Grand Central Terminal with the MetLife Building behind it, seen from East 40th Street
Development Tracker — Midtown East

What's Being Built in Midtown East? A Citadel Supertall, Office Towers Becoming 5,000 Apartments & the Pfizer Conversion That Buckled

Hush Street tracks what's changing in Midtown East: new office towers around Grand Central under the 2017 rezoning, the 350 Park Avenue supertall, 11 office-to-apartment conversions with more than 5,000 homes in city filings, and the stalled former Pfizer headquarters.
18
Projects Tracked
5,000+
Homes in Conversion Filings
9
Under Construction
7
Pre-Construction
Oct. 2026
Updated
Watch → 1 Halted (Column Failure)
What’s Changing
→
Ken Griffin, Vornado and Rudin closed a $3.3 billion construction loan for the 350 Park Avenue supertall, targeting 2032.Oct. 2026
→
SL Green filed the new-building application for 346 Madison Avenue after DOB permitted demolition of the old building.Oct. 2026
→
Two columns buckled inside the former Pfizer headquarters on East 42nd Street, halting the neighborhood's largest conversion.Jul. 2026
343 Madison Avenue Construction loan (BXP)$1.2B
6 East 43rd Street Conversion loan (YIMBY)$300M
1011 First Avenue Conversion loan (Vanbarton)$250M
845 Third Avenue Bridge loan (TRD)$88M
See full project list →

Hush Street is tracking what’s being built in Manhattan’s Midtown East.

Two very different booms are happening at once. Around Grand Central and Park Avenue, the 2017 Greater East Midtown rezoning is producing a new generation of office towers, led by a Citadel-anchored supertall at 350 Park Avenue that bought air rights from St. Patrick’s Cathedral and St. Bartholomew’s Church. A few blocks east, older office buildings on Third, Lexington and First Avenues are being converted into apartments: the 11 conversions on this page add up to more than 5,000 homes in Department of Buildings filings.

The conversion wave has also produced the neighborhood’s most alarming story of 2026. In July, two columns buckled inside the former Pfizer headquarters on East 42nd Street, halting the largest conversion here, and weeks later DOB briefly stopped steel work at 750 Third Avenue.

Where DOB records and press reports disagree on heights or unit counts, both are given. A permit is not treated as proof that construction has started.

Project Location Status
1Former Pfizer Headquarters (219-235 East 42nd Street) 235 E. 42nd St. Halted After Column Failure
2750 Third Avenue 750 Third Ave. Under Construction
36 East 43rd Street 6 E. 43rd St. Under Construction
4675 Third Avenue 675 Third Ave. Under Construction
51011 First Avenue First Ave. at E. 55th St. Under Construction
6Tower 57 (135 East 57th Street) 135 E. 57th St. Under Construction
7845 Third Avenue 845 Third Ave. Under Construction
8767 Third Avenue Third Ave. at E. 48th St. Permitted
9355 Lexington Avenue Lexington Ave. at E. 40th St. Permitted
10830 Third Avenue Third Ave. at E. 50th St. Permitted
11300 East 42nd Street 300 E. 42nd St. Under Construction
12350 Park Avenue (Citadel Headquarters) Park Ave. at E. 51st St. Demolition Permitted
13343 Madison Avenue Madison Ave. at E. 45th St. Under Construction
14346 Madison Avenue Madison Ave. at E. 44th St. Demolition Permitted
15415 Madison Avenue Madison Ave. at E. 48th St. Approved; Site Cleared
16Beekman (401 East 51st Street) First Ave. at E. 51st St. Topped Out
17250 East 56th Street Second Ave. at E. 56th St. Demolition Permitted
18New Providence (225 East 45th Street) 225 E. 45th St. Completed (2026)

Office Buildings Becoming Apartments

Eleven conversions on and around Third Avenue, from the stalled Pfizer complex to a former Archdiocese headquarters on First Avenue.

