The Gowanus Canal waterfront in Gowanus, Brooklyn
Development Tracker — Gowanus

What’s Being Built in Gowanus? New Developments, Rezonings & Public Projects to Watch

Tracking the towers, the stalled affordable megaproject, and the billion-dollar sewage-tank fix reshaping Gowanus, Brooklyn.
12
Projects Tracked
4,500+
Units Represented
6
Under Construction
3
Pre-Construction
Oct. 2026
Updated
Watch → 1 Behind Schedule 1 Unresolved
What’s Changing
→
Earthwork began on 175 Third Street, the Wharf plan’s largest building, after its $785M financing close.Oct. 2026
→
Ailanthus filed a rezoning application for 424 Hoyt Street — 400 units including a public school.Sept. 2026
→
213 Third Avenue’s construction financing confirmed: $38.5M, alongside an HPD affordability agreement.Jul. 2026
175 Third St. Financing$785M
213 Third Ave. Financing$38.5M
248–258 4th Ave. Assemblage$10.5M
604 Union St. Acquisition$11M
See recent property activity →

Hush Street is tracking what’s changing in Gowanus — the industrial valley along Brooklyn’s most infamous waterway, rezoned in 2021 to allow roughly 8,500 new apartments where auto shops and self-storage lots used to sit. Five years in, one developer alone has delivered two buildings and started leasing two more.

Jump Around

It just closed $785 million to start the largest building in the neighborhood’s history. A separate, fully affordable megaproject one canal crossing away is finally inching toward groundbreaking after two years frozen by a fight between the state and National Grid.

None of it matters much if the canal itself doesn’t get fixed first. The EPA’s Superfund cleanup running beneath all this new construction is now more than six years behind schedule and, per the agency’s own inspector general, over 1,000% above its original budget.

The city’s sewage-tank fix for the canal won’t be fully online until 2029. We cover the towers below, but we’re giving equal space to the tanks, a landmark bridge that just permanently changed, a neighborhood pool caught in the middle of the cleanup, and the public-housing repairs the rezoning itself promised — because underneath and around the canal is arguably the bigger Gowanus story right now, not just what’s rising beside it.

A Note on Gowanus’s BoundariesGowanus’s edges are genuinely fuzzy: sources vary on whether the northern line runs along Wyckoff Street or Baltic Street and the southern line along Hamilton Avenue or the Gowanus Expressway, and the neighborhood is bordered by Park Slope, Boerum Hill, Carroll Gardens, and Cobble Hill. We’ve focused on the rezoned core along the canal itself rather than stretching into any of those neighborhoods’ own tracked territory.
ProjectLocationStatus
1Gowanus WharfThird Ave. & Nevins St.Under Construction / Leasing
2Gowanus Green (Public Place)Smith St. & 2nd Ave.Remediation / Pre-Construction
3155 Third Street155 Third StreetFinanced / Pre-Construction
4Society Brooklyn & Sackett PlaceBond & Sackett StreetsCompleted / Leasing
5Gowanus Canal Superfund CleanupThe canal itselfActive / Behind Schedule
6Combined Sewer Overflow TanksButler St. & 2nd Ave.Under Construction
7Carroll Street BridgeCarroll St. over the canalReopened / Reconfigured
8The Douglass & DeGraw PoolThomas Greene PlaygroundUnresolved
9Wyckoff Gardens & Gowanus HousesNYCHA campusesUnder Construction
10224 3rd Avenue (579 Sackett St.)3rd Ave. & Sackett St.Topped Out
11213 Third Avenue3rd Ave. & Degraw St.Under Construction
12424 Hoyt Street (Ailanthus)Hoyt St.Filed / Rezoning Application

The Projects Reshaping Gowanus

From towers rising along the canal to the cleanup running beneath them.

