood Plan | About 230 blocks around Jamaica Center | Rezoning Adopted |
| 2147-27 Archer Avenue | Archer Ave. at 147th Pl. | Filed (Plan Review) |
| 3Nine Buildings on 95th–97th Avenues | 95th–97th Aves., 149th–150th Sts. | Filed (Plan Review) |
| 4165th Street Assemblage | 165th St. mall, Jamaica–89th Aves. | Filed (Plan Review) |
| 5164-02 Jamaica Avenue | Jamaica Ave. at 164th St. | Filed (Plan Review) |
| 6161-09 and 161-10 Hillside Avenue | Hillside Ave. at 161st St. | Filed (Plan Review) |
| 7159-31 90th Avenue | 90th Ave. at 160th St. | Filed (Plan Review) |
| 8148-15 Archer Avenue | Archer Ave. at 149th St. | Filed (Plan Review) |
| 993-47 Sutphin Boulevard | Sutphin Blvd. at the AirTrain | Stalled |
| 10Archer Towers II (163-25 Archer Avenue) | Archer Ave., 165th St.–Guy R. Brewer Blvd. | Under Construction |
| 1189-26 162nd Street | 162nd St., Jamaica–89th Aves. | Under Construction |
| 1294-09 and 94-11 148th Street | 148th St. near 94th Ave. | Under Construction |
| 13Success Academy High School (153-10 Hillside Avenue) | Hillside Ave. at 153rd St. | Under Construction |
| 14Jamaica Bus Depot | South Rd. near York College | Under Construction |
| 1594-15 Sutphin Boulevard | Sutphin Blvd. at 95th Ave. | Completed |
| 16Sutphin Senior Residence (97-04 Sutphin Boulevard) | Sutphin Blvd. at 97th Ave. | Completed |
| 17Jamaica Central and Tower 162 | 162nd St., Jamaica–90th Aves. | Completed |
| 18Q497 High School (165-15 88th Avenue) | 88th Ave. at 165th St. | Completed |
The Rezoning & the Big New Plans
The 2025 rezoning, the towers filed since, and one hotel site that has waited a decade.
1
Jamaica Neighborhood Plan
$413 Million in Promises
The Council said it negotiated $413 million in community investments, including a hospital expansion, a new public health center, two parks and a STEAM center.
Sources: NYC Planning ZAP 2023Q0381; New York City Council (Oct. 2025); Queens Eagle (Oct. 2025); Cozen O'Connor (Oct. 2025)
2
147-27 Archer Avenue
The Tallest Plan in Jamaica
Press reports conflict on the site’s recent ownership, and the current developer has not been confirmed. The vacant lot sits next to The Crossing at Jamaica Station.
Sources: NYC DOB NOW job Q00676542-I1 (Sept. 2026); New York YIMBY (Dec. 2024); Marketproof
3
Nine Buildings on 95th–97th Avenues
Among the First Big Rezoning Filings
The same owner built the completed 94-15 Sutphin Boulevard tower nearby.
Sources: PincusCo (Aug. 2026); NYC DOB NOW new-building filings on block 10002 (Oct. 2026)
4
165th Street Assemblage
Six Buildings on the Mall
Another developer has filed three more 12-story buildings on 164th and 165th Streets nearby.
Sources: New York YIMBY (July 2025); NYC DOB NOW jobs Q01243880-I1 and related filings (Mar. 2026)
5
164-02 Jamaica Avenue
A Supportive Housing Tower
Communilife bought the three buildings on the site for $13.5 million, YIMBY reported.
Sources: New York YIMBY (June 2026); NYC DOB NOW job Q01367014-I1 (Oct. 2026)
6
161-09 and 161-10 Hillside Avenue
An Award Before Groundbreaking
YIMBY listed the north building as 161-05 Hillside Avenue with a smaller floor area than the DOB filing.
Sources: QNS (Oct. 2026); New York YIMBY (Oct. 2026); NYC DOB NOW jobs Q01289631-I1 and Q01289649-I1 (Oct. 2026)
7
159-31 90th Avenue
Housing With a Sanctuary Inside
Haussmann took over a stalled ground-lease project on the church’s land, The Real Deal reported.