1

Former Pfizer Headquarters (219-235 East 42nd Street)

Google Street View of 235 East 42nd Street, New York, NY
Former Pfizer Headquarters (219-235 East 42nd Street), via Google Street View. — Imagery: Google Street View
Address/Location235 East 42nd Street, and 219 East 42nd Street
Developer/ApplicantMetro Loft Management and David Werner Real Estate Investments; Gensler, architect
ProjectConversion of the former Pfizer headquarters complex into apartments, with floors added to both buildings. DOB filings list 927 units at 235 East 42nd Street and 481 at 219 East 42nd Street, 1,408 in all; a city Comptroller table lists 1,600.
StatusHalted After Column Failure
Latest UpdateTwo columns buckled on the 21st floor on July 7, 2026, forcing evacuations (ENR). DOB ordered a structural peer review and forensic investigation and issued further violations through Sept. 11. On Oct. 15, The New York Times reported that work to lift the damaged floors was set to begin.

The Conversion That Shook the Boom

No one was hurt when the columns buckled, ENR reported, but the failure froze the surrounding area for nearly three weeks, and later reporting by The New York Times found that eight more columns needed repair and that steel reinforcing plates were missing. The city had not announced a cause as of the reporting Hush Street reviewed.

The same developers are converting 675 Third Avenue on the same block, which has no stop-work order in DOB records.

Sources: NYC DOB NOW jobs M01075133-I1 and M01075131-I1; DOB violations for BIN 1037552 (accessed Oct. 2026); ENR (July 2026); The New York Times, via GV Wire (Aug. 2026); The New York Times (Oct. 2026)

2

750 Third Avenue

Google Street View of 750 Third Avenue, New York, NY
750 Third Avenue, via Google Street View. — Imagery: Google Street View
Address/Location750 Third Avenue
Developer/ApplicantSL Green Realty; Gensler, architect
ProjectConversion of a 34-story office building into apartments, a quarter of them affordable per YIMBY. Unit counts differ: DOB lists 609, YIMBY and The New York Times 639, and The Real Deal and Commercial Observer 680.
StatusUnder Construction
Latest UpdateDOB issued structural, plumbing and sprinkler permits between Sept. 11 and 16, 2026, after a partial stop-work order on steel work was issued July 28 and rescinded two days later.

Paused for Two Days

DOB halted structural steel work on the ninth floor and above on July 28 over welding that did not match the filed plans, then lifted the order after a re-inspection, The Real Deal reported. YIMBY reported in August that demolition began in October 2025 and steel work was underway, with a total project cost of $805 million. The Real Deal also reported that SL Green has been marketing a 65% stake in the project.

Sources: NYC DOB NOW job M01197450-I1; ECB violation, BIN 1036207 (accessed Oct. 2026); The Real Deal (July 2026); New York YIMBY (Aug. 2026)

3

6 East 43rd Street

Google Street View of 6 East 43rd Street, New York, NY
6 East 43rd Street, via Google Street View. — Imagery: Google Street View
Address/Location6 East 43rd Street, near Fifth Avenue and Grand Central
Developer/ApplicantVanbarton Group; Gensler, architect
ProjectConversion and expansion of a 27-story office building into 440 apartments (DOB; YIMBY says 441, 111 of them affordable). DOB lists 36 proposed stories; YIMBY described five new floors.
StatusUnder Construction
Latest UpdateDOB issued sprinkler and standpipe permits on Oct. 13, 2026, after renewing the general construction, structural and mechanical permits in August. YIMBY reported occupancy anticipated in spring 2027.

A $300 Million Brookfield Loan

Vanbarton bought the building for $135 million and closed a $300 million loan from Brookfield, according to YIMBY and the developer. It is one of two Vanbarton conversions on this page, along with 1011 First Avenue, and the company is also converting 77 Water Street in the Financial District.

Sources: NYC DOB NOW job M01297210-I1 (accessed Oct. 2026); New York YIMBY (Nov. 2025); Vanbarton Group

4

675 Third Avenue

Google Street View of 675 Third Avenue, New York, NY
675 Third Avenue, via Google Street View. — Imagery: Google Street View
Address/Location675 Third Avenue
Developer/ApplicantMetro Loft Management and David Werner Real Estate Investments; Gensler, DOB applicant
ProjectConversion of an office building into apartments, expanded by four floors. DOB lists 450 units and 34 stories; The Real Deal and YIMBY report 464 units and 35 stories.
StatusUnder Construction
Latest UpdateDOB issued a mechanical permit on Oct. 23, 2026, after renewing the general construction permit in August. YIMBY reported a sidewalk shed and window removal, with occupancy slated for the second quarter of 2027.