1

The Developer Building More Than 2,200 Apartments Along One Stretch of Canal

The 175 Third Street site in November 2024, cleared and awaiting construction of what will be Gowanus's largest building. Not the site's current condition. — Imagery: Google Street View
Address/LocationThird Avenue between Union & Sackett Streets, and 310–340 Nevins Street, Gowanus
Developer/ApplicantCharney Companies and Tavros Capital; 175 Third St. designed by Bjarke Ingels Group (BIG)
Project5-building master plan, 2,200+ units total, 25% affordable in each building
StatusUnder Construction / Leasing
Latest UpdateEarthwork began at 175 Third Street in early October 2026, following the $785 million construction financing Charney and Tavros closed for the building in June 2026 — the fourth and largest building in the master plan

One Master Plan, Five Buildings, One Canal

Charney Companies and Tavros have spent the past two years assembling and building out a single continuous stretch of Gowanus’s east bank under the name Gowanus Wharf. Union Channel, at 240 Third Avenue, was the first to open and is now fully leased. Douglass Port, at 251 Douglass Street, followed and was about 20% leased as of July 2026. The two-tower Nevins Landing complex began leasing its southern building in July 2026, with the northern tower to follow.

Each building has carried the same structure: roughly a quarter of units set aside as permanently affordable, a shared amenity campus that eventually totals some 160,000 square feet, and direct canal frontage as part of the rezoning’s required waterfront public access.

The Biggest Building Yet Is Just Getting Its Money

175 Third Street is the plan’s largest and final piece: a 27-story tower designed by Bjarke Ingels Group, reported at various points as roughly 827 to 1,100 apartments depending on the source and the design’s evolution since 2025 — we’re not picking one figure. Apollo and Affinius Capital are providing $600 million in debt and RXR another $185 million in equity, the capitalization that closed in June 2026. Life Time has already signed on for an 85,000-square-foot fitness club and spa inside it. The site has been cleared and earthwork began in early October 2026, with no completion date yet announced.

Sources: Mann Report; New York YIMBY; Brownstoner; Commercial Observer; Mann Report; New York YIMBY

2

A 100%-Affordable Megaproject That’s Finally Getting Unstuck

The Public Place site along Smith Street and 2nd Avenue, the still-undeveloped former manufactured gas plant where Gowanus Green would rise. Aerial view; not evidence of current ground conditions. — Imagery: Google Maps
Address/Location“Public Place,” bounded by Smith St., 2nd Ave., 5th St. & Butler St., Gowanus
Developer/ApplicantGowanus Green Partners — The Hudson Companies, Jonathan Rose Companies, The Bluestone Organization, Fifth Avenue Committee & Mega Group Development; NYC HPD land
Project6 buildings, 950 apartments (100% affordable), a public school, a waterfront park
StatusRemediation / Pre-Construction
Latest UpdateState regulators and National Grid appear close to settling a dispute that froze the project for two years; developers hope to close construction financing for the first building by June 2026 and finish it in spring 2029

Housing Built on a Century of Coal Tar

Gowanus Green would replace “Public Place” — the site of the Citizens Manufactured Gas Plant for more than 100 years — with six buildings holding 950 fully affordable apartments, split between households earning up to 50% of area median income and up to 120%, plus a new public school and waterfront park. The city has held the site since 2008, when Gowanus Green Partners won it through a competitive RFP.

The project has been on ice since 2024, when the state Department of Environmental Conservation and National Grid — the utility responsible for the cleanup — deadlocked over how aggressively to treat contaminated groundwater. DEC wanted National Grid to inject concrete into the soil to stabilize it; the developers submitted a narrower supplemental cleanup plan for the smaller of the site’s two parcels rather than wait for a resolution covering the whole site.

A School With No Money Attached Yet

The plan’s public school is a genuine open question, not a formality: the city’s own School Construction Authority has made no funding or construction commitment, and no zoning or admissions plan exists yet. If remediation of the larger parcel — which would hold the school, the park, and most of the housing — proceeds on the currently discussed timeline, construction across all six buildings would run from roughly 2026 to 2031.

