What’s Being Built in Park Slope? New Developments & Public Realm Projects to Watch

A landmarked brownstone core generates almost no development of its own — Park Slope’s real story is a five-project building wave along Fourth Avenue, plus public-realm plans for Grand Army Plaza and Fifth Avenue.
7
Projects Tracked
2
Under Construction
2
Pre-Construction
Oct. 2026
Updated
What’s Changing
→
Goose Property Management bought the Arrow Linen site for $55 million and filed plans to expand it to four 10-story buildings (396 units, up from the approved 250) — a configuration that avoids the 485-x construction-wage-floor threshold.Sept. 2026
→
A construction-fence permit was issued at 67-75 Fourth Avenue, the first confirmed sign of physical site activity on the 14-story, 99-unit building, following April 2026 demolition.Jul. 2026
→
Public workshops for the Grand Army Plaza redesign began, with Landmarks and Public Design Commission review continuing through the summer.Apr. 2026
370 19th St. Financing$11M
369 7th Ave. Acquisition$5M
See recent property activity →

Hush Street is tracking what’s changing in Park Slope — a neighborhood whose landmarked brownstone core generates almost no development activity of its own, and whose real story is happening on its edges. Fourth Avenue, the wide mixed-use boulevard that Park Slope’s historic district doesn’t touch, is in the middle of a genuine building wave: five projects, well over 500 new homes between them. Separately, two public-realm plans — one for Grand Army Plaza, one for Fifth Avenue’s whole commercial spine — are moving through early city planning stages.

We also found a rezoning that took two years and a scaled-down compromise to settle, and at least one unresolved factual discrepancy we’re not pretending to have an answer for. Both are below rather than smoothed over.

ProjectLocationStatus
1Arrow Linen Rezoning441-467 Prospect AvenueSold / New Plans Filed
267-75 Fourth Avenue67-75 Fourth Ave.Under Construction
385 Fourth Avenue / Solace85 Fourth Ave.Under Construction
4Paseo on Fifth50-55 Paseo PlaceCompleted
5Kay’s Place487 4th AvenueCompleted
6Grand Army Plaza RedesignGrand Army PlazaProposal / Public Review
7Fifth Avenue Vision PlanFifth Avenue, neighborhood-widePlanning

The Projects Reshaping Fourth Avenue and Park Slope’s Public Realm

Five buildings on one corridor, and two plans to redesign how the neighborhood moves.

1

Arrow Linen Rezoning

467 Prospect Avenue in June 2022, when Arrow Linen still operated the site. The company sold the assemblage in September 2026; a demolition/construction fence permit has since been issued. — Imagery: Google Street View
Address/Location441-467 Prospect Avenue, Park Slope/Windsor Terrace border
Developer/ApplicantGoose Property Management (Yitzchok Katz); architect Hamish Whitefield Architects, confirmed on all four current DOB filings
ProjectExpanded to four 10-story residential buildings, 396 units total (99 per building); affordable-unit count disputed, see below
StatusSold / New Plans Filed
Latest UpdateGoose Property Management bought the site for $55 million on Sept. 29, 2026, after filing plans to expand the project from two buildings to four; a local Council Member disputes that the new plan honors the original affordability deal

A Compromise Two Years in the Making

The Arrow Linen site — a working industrial laundry on Prospect Avenue — didn’t arrive at “two 10-story buildings” cleanly. Early reporting in August 2023 described a nine-story concept. By the time a formal rezoning application entered public review, it had grown into two 13-story towers with roughly 244 apartments, 25% of them affordable.

That version drew sustained opposition from Park Slope and Windsor Terrace residents, who argued it was out of scale with the surrounding three-story row houses. A group even sued the city, seeking to delay the land-use review until after the mayor’s citywide “City of Yes for Housing” rezoning was decided, on the theory that it could unlock an even bigger building on the same site.

What actually passed, after Borough President Reynoso backed a scaled-down version and the City Council negotiated further, is smaller than either earlier figure: two 10-story buildings, with affordability raised to 40% of units at an average of 60% of area median income (roughly 100 of 250 units). A signed Community Benefits Agreement adds a green roof, flood mitigation measures, and a local-hiring partnership with 32BJ SEIU.