Next Door to the Pfizer Site

675 Third Avenue shares a block and a development team with the halted former Pfizer headquarters. The project took a $90 million acquisition and predevelopment loan from Northwind in 2025, The Real Deal reported. DOB records reviewed by Hush Street show no stop-work order here.

Sources: NYC DOB NOW job M01259040-I1 (accessed Oct. 2026); The Real Deal (Sept. 2025); New York YIMBY (June 2026)

5

1011 First Avenue

Google Street View of 1011 First Avenue, New York, NY
1011 First Avenue, via Google Street View. — Imagery: Google Street View
Address/Location1011 First Avenue, between East 55th and 56th Streets
Developer/ApplicantVanbarton Group; CetraRuddy Architecture
ProjectConversion of the former Archdiocese of New York headquarters into 420 apartments, 105 of them affordable, with six floors added (Vanbarton). DOB lists 417 units and 27 stories.
StatusUnder Construction
Latest UpdateDOB renewed the general construction and structural permits on July 21 and 22, 2026. YIMBY reported in May that crews were working across the building, with completion expected in summer 2027.

The Archdiocese's Former Home

The building served as the Archdiocese’s headquarters from 1973. Vanbarton closed a $250 million loan from Eldridge for the conversion, which also includes about 8,000 square feet of retail.

Sources: NYC DOB NOW job M01216837-I1 (accessed Oct. 2026); Vanbarton Group; New York YIMBY (May 2026)

6

Tower 57 (135 East 57th Street)

Google Street View of 135 East 57th Street, New York, NY
Tower 57 (135 East 57th Street), via Google Street View. — Imagery: Google Street View
Address/Location135 East 57th Street, at Lexington Avenue
Developer/ApplicantTF Cornerstone, on a ground lease; CetraRuddy Architecture
ProjectConversion of a 32-story office tower into rental apartments. DOB lists 369 units; 6sqft, Multi-Housing News and YIMBY report 350, a quarter of them affordable under the 467-m program per 6sqft.
StatusUnder Construction
Latest UpdateA structural amendment entered DOB plan review on Oct. 9, 2026. YIMBY reported in May that crews were tearing up the building’s old plaza, with completion projected for April 2028.

A Conversion on 57th Street

The 467-m tax incentive that several of these projects use requires a quarter of the apartments to be affordable at an average of 80% of area median income, according to 6sqft. Tower 57 was filed under a newer DOB category for buildings rebuilt around existing elements, which is one reason it is easy to miss in permit searches.

Sources: NYC DOB NOW job M01304547-I1 (accessed Oct. 2026); 6sqft (Aug. 2025); New York YIMBY (May 2026)

7

845 Third Avenue

Google Street View of 845 Third Avenue, New York, NY
845 Third Avenue, via Google Street View. — Imagery: Google Street View
Address/Location845 Third Avenue, between East 51st and 52nd Streets
Developer/ApplicantFiled by Rudin Management; Quantum Pacific (75% equity partner) and Metro Loft per The Real Deal; CetraRuddy Architecture
ProjectConversion of a 21-story office building, expanded to 24 stories in DOB records, into apartments. The count is unsettled: DOB lists 398, Rudin’s original filing 411, and The Real Deal reported in March 2026 that it had been raised to 529.
StatusUnder Construction
Latest UpdateDOB renewed the general construction permit on Oct. 16, 2026. YIMBY reported work progressing in May.

A Change of Control

The Real Deal reported an $88 million bridge loan from Bank Hapoalim to Quantum Pacific and Metro Loft in March and said Rudin appears to be moving away from ownership. That shift has not yet shown up in a public property record, so both are named here.

Sources: NYC DOB NOW job M01277486-I1 (accessed Oct. 2026); The Real Deal (Mar. 2026); New York YIMBY (May 2026)

8

767 Third Avenue

Google Street View of 767 Third Avenue, New York, NY
767 Third Avenue, via Google Street View. — Imagery: Google Street View
Address/Location767 Third Avenue
Developer/ApplicantMetro Loft Management and Quantum Pacific; Fogarty Finger, DOB applicant
ProjectConversion of a 40-story, 1980 office tower into 337 apartments, keeping about 45,800 square feet of commercial space (Commercial Observer).
StatusPermitted
Latest UpdateDOB renewed the general construction permit on July 30, 2026. Commercial Observer reported a $169.5 million construction loan from BHI in June 2026.