Sources: Brownstoner; Red Hook Star-Revue; City Limits; The Hudson Companies

Gowanus, Visually

Six numbers tell the bigger story.

Chart: Gowanus's 2021 rezoning enabled roughly 8,500 new apartments across the neighborhood's former industrial core.
Roughly 8,500 new apartments were enabled by Gowanus's 2021 rezoning.
View full sizeDownload PNG
Copy embed code
Chart: Gowanus Wharf's five-building master plan totals more than 2,200 apartments along the canal's east bank.
Gowanus Wharf's five-building master plan totals 2,200+ apartments, with leasing underway at three.
View full sizeDownload PNG
Copy embed code
Chart: the Gowanus Canal Superfund cleanup now costs more than $1 billion, up from an original 2013 estimate of $78 million, per the EPA Office of Inspector General.
The EPA's own inspector general put the Superfund cleanup's cost at more than 13 times its original 2013 estimate.
View full sizeDownload PNG
Copy embed code
Chart: the Gowanus Canal Superfund cleanup is more than 6.5 years behind its original schedule, per the EPA Office of Inspector General.
The same EPA watchdog report found the cleanup running more than 6.5 years behind its original schedule.
View full sizeDownload PNG
Copy embed code
Chart: Gowanus's two combined sewer overflow retention tanks, part of a $1.6 billion DEP program, are not expected to be fully operational until 2029.
The city's $1.6 billion sewage-tank program protecting the canal won't be fully operational until 2029.
View full sizeDownload PNG
Copy embed code
Chart: more than 2,200 Gowanus apartments are already leasing while the canal's sewage tanks won't be fully operational until 2029.
Private development is leasing now; the public infrastructure protecting the canal won't be finished until 2029.
View full sizeDownload PNG
Copy embed code

Free to embed with attribution and a link to Hush Street.

3

The Next Building in Line on Third Street

155 Third Street in May 2022, before redevelopment. Not the site's current condition. — Imagery: Google Street View
Address/Location155 Third Street, Gowanus
Developer/ApplicantMonadnock Development
Project300 units (225 market-rate, 75 affordable), retail/artist/commercial space
StatusFinanced / Pre-Construction
Latest UpdateMonadnock closed a $175 million construction loan in December 2025 and expected to file a New Building application with DOB in early 2026, targeting a Q4 2027 delivery

A Smaller Project, Still Real Money

155 Third Street won’t rival 175 Third Street or Gowanus Green in scale, but it’s a genuine, financed, mid-sized entry in the rezoning’s pipeline: 300 units with a quarter set aside as affordable, plus space earmarked specifically for retail, artists, and other commercial tenants rather than pure residential ground floor. Site work and a formal DOB filing were expected in early 2026, with construction to follow later in the year.

Sources: BLDUP

4

Gowanus Got a Rooftop Pool Before It Got a Park

Address/Location267 Bond Street & 498 Sackett Street, Gowanus
Developer/ApplicantProperty Markets Group; architect SLCE Architects
ProjectTwo 21-story towers, 517 units combined, 25% affordable; heated rooftop pool, waterfront esplanade
StatusCompleted / Leasing
Latest UpdateBoth towers wrapped construction in early 2025 and are now leasing, with rent-stabilized studios starting at $823/month through the affordable housing lottery

Amenities Ahead of Infrastructure

Society Brooklyn (267 Bond Street, 344 units) and Sackett Place (498 Sackett Street, 173 units) are a matched pair of towers with 605,000 square feet combined, a shared heated rooftop pool, and a new waterfront esplanade required as public access under the rezoning. It’s a small irony worth naming directly: new residents got a private pool and a canalside walkway years before the public sewage-tank and dredging work below is even finished — see the two sections after next.