Ownership Changes, and the Plan Grows

Arrow Linen, founded in Brooklyn in 1947 by Sicilian immigrant Ambrogio Magliocco, stepped back from developing the site itself after his son and successor, John Ambrose Magliocco, died in May 2026 at 96. The remaining shareholders first brought in another firm, Apex Development, then sold the approved, assembled site outright: Yitzchok Katz’s Goose Property Management paid $55 million for 441-467 Prospect Avenue on September 29, 2026, in a deal brokered by JLL.

Before the sale closed, Goose had already filed plans in August 2026 to expand the project to four 10-story buildings with 99 units each — 396 units total, up from the approved 250 — a configuration that appears designed to avoid New York’s 485x construction-wage-floor requirement, which only applies to buildings of 100 units or more.

What that means for affordability is a genuine, currently unresolved dispute rather than a settled fact. The Real Deal reported Goose intends roughly 100 affordable units (about 25% of 396, down from the approved 40%), with negotiations “ongoing.” Commercial Observer, reporting a day earlier, said it remains unclear whether the new plan increases or decreases the affordable count at all. Goose’s own statement says its plan “fully honors the commitments made to the community,” while Council Member Shahana Hanif, whose district includes the site, said in a statement that “a change in ownership does not erase the commitments made to the Windsor Terrace community” and that she remains committed to 40% affordability, a mix of bedroom sizes, and on-site community facility space. We’re preserving this as an open discrepancy rather than picking a side.

What Happens Next

A construction-fence permit (DOB Job B01422694-I1) was issued July 1, 2026, the first confirmed sign of physical site activity — predating the ownership change, and likely tied to Apex’s earlier site-prep work rather than Goose’s expanded plan. Goose has since filed all four new-building applications for the expanded plan (DOB jobs B01434691, B01427446, B01434126, B01434190, filed July 29–30, 2026) — all four currently carry open DOB plan-exam objections, meaning none is yet cleared for construction. That approval, and the resolution of the affordability dispute above, are the project’s next real milestones.

For the full ownership history, the exact building-by-building filing details, and the 485-x wage-floor mechanics behind the four-building redesign, see Hush Street’s Spotlight on the Arrow Linen redevelopment.

Sources: The Real Deal; Brownstoner; NYC Council; Brooklyn Paper; The Real Deal; Commercial Observer

2

67-75 Fourth Avenue

67 Fourth Avenue in November 2024 — before demolition. The buildings pictured are no longer standing; demolition finished in April 2026. — Imagery: Google Street View
Address/Location67-75 Fourth Avenue, plus 77 St. Marks Place
Developer/ApplicantShimon Kleinman / Borough Developers; Kao Hwa Lee Architects
Project14-story, 99-unit residential building, ~5,872 sq ft commercial
StatusUnder Construction
Latest UpdateDemolition complete as of April 2026; a DOB application (Job B01249173) has been on file since July 2025

Five Parcels, One Buyer

The site is an assembly: five separate parcels along Fourth Avenue and St. Marks Place, bought individually by Brooklyn businessman Tolib Mansurov between 2020 and 2022 for a combined roughly $19 million. In mid-2025, Mansurov sold the assembled site to Shimon Kleinman, affiliated with Williamsburg-based Borough Developers, who filed for the 14-story building that July.

Demolition of the existing low-rise structures finished in April 2026. Vertical construction on the new 145-foot building hadn’t been reported as of our last check.

Sources: New York YIMBY; Crain’s New York Business; Brooklyn Eagle

3

85 Fourth Avenue / Solace

85 Fourth Avenue in November 2024, during construction. The building has since been marketed as "Solace." — Imagery: Google Street View
Address/Location85 Fourth Avenue, aka 74 St. Marks Place
Developer/ApplicantStretke Corp.; Harry Einhorn
ProjectMixed-income rental building, permit-era count of 193 units
StatusUnder Construction
Latest UpdateMarketed as “Solace,” with an open affordable-housing lottery; completion targeted for summer 2026

What We Couldn’t Pin Down

This building’s own numbers don’t agree with each other. Permit-era reporting from New York YIMBY — which cites detailed square-footage breakdowns — puts it at 193 units across 13 stories. The building’s own marketing, for the completed project branded “Solace,” advertises 247 “thoughtfully crafted residences.” A 2019 permit filing described an earlier, 12-story version of the same address; a 2026 lottery announcement’s headline called it 18 stories.