Sources: The Real Deal (Aug. 2025); New York YIMBY (Aug. 2025); NYC DOB NOW job Q01233524-I1 (Oct. 2026)
8
148-15 Archer Avenue
Supportive Housing at the Station
No construction timeline has been announced.
Sources: New York YIMBY (Nov. 2025); NYC DOB NOW job Q01274353-I1 (Nov. 2025)
9
93-47 Sutphin Boulevard
A Decade-Old Hotel Plan
The new zoning could let the site be redeveloped differently.
Sources: QNS (Nov. 2024); NYC DOB BIS job 420654786 (accessed Oct. 2026)
Under Construction
An all-affordable tower, mid-rise rentals, a charter high school and the MTA’s electric bus depot.
10
Archer Towers II (163-25 Archer Avenue)
A $303 Million Loan
BRP closed a $303 million construction loan, YIMBY reported in January 2026. It is BRP’s fourth Jamaica development.
Sources: New York YIMBY (Jan. 2026); Urbanize NYC; NYC DOB NOW job Q01118133-I1 (Aug. 2026)
11
89-26 162nd Street
Across From Its Finished Sibling
The same group’s Jamaica Central, across the street, was finished in 2026. A June 2026 violation cited a plywood sheet falling onto a neighboring site.
Sources: New York YIMBY (Apr. 2022); NYC DOB NOW job Q00721236-I1 and ECB records (Oct. 2026)
12
94-09 and 94-11 148th Street
Earthwork Under Way
The sites are a block from the Sutphin Boulevard rail hub.
Sources: NYC DOB NOW jobs Q01278129-I1 and Q01295343-I1 (Oct. 2026); NYC DOB/ECB violations (Sept. 2026)
13
Success Academy High School (153-10 Hillside Avenue)
A Charter High School on Hillside
Success Academy has not announced an opening date or seat count for the building.
Sources: Queens Chronicle (Mar. 2023); NYC DOB NOW job Q01220686-I1 (Oct. 2026)
14
Jamaica Bus Depot
An All-Electric Depot
Buses have been parked at a temporary lot near York College during construction.
Sources: MTA (Oct. 2026); Queens Chronicle (Apr. 2026); Skanska (Jan. 2023)
Finished in 2025 & 2026
A 524-unit tower at the AirTrain, senior housing, two mid-rise rentals and a new public high school.
15
94-15 Sutphin Boulevard
Big Towers at the Rail Hub
Its sister tower at 147-35 95th Avenue was finished in early 2025.
Sources: New York YIMBY (July 2025); 6sqft; NYC DOB NOW job Q00657653-I1 and CO records (Sept. 2026)
16
Sutphin Senior Residence (97-04 Sutphin Boulevard)
Senior Housing With a Clinic
The health center is run by Community Healthcare Network.
Sources: New York YIMBY (Sept. 2026); NYC DOB NOW job Q00641359-I1 and CO records (Sept. 2026)
17
Jamaica Central and Tower 162
A Stop-Work Order, Then Dismissed
DOB issued a stop-work order at 89-61 162nd Street in January 2026 over its intent to revoke an approval; it was later dismissed.
Sources: New York YIMBY (July 2026); New York YIMBY (Mar. 2026); NYC DOB CO and violation records (Oct. 2026)
18
Q497 High School (165-15 88th Avenue)
A New School Opens
It serves grades 9 through 12.
Sources: Patch (Sept. 2026); Queens Chronicle (Sept. 2026); NYC DOB NOW job Q00687157-I1 and CO records (Aug. 2026)
What We're Watching Next
Permits for the 147-27 Archer Avenue tower and the nine 95th Avenue buildings, demolition on the 165th Street mall, the start of construction at 164-02 Jamaica Avenue and the Hillside Avenue pair, the bus depot’s completion and the first projects funded by the rezoning’s $413 million in community investments are next.
Header photo: new towers over Jamaica Avenue at 149th Street, Downtown Jamaica, 2022, by Tdorante10, via Wikimedia Commons, CC BY-SA 4.0.
By Hush Street Editorial Updated Built from city filings and published reporting. About Hush Street