Sources: New York YIMBY; 6sqft; Brownstoner

5

The Cleanup That’s More Than 1,000% Over Budget and Still Not Done

The Gowanus Canal, Brooklyn
The Gowanus Canal, photographed in July 2024. Photo by Kidfly182 via Wikimedia Commons, CC BY 4.0.
Address/LocationThe Gowanus Canal, full 1.8-mile length
Developer/ApplicantU.S. Environmental Protection Agency (EPA); dredging contractors overseen by EPA
ProjectFederal Superfund dredging & capping, upper & middle canal segments
StatusActive / Behind Schedule
Latest UpdateThe upper canal segment (RTA 1) finished dredging in summer 2024; full-scale dredging of the middle segment (RTA 2), a $369 million phase, began in June 2024 and is still underway after its 100% design report was approved in 2025

Thirteen Times the Original Estimate

The EPA’s own Office of Inspector General put a number on what Gowanus residents have watched happen for years: the Superfund cleanup now costs more than $1 billion, versus an original 2013 estimate of $78 million — over a 1,300% increase — and runs more than six and a half years behind its original schedule. The OIG’s report blamed disagreements between EPA and New York City over the cleanup’s Record of Decision, and warned the canal could need a second round of dredging if current delays continue.

Chart: the Gowanus Canal Superfund cleanup now costs more than $1 billion, versus an original 2013 estimate of $78 million -- a 13x overrun and 6.5+ years behind schedule, per the EPA Office of Inspector General.
Original Hush Street graphic. Source: U.S. EPA Office of Inspector General.

Everything Above the Canal Depends on What’s Below It

Every project in this tracker — the towers, Gowanus Green’s housing, even the Douglass & DeGraw Pool below — sits downstream of this single federal cleanup finishing on time. The next section covers the sewage-tank half of that same cleanup, which the OIG’s report specifically singled out for its own cost and schedule blowouts.

Sources: EPA Office of Inspector General; Gothamist; City & State New York; EPA

6

Two Tanks, $1.6 Billion, and a Decade of Delay

The Head End Tank construction site along Butler, Nevins, and Degraw Streets, where an 8-million-gallon sewage retention tank is being built underground. Aerial view. — Imagery: Google Maps
Address/LocationNevins St. between Butler & Degraw Sts. (Head End Tank); 2nd Ave. near 6th St. (smaller tank), Gowanus
Developer/ApplicantNYC Department of Environmental Protection (DEP); designed by Selldorf Architects
Project8-million-gallon & 4-million-gallon underground CSO retention tanks, plus a headhouse and 1.6-acre public park
StatusUnder Construction
Latest UpdateExcavation for the larger, 8-million-gallon Head End Tank is complete; construction of its base and walls is underway and targeted for completion in late 2026, with both tanks not expected to be operational until 2029

The City’s Half of the Superfund Deal

Where the previous section’s dredging is EPA’s responsibility, these two tanks are the city’s: a $329 million, 8-million-gallon tank at the canal’s head, running underground for nearly two blocks between Butler and Degraw Streets, plus a smaller 4-million-gallon tank further down the canal. Together they’re meant to stop the raw sewage that currently overflows into the canal every time it rains hard, and the site will eventually double as a 1.6-acre public park designed by Selldorf Architects once construction wraps.

A Watchdog Report Named This Specifically

The EPA Inspector General’s report on Gowanus Superfund delays and cost overruns was written specifically about these tanks, not the canal dredging — putting a federal magnifying glass on a project that was originally supposed to be finished years ago. DEP says it delivered the excavation phase six months ahead of an accelerated schedule set in December 2024, which is real progress, but “on schedule for a schedule that was already years late” is a different claim than “on time.”

Sources: NYC DEP; Brooklyn Paper; Gowanus Canal Community Advisory Group; 6sqft

7

Brooklyn’s Oldest Movable Bridge Reopened. Cars Aren’t Invited Back.