The Tallest Conversion on Third Avenue

At 40 stories, this is the tallest building in the Third Avenue conversion group. A Metro Loft document mentions a $220 million construction loan, which Hush Street has not reconciled with the $169.5 million reported by Commercial Observer.

Sources: NYC DOB NOW job M01237433-I1 (accessed Oct. 2026); Commercial Observer (Aug. 2025); Commercial Observer (June 2026)

9

355 Lexington Avenue

Google Street View of 355 Lexington Avenue, New York, NY
355 Lexington Avenue, via Google Street View. — Imagery: Google Street View
Address/Location355 Lexington Avenue, filed as 133 East 40th Street
Developer/ApplicantRudin Management; Hill West Architects, DOB applicant
ProjectConversion of a 22-story Emery Roth & Sons office building, enlarged by four floors, into 297 apartments plus retail (Rudin, YIMBY). DOB lists 25 stories.
StatusPermitted
Latest UpdateCrain’s reported on Sept. 17, 2026 that Rudin landed $175 million in financing for the conversion. DOB issued Turner Construction’s structural permit on July 16, 2026.

Rudin's Lexington Avenue Conversion

The financing combines a $139 million building loan with about $35.8 million more, according to Crain’s. YIMBY’s last site visit predates the main permits, so Hush Street lists this as permitted rather than under construction.

Sources: NYC DOB NOW job M01277491-I1 (accessed Oct. 2026); Crain's New York Business (Sept. 2026); Rudin

10

830 Third Avenue

Google Street View of 830 Third Avenue, New York, NY
830 Third Avenue, via Google Street View. — Imagery: Google Street View
Address/Location830 Third Avenue
Developer/ApplicantNamdar Realty Group and Empire Capital Holdings; Basic Groups Corp, DOB applicant
ProjectConversion of a 13-story office building (14 stories in DOB records) into 188 rental apartments, mostly studios.
StatusPermitted
Latest UpdateDOB issued sprinkler permits on Aug. 26, 2026, after general construction and structural permits in the spring. A $93.5 million construction loan closed in January 2026 (Multi-Housing News).

A Studio-Heavy Conversion

According to Yield Pro, 124 of the 188 apartments will be studios and 60 one-bedrooms, a much smaller unit mix than most of the conversions here.

Sources: NYC DOB NOW job M01109601-I1 (accessed Oct. 2026); Multi-Housing News; Yield Pro (Jan. 2026)

11

300 East 42nd Street

Google Street View of 300 East 42nd Street, New York, NY
300 East 42nd Street, via Google Street View. — Imagery: Google Street View
Address/Location300 East 42nd Street
Developer/ApplicantCSC Real Estate; Tang Studio Architect, DOB applicant
ProjectPartial conversion of an 18-story office building: the ground floor and floors 6 through 18 become 133 apartments (DOB; Multi-Housing News and YIMBY say 135).
StatusUnder Construction
Latest UpdateDOB issued mechanical and general construction permits on Sept. 1, 2026. YIMBY reported interior work underway behind a sidewalk shed in June.

A Partial Conversion

CSC bought the office portion of the building in 2025 and took a $45 million loan for the work, according to YIMBY.

Sources: NYC DOB NOW job M01254875-I1 (accessed Oct. 2026); Multi-Housing News (Apr. 2025); New York YIMBY (June 2026)

New Towers, a Supertall & a New Shelter

Office towers rising on Park and Madison under the 2017 rezoning, two new condo and rental towers farther east, and a completed shelter with supportive housing.

12

350 Park Avenue (Citadel Headquarters)

Google Street View of 350 Park Avenue, New York, NY
350 Park Avenue (Citadel Headquarters), via Google Street View. — Imagery: Google Street View
Address/Location350 Park Avenue
Developer/ApplicantJoint venture of a Ken Griffin/Citadel affiliate, Vornado Realty Trust and Rudin; Foster + Partners (design), AAI Architects (DOB applicant)
ProjectA new office supertall replacing the existing 31-story tower and two smaller buildings. DOB lists 62 stories, 1,413 feet and about 2.08 million square feet; the New York Post says about 1,400 feet and ENR about 1,600 feet.
StatusDemolition Permitted
Latest UpdateThe partners closed their joint venture and a $3.3 billion construction loan, with completion estimated for 2032, the New York Post reported on Oct. 21, 2026. DOB issued the demolition permit for the existing tower on July 29.