We’re not picking a winner. None of these figures reconciles cleanly to a single primary Department of Buildings record we could find, and it’s plausible the project was genuinely revised more than once between 2019 and now. We’re using the 13-story, 193-unit figures in this piece because they come with the most detailed sourcing, not because we’ve confirmed them as final.

A Real Lottery, Whatever the Final Count

What is confirmed: an affordable-housing lottery is open now, with units set aside for households earning 40%, 60%, and 130% of area median income — studios starting at $992 a month, two-bedrooms up to $4,518. Completion is targeted for summer 2026.

Sources: New York YIMBY; Patch; 6sqft

4

Paseo on Fifth

Address/Location50-55 Paseo Place, between 5th Ave., Baltic St., and Gregory Place
Developer/ApplicantWilliam Macklowe Company (developer); SLCE Architects
Project180 rental units across two buildings, plus a 25,000 sq ft Lidl
StatusCompleted
Latest UpdateConstruction complete on both buildings as of June 2026

Grocery as Amenity

Paseo on Fifth is two buildings — six stories at 55 Paseo Place, four at 50 Paseo Place — separated by a landscaped pedestrian corridor on a 1.8-acre site. Together they add 180 rental units and 45,000 square feet of commercial and retail space, anchored by a 25,000-square-foot Lidl supermarket the developer has marketed as a defining amenity rather than an afterthought.

We couldn’t find a freely licensed image of the finished buildings and aren’t using a stand-in; the site’s own coverage (linked below) has current photos.

Sources: New York YIMBY; developer press releases via PR Newswire

5

Kay’s Place

Address/Location487 4th Avenue
Developer/ApplicantProcida Companies (developer); Aufgang Architects
Project44-unit affordable rental building, avg. 864 sq ft units
StatusCompleted
Latest UpdateConstruction complete as of July 2026

Housing With a Specific Purpose

Kay’s Place is smaller than the other buildings on this list, but its program is unusual: ten of the 44 units are one-bedroom apartments set aside for residents with developmental disabilities, and a further portion is reserved for people who were formerly homeless. It’s the kind of project that doesn’t generate a rezoning fight or a permit-count discrepancy, but represents real, targeted housing capacity the neighborhood didn’t have before.

As with Paseo on Fifth, we didn’t find a freely licensed photo of the completed, occupied building and aren’t substituting a stand-in image.

Sources: New York YIMBY

Park Slope, Visually

Five numbers behind the two tracks.

View full sizeDownload PNG
Copy embed code
View full sizeDownload PNG
Copy embed code
View full sizeDownload PNG
Copy embed code
View full sizeDownload PNG
Copy embed code
View full sizeDownload PNG
Copy embed code

Free to embed with attribution and a link to Hush Street.

6

Grand Army Plaza Redesign

The Soldiers' and Sailors' Memorial Arch at Grand Army Plaza, Brooklyn
The Soldiers’ and Sailors’ Memorial Arch at Grand Army Plaza, the monument the redesign would connect directly to Prospect Park. Photo by Ad Meskens via Wikimedia Commons, CC BY-SA 3.0.
Address/LocationGrand Army Plaza, at Prospect Park West, Flatbush Ave., Eastern Parkway & Union St.
Developer/ApplicantNYC Department of Transportation; NYC Mayor’s Office
ProjectPedestrian plaza connecting the Memorial Arch to Prospect Park; 42% more public space
StatusProposal / Public Review
Latest UpdatePublic workshops began April 23, 2026; feedback accepted through May 31, with Community Board presentations in May and Landmarks/Public Design Commission review over the summer

Untangling One of Brooklyn’s Most Dangerous Intersections

Grand Army Plaza sits at the convergence of Union Street, Flatbush Avenue, Eastern Parkway, and Prospect Park West — Park Slope’s own boundary street runs directly into it. Mayor Mamdani and DOT Commissioner Mike Flynn unveiled a proposal in April 2026 to eliminate that convergence’s confusing road geometry, connecting the Soldiers’ and Sailors’ Memorial Arch and Bailey Fountain to Prospect Park in a single pedestrian plaza.