Carroll Street Bridge over the Gowanus Canal, Brooklyn
Carroll Street looking west from the Gowanus Canal, May 2026, shortly before the bridge’s June reopening. Photo by Epicgenius via Wikimedia Commons, CC BY-SA 4.0.
Address/LocationCarroll Street over the Gowanus Canal
Developer/ApplicantNYC Department of Transportation (DOT)
ProjectFive-year rehabilitation of a landmarked 1889 timber-retractile bridge
StatusReopened / Reconfigured
Latest UpdateDOT reopened the bridge on June 15, 2026, after five years of repairs — but permanently limited it to pedestrians, cyclists, and emergency vehicles, ending its role as a through street for cars

One of Four Left in the Country

The Carroll Street Bridge is a rare trapezoid-shaped timber-retractile bridge — one of just four of its kind still standing in the United States — that has swung diagonally to let boat traffic through the canal since 1889. DOT’s five-year rehab repaired its abutment and approach and added a new timber wearing surface.

The Closure That Became Permanent Policy

DOT’s own traffic counts during the five-year closure found no measurable increase in traffic on the three alternate crossings — Union Street, Third Street, and Ninth Street — because the Carroll Street Bridge was already the least-used of the four Gowanus Canal crossings. That data is the stated reason the reopened bridge is staying car-free for through traffic, with planters and new signage blocking vehicles rather than just recommending against them. It’s a rare case of a five-year construction inconvenience directly producing a permanent, evidence-based street redesign.

Sources: NYC DOT; Gothamist; 6sqft

8

The Neighborhood Pool Caught Between a Toxic Cleanup and a Housing Fight

Thomas Greene Playground, home to the Douglass & DeGraw ('Double D') Pool, photographed in October 2024. — Imagery: Google Street View
Address/LocationThomas Greene Playground, Nevins St. between Douglass & Degraw Sts., Gowanus
Developer/ApplicantEPA / National Grid (remediation); NYC Parks (the pool itself)
ProjectManufactured-gas-plant remediation beneath a public pool and playground
StatusUnresolved
Latest UpdateThe EPA asked National Grid in fall 2025 to pilot a less invasive stabilization method that could avoid draining and demolishing the pool entirely — a real reprieve from the demolish-and-relocate plan the agency had been pursuing for years

A Pool Sitting on a Century-Old Gas Plant

The beloved “Double D” pool — nicknamed for sitting between Douglass and DeGraw Streets — occupies part of the former Brooklyn Union Gas Fulton Municipal Manufactured Gas Plant site, active from 1879 into the early 1930s. Coal tar has been oozing under the pool for years, and the EPA has long said the pool would need to be drained and demolished to excavate the contamination beneath it.

Where Would a Temporary Pool Even Go?

The EPA’s original plan to relocate the pool temporarily to a parking lot next to Wyckoff Gardens collided head-on with the city’s own separate plan to build new housing towers on that exact lot — the same NYCHA campus covered in the next section. That collision, unresolved for years, is part of why the newer in-situ stabilization pilot National Grid is now testing matters so much: if it works, it could make the whole demolish-relocate-rebuild question moot. As of this update, no final decision has been announced either way — a genuinely open story worth watching.

Sources: Brooklyn Paper; Friends of Thomas Greene Park & Gowanus Canal Conservancy; NYC Parks

9

The Public Housing Repairs the Rezoning Promised

Wyckoff Gardens public housing, Brooklyn
Wyckoff Gardens, photographed in 2012 — well before the current modernization work, shown here for context of the same public housing campus. Photo by Jim.henderson via Wikimedia Commons, CC0.
Address/LocationWyckoff Gardens & Gowanus Houses, NYCHA campuses, Gowanus/Boerum Hill border
Developer/ApplicantNYCHA; design-build team Mega/Technico Joint Venture
Project$216 million in-unit and building-systems modernization, ~3,700 residents
StatusUnder Construction
Latest UpdateThe first phase of in-unit construction at Gowanus Houses began the week of February 17, 2026, across three buildings, after model units opened at both campuses showing the new kitchens and bathrooms residents can expect

The Non-Negotiable Part of the Rezoning Deal

NYCHA repairs at Wyckoff Gardens and Gowanus Houses were one of the specific community-benefits commitments that got the 2021 Gowanus rezoning through a nearly unanimous City Council vote in the first place, alongside sewer improvements and affordable artist space. Four years later, the $216 million modernization is real, funded, and now visibly underway rather than a line in a memorandum of understanding.