The Rezoning's Biggest Test

The project won its Greater East Midtown approvals in September 2025 (ZAP 2024M0321), buying unused development rights from St. Patrick’s Cathedral and St. Bartholomew’s Church. The Post reported that the deal includes $150 million for landmark maintenance and more than $35 million for the East Midtown Public Realm Improvement Fund.

The new-building application is still in DOB plan review. Citadel’s planned headquarters is a block from JPMorgan Chase’s new 270 Park Avenue, which Hush Street tracks separately, as it does 245 Park Avenue.

Sources: NYC DOB NOW jobs M01297618-I1 and M01297566-I1 (accessed Oct. 2026); NYC Planning ZAP 2024M0321; New York Post (Oct. 2026); ENR (Feb. 2026)

13

343 Madison Avenue

Google Street View of 343 Madison Avenue, New York, NY
343 Madison Avenue, via Google Street View. — Imagery: Google Street View
Address/Location343 Madison Avenue, the former MTA headquarters site
Developer/ApplicantBXP (formerly Boston Properties), in partnership with the MTA; Kohn Pedersen Fox
ProjectA 46-story, 782-foot office tower of about 930,000 square feet next to Grand Central (DOB lists 47 stories). The New York Post put the project cost at $2 billion.
StatusUnder Construction
Latest UpdateThe New York Post reported on Oct. 11, 2026 that construction had reached the podium level, with completion set for 2029. DOB renewed the excavation-support permit on Oct. 20.

Half Leased Before It Tops Out

Starr and the law firm McDermott Will & Schulte have leased about half the building, according to the Post, and BXP secured a $1.2 billion construction loan in July. Turner Construction holds the foundation, structural and general construction permits.

Sources: NYC DOB NOW job M00615380-I1 (accessed Oct. 2026); New York Post (Oct. 2026); BXP (Business Wire) (July 2026); NYC Planning ZAP 2026M0218

14

346 Madison Avenue

Google Street View of 346 Madison Avenue, New York, NY
346 Madison Avenue, via Google Street View. — Imagery: Google Street View
Address/Location346 Madison Avenue, the former Brooks Brothers flagship site
Developer/ApplicantSL Green Realty and Mori Building; Kohn Pedersen Fox
ProjectA 46-floor office tower of about 850,000 rentable square feet, replacing the 11-story 346 Madison Avenue and the 18-story 11 East 44th Street (SL Green). The first DOB new-building filing lists only 20 stories and about 331,000 square feet, which may be an early-stage scope.
StatusDemolition Permitted
Latest UpdateDOB issued the demolition permit for 346 Madison Avenue on Oct. 13, 2026, and SL Green filed the new-building application on Oct. 20. The New York Post reported completion targeted for the third quarter of 2031.

Across the Street From 343 Madison

SL Green and Japan’s Mori Building formed a joint venture for the tower, which will face BXP’s 343 Madison across the avenue. Demolition of the second building, 11 East 44th Street, is approved but not yet permitted.

Sources: NYC DOB NOW jobs M01451684-I1 and M01412252-I1 (accessed Oct. 2026); SL Green; New York Post (May 2026)

15

415 Madison Avenue

Google Street View of 415 Madison Avenue, New York, NY
415 Madison Avenue, via Google Street View. — Imagery: Google Street View
Address/Location415 Madison Avenue
Developer/ApplicantRudin Management; Skidmore, Owings & Merrill (design, per YIMBY)
ProjectA planned 40-story, 605-foot office tower of about 343,000 square feet on a cleared site.
StatusApproved; Site Cleared
Latest UpdateRudin’s application to renew the project’s two Greater East Midtown special permits recorded a filing milestone with City Planning on Oct. 9, 2026 (ZAP 2026M0275). The new-building application filed in 2022 is still in DOB objections.