The stakes are concrete: the plaza’s roadways saw 219 traffic injuries between 2021 and 2025. The redesign would cut pedestrian crossings from 39 to 24 and add roughly three-quarters of an acre of public space, a 42% expansion, while speeding up the B41 bus.

The idea itself isn’t new — it revives a two-decade-old advocacy proposal — but this is the first time it’s carried mayoral and DOT backing. Earlier 2024 outreach found more than 85% of roughly 3,600 survey respondents in favor of better connecting the plaza to the park.

What Happens Next

This is a proposal, not an approved plan. Public workshops ran through late April 2026, with feedback accepted through May 31; DOT is expected to present to local Community Boards in May, with Landmarks Preservation Commission and Public Design Commission review — both required given the plaza’s landmark status — over the summer.

One related piece is already under construction, not just proposed: DOT began rebuilding Flatbush Avenue itself from Livingston Street to Grand Army Plaza in late April 2026, adding center-running protected bus lanes (including for the B41 that runs through the plaza) and roughly 29,000 square feet of new pedestrian space, with work expected to continue into fall 2026.

Sources: NYC Mayor’s Office; Streetsblog NYC; CBS New York; New York YIMBY; NYC DOT (Flatbush Avenue reconstruction)

7

Fifth Avenue Vision Plan

Fifth Avenue near 9th Street — one stretch of the roughly 30-block corridor the vision plan covers. — Imagery: Google Maps
Address/LocationFifth Avenue, roughly 30 blocks south from Dean Street
Developer/ApplicantPark Slope Fifth Avenue BID; WXY Architecture and Urban Design; NYC DOT
ProjectWider sidewalks, safer intersections, green/stormwater infrastructure
StatusPlanning
Latest UpdateVision plan released October 2025; NYC DOT has received it and began its own Street Improvement Project planning process that fall

A Response to Real Flood Damage

The Park Slope Fifth Avenue BID, working with WXY Architecture and Urban Design and funded in part by a New York-Presbyterian Hospital community grant, released “Putting People First on Park Slope’s Fifth Avenue” in October 2025. The plan calls for wider sidewalks, safer intersections, less bus congestion, and expanded green stormwater infrastructure along the commercial corridor.

That last piece isn’t abstract: stormwater flooding damaged more than 30 small businesses along Fifth Avenue in 2023 alone, and the plan’s green-infrastructure proposals are a direct response.

NYC DOT has formally received the BID’s report and, that same fall, began its own Street Improvement Project planning process to advance implementation. No construction timeline has been announced. (One detail we’re not repeating as fact: a piece of secondary coverage described the study area’s southern end as “18th Street” and, separately, as being “in Bay Ridge” — the two don’t match geographically, and we haven’t traced the plan’s own document to confirm the precise boundary.)

Sources: The Architect’s Newspaper; Brooklyn Eagle; WXY Studio; Park Slope Fifth Avenue BID

Capital & Transactions

Money Moving in Park Slope

A curated look at recent property sales and financing that help explain who’s buying, building, and lending in Park Slope right now. Drawn from New York City’s public ACRIS property records, not a complete log of every filing — we include only transactions that say something real about the neighborhood’s direction, and leave out routine paperwork, internal transfers, and deals we can’t explain responsibly.

Financing$11M

370 19th StreetJul. 2026

Confirmed via Traded.co: Hirshmark Capital financed a development site and industrial buildings spanning the Park Slope/Sunset Park border, including this address, in a deal recorded July 2026 — a real, current capital event, though the site sits at the neighborhood’s own southern edge rather than its core.

Borrower: 370 19th Street LLC · Lender: Customers Bank · ACRIS record ↗

Acquisition + Financing$5M

369 7th AvenueSep. 2026

A confirmed September 2026 sale of a mixed-use building on Park Slope’s 7th Avenue commercial corridor (2 commercial units, 10 residential units), with same-day acquisition financing from Peapack Private Bank & Trust.

Seller: WECM 369 7th Ave PS LLC · Buyer: 369 7th LLC / Galeta Partners RE 369 LLC · Lender: Peapack Private Bank & Trust · ACRIS record ↗

Source: New York City’s public ACRIS property records. This module is reviewed and curated by Hush Street editors, not an automated feed, and will be updated as new, meaningful filings are confirmed.

Have a tip on a Park Slope project we should be tracking? Let us know.