It’s worth reading this section alongside the Douglass & DeGraw Pool above: the same Wyckoff Gardens site that’s getting these interior repairs is also the parking lot the EPA once proposed for a temporary pool relocation — two different agencies with two different plans for the same few acres, playing out at the same time.

Sources: The NYCHA Journal; The NYCHA Journal; City Limits; Brownstoner

10

A Corner Rental Tower Tops Out on Sackett Street

The site at 3rd Avenue and Sackett Street, October 2024, before redevelopment. Not the site's current condition. — Imagery: Google Street View
Address/Location224 3rd Avenue (also addressed as 579 Sackett Street), at the corner of 3rd Avenue and Sackett Street
Developer/ApplicantHershy Silberstein / BlueSky Developers
Project11 stories, 64 rental units, ~3,300 sq ft ground-floor retail
StatusTopped Out
Latest UpdateConstruction topped out in March 2026, following excavation that began in May 2025

A Site Assembled, Then Rebuilt

Hershy Silberstein bought this corner site — a former auto repair shop — for $16.5 million in early 2025 from Martin Nussbaum, co-founder of Slate Property Group. His firm, BlueSky Developers, replaced it with an 11-story, 64-unit rental building designed by Kao Hwa Lee Architects, with studios to three-bedroom units, ground-floor retail, and amenities including a fitness room and rooftop recreation space.

Excavation began in May 2025; the building topped out in March 2026, one of several BlueSky/Silberstein projects moving through Gowanus’s rezoned blocks around the same time.

Sources: New York YIMBY; The Real Deal; Commercial Observer; Hoodline

11

An 80-Unit Tower Breaks Ground at Third and Degraw

The site at 3rd Avenue and Degraw Street, October 2024, cleared and staged for construction. Not the site's current condition. — Imagery: Google Street View
Address/Location213 3rd Avenue, at the corner of 3rd Avenue and Degraw Street
Developer/Applicant590 Degraw LLC; architect Kushner Studios
Project14 stories, 80 units, ~5,900 sq ft commercial space, 10-car garage
StatusUnder Construction
Latest UpdateSite prepared for groundbreaking as of April 2026, with a piling machine on site and excavation underway behind construction boards

A Former Industrial Yard, Now a 14-Story Tower

This corner lot — formerly a low-rise industrial building and open-air yard — is becoming a 145-foot, 80-unit residential building for 590 Degraw LLC, designed by Kushner Studios. Average unit size runs around 963 square feet, with roughly 5,900 square feet of ground-floor commercial space, a cellar, a 30-foot rear yard, and a 10-vehicle parking garage.

As of April 2026, the site had been cleared behind construction boards with a piling machine in place — active early-stage construction, consistent with the surrounding Third Avenue corridor’s broader building wave.

Sources: New York YIMBY

12

An Auto Shop Ground-Leased From Two Trees Could Become 400 Apartments

424 Hoyt Street in late 2024 — a one-story auto repair shop and vehicle storage facility. Not the site's current condition. — Imagery: Google Street View
Address/Location424 Hoyt Street
Developer/ApplicantAilanthus (Ofer Cohen, Vivian Liao, Tucker Reed), ground-leased from Two Trees Management
Project17 stories, 400 units (100–120 affordable), plus a 46,000 sq. ft. public school and 14,000 sq. ft. of retail
StatusFiled / Rezoning Application
Latest UpdateAilanthus filed a rezoning application with the NYC Department of City Planning in September 2026 to take the site from manufacturing to a mixed-use district, allowing the proposed 400-unit building

A Ground Lease From Gowanus’s Largest Landlord

Two Trees Management — the developer behind DUMBO’s transformation and better known there than in Gowanus — has owned 424 Hoyt Street since 2008, when it paid $7.7 million for the site. Today it holds a one-story automotive repair building and a separate vehicle storage facility, as-of-right good for about 91,800 square feet.