Approved, Cleared and Waiting

Demolition of the old building finished in April 2023, YIMBY reported. More than three years later the tower has not started, and Rudin is renewing the special permits it won in 2022, a sign the project is still waiting for the right moment rather than moving into construction.

Sources: NYC Planning ZAP 2026M0275; NYC DOB NOW job M00759520-I1 (accessed Oct. 2026); Rudin; New York YIMBY (Apr. 2023)

16

Beekman (401 East 51st Street)

Google Street View of 401 East 51st Street, New York, NY
Beekman (401 East 51st Street), via Google Street View. — Imagery: Google Street View
Address/Location401 East 51st Street
Developer/ApplicantSK Development and CB Developers; SLCE Architects, DOB applicant
ProjectA 29-story, 335-foot condominium tower with 83 residences on a six-story podium.
StatusTopped Out
Latest UpdateYIMBY reported on May 13, 2026 that the tower had topped out, with facade installation underway and completion slated for fall 2027.

A New Condo at the Edge of Beekman Place

One of the few ground-up condo towers in the neighborhood, Beekman sits at First Avenue at the gateway to Turtle Bay and Beekman Place. CityRealty also lists completion for fall 2027.

Sources: NYC DOB NOW job M00951363-I1 (accessed Oct. 2026); New York YIMBY (May 2026); CityRealty

17

250 East 56th Street

Google Street View of 250 East 56th Street, New York, NY
250 East 56th Street, via Google Street View. — Imagery: Google Street View
Address/Location250 East 56th Street
Developer/ApplicantEJS Group with Krown Point Capital; Hill West Architects
ProjectA 36-story residential tower with 141 apartments and about 192,000 square feet, replacing three four-story buildings on Second Avenue.
StatusDemolition Permitted
Latest UpdateDOB issued demolition permits for the three existing buildings in August 2026, and City Planning and the MTA completed a Second Avenue transit-easement certification on Sept. 18, 2026 (ZAP 2025M0473). The new-building application is in DOB objections.

Clearing a Second Avenue Corner

The new building’s application does not yet list a height; Marketproof’s summary of the filing puts it at 406 feet. CityRealty lists the project as a condominium, which neither the developer nor a primary record has confirmed.

Sources: NYC DOB NOW jobs M01370073-I1 and M01301215-I1 (accessed Oct. 2026); NYC Planning ZAP 2025M0473; Marketproof

18

New Providence (225 East 45th Street)

Google Street View of 225 East 45th Street, New York, NY
New Providence (225 East 45th Street), via Google Street View. — Imagery: Google Street View
Address/Location225 East 45th Street
Developer/ApplicantProject Renewal and Monadnock Development, on a city-owned site
ProjectA 21-story, 217-foot building combining a 171-bed women’s shelter with 130 permanently affordable and supportive apartments and an on-site clinic, about 133,000 square feet.
StatusCompleted (2026)
Latest UpdateDOB issued an initial certificate of occupancy on Aug. 3, 2026.

Supportive Housing in Midtown

New Providence went through the city’s land-use review in 2022 (ZAP 2021M0234) as a disposition of city land, and it is one of the few new homes for lower-income New Yorkers in this part of Manhattan. DOB records list 131 dwelling units on the new-building job and 149 on the certificate of occupancy; the developers describe 130 supportive and affordable apartments plus the shelter.

Sources: NYC DOB certificate of occupancy, job 121253785 (Aug. 2026); NYC Planning ZAP 2021M0234; Project Renewal; New York Housing Conference

What We're Watching Next

The cause of the column failure at the former Pfizer headquarters, and whether it changes how DOB oversees conversions, is the story to watch, along with when 350 Park Avenue’s new building clears plan review. Sites without plans yet include Extell’s 110 East 55th Street assemblage, where a demolition application was filed in August, and Vornado’s 3 East 54th Street, bought for $141 million in January.

Hush Street also tracks individual Midtown East projects, including 383 Madison Avenue, 625 Madison Avenue and the LVMH Tower at 19 East 57th Street. Downtown, the Financial District is going through its own office-to-apartment wave.

Header photo: Grand Central Terminal and East 40th Street, November 2025, by Kidfly182, via Wikimedia Commons, CC BY 4.0, resized.

By Updated Built from city filings and published reporting. About Hush Street