Ailanthus, a mixed-income housing developer led by TerraCRG’s Ofer Cohen alongside Tucker Reed and Vivian Liao, holds a ground lease on the site from Two Trees and filed a rezoning application (NYC Planning project 2025K0417) in September 2026 to build a 17-story, 175-foot building with 400 apartments, 100 to 120 of them affordable, plus a 46,000-square-foot public school and 14,000 square feet of ground-floor retail. The application still has to clear ULURP review before anything is approved.

Ailanthus has pointed to the Mamdani administration’s citywide target of 700,000 new homes over the next decade, and to Gowanus’s own Community Board 6 being named one of three Brooklyn districts with the least access to affordable housing, as the rationale for the filing.

Sources: Commercial Observer; The Real Deal; NYC Planning ZAP

Capital & Transactions

Money Moving in Gowanus

A curated look at recent property sales and financing that help explain who’s buying, building, and lending in Gowanus right now. Drawn from New York City’s public ACRIS property records, not a complete log of every filing — we include only transactions that say something real about the neighborhood’s direction, and leave out routine paperwork, internal transfers, and deals we can’t explain responsibly.

Construction Financing$785M

175 Third Street — Gowanus WharfAug. 2026

Public filings name Athene Annuity and Life Company — Apollo Global Management’s insurance-based lending arm — as the mortgagee behind part of the $785 million already reported for Gowanus’s largest building (Section 1, above). The same filings include a City of New York/HPD regulatory agreement, confirming the project’s required affordable-housing restriction is formally in place.

Borrower: Gowanus 3rd Street Owner LLC (Charney Companies / Tavros Capital) · ACRIS record ↗ · Hush Street Deal record →

Construction Financing$38.5M

213 Third AvenueJul. 2026

The first public confirmation of financing behind the Third Avenue tower already under construction (Section 11, above) — two mortgages totaling $38.5 million, closed alongside a City of New York/HPD regulatory agreement.

Borrower: 213 3rd Ave 1 LLC / 590 Degraw LLC · ACRIS record ↗ · Hush Street Deal record →

Site Assemblage$10.5M

248–258 4th AvenueJul. 2026

Three adjacent small buildings on Gowanus’s main commercial corridor sold the same week to newly formed, single-purpose ownership entities, financed together with one blanket mortgage. No redevelopment has been announced — but the pattern (coordinated closings, fresh ownership LLCs, bridge financing) is the shape a site assembly usually takes, not a routine resale. Worth watching, not yet a confirmed project.

Buyer: newly formed ownership entities (not otherwise disclosed) · Lender: Maxim Credit Group · ACRIS record ↗

Site Acquisition$11M

604 Union StreetJul. 2026

A new ownership entity bought the site for $11 million the same week a permit was filed for an 85-unit, 9-story building here — a real, previously-untracked Gowanus site with both a buyer and a construction filing now on record.

Buyer: 604 Union TIC LLC / Union Residents NY LLC · Lender: Popular Bank · ACRIS record ↗

Loan Assignment~$90M

164 4th Avenue — Douglass Street ApartmentsJun. 2026

Artimus Construction’s ~$90 million JPMorgan Chase/Community Preservation Corporation construction loan for this 160-unit, 30%-affordable tower was assigned to the Federal Home Loan Mortgage Corporation (Freddie Mac) in June 2026 — typically a sign a project has moved from construction into permanent, stabilized financing.

Borrower: 164 4 LLC · ACRIS record ↗ · Hush Street Deal record →

Source: New York City’s public ACRIS property records. This module is reviewed and curated by Hush Street editors, not an automated feed, and will be updated as new, meaningful filings are confirmed.

Have a tip on a Gowanus project we should be tracking? Let us know.

By Updated Built from city filings and published reporting. About Hush Street