Empire Stores, DUMBO, Brooklyn
Development Tracker — DUMBO

What’s Being Built in DUMBO? New Developments & Renovation Projects

Track renovations, commercial shifts, and infrastructure projects reshaping DUMBO, Brooklyn — updated as filings and news happen.
8
Projects Tracked
4
Under Construction
2
Pre-Construction
Sept. 2026
Updated
What’s Changing
→
Empire Stores’ floors 4-6 buildout entered its major construction phase — $13.5M in general-construction permits, plus HVAC, structural, and plumbing work, filed across floors 4, 5, 6, and the roof.May 2026
→
27 Bridge Street’s Electrify America facility conversion is active, with all major permits — foundation, excavation support for new Con Edison vaults, mechanical — now issued.May 2026
→
CityPickle’s 60,000-sq-ft Anchorage Plaza pickleball complex has active site-prep permits, though its original spring 2026 opening target has passed unconfirmed.Apr. 2026
Under Construction4
Pre-Construction2
Completed1
See full project list →

Hush Street is tracking what’s changing in DUMBO — the waterfront neighborhood under the Manhattan Bridge that’s spent the last decade turning 19th-century warehouses into offices, condos, and public space. Unlike Brooklyn Heights, where several ground-up towers are actively rising, DUMBO’s current story is different in kind: no major ground-up development is moving through the city’s land-use process right now. What’s actually happening is renovation, commercial repositioning inside buildings that already exist, and infrastructure work — a neighborhood in the middle of reinventing what its existing buildings are for, not building new ones.

Some of what follows is well covered elsewhere — a completed city infrastructure project, a real commercial trend. Some of it isn’t: we found a multimillion-dollar renovation at one of DUMBO’s most visible buildings that, as far as we can tell, nobody has reported on at all. Where a claim comes from a public permit, filing, or city record rather than published reporting, we say so.

ProjectLocationStatus
1Empire Stores Floors 4-6 Buildout55 Water StreetUnder Construction
2DUMBO’s Design-District Leasing BoomConcentrated at 45 Main, 55 Washington, 20 Jay StActive / Ongoing
3Historic Street Restoration & Pearl Street Plaza26 blocks, DUMBO-wideCompleted
427 Bridge Street (Vinegar Hill)27 Bridge StreetUnder Construction
5Clocktower Building Facade Work1 Main StreetApproved
6Empire Fulton Ferry Structural RehabBrooklyn Bridge ParkPermitting
7175 Pearl StreetPearl St.Under Construction
8CityPickle at Anchorage PlazaAnchorage PlazaUnder Construction

What’s Actually Changing Inside DUMBO’s Buildings

No ground-up towers are rising here — the real story is renovation, repositioning, and infrastructure.

1

Empire Stores Floors 4-6 Buildout

Empire Stores, the converted 19th-century warehouse complex at 55 Water Street in DUMBO
Empire Stores at 55 Water Street. Photo by Kidfly182 via Wikimedia Commons, CC BY-SA 4.0.
Address/Location55 Water Street
Developer/Applicant55 Water LLC (Midtown Equities); general contractor Structure Tone LLC; mechanical Bedrock Mechanical
ProjectCoordinated buildout spanning floors 4, 5, 6, and the roof of Empire Stores — occupant not publicly identified
StatusUnder Construction
Latest UpdateMajor construction permits issued through May 8, 2026, following a demolition-and-whitebox phase that began in December 2025

What the Permit Record Actually Shows

Empire Stores — the row of 1868-to-1885 warehouse buildings that Midtown Equities redeveloped into offices and retail in 2016 — is in the middle of a substantial renovation that, as far as we can determine, has not been reported anywhere. We found it by pulling the building’s complete permit history rather than relying on news search, and the pattern that emerges is specific enough to describe with real confidence, even though one central fact — who it’s for — remains unknown.

The sequence starts in December 2025 with a “whitebox” demolition permit on floors 5 and 6 — standard language for stripping a space down to its base condition ahead of a new build-out. Through the winter and spring, a run of Landmarks Preservation Commission filings tracked interior alteration work floor by floor, including new interior openings and ADA-consistent ramps.

Then, in permits issued through early May 2026, the project became unmistakably large: $13.5 million in general construction work across floors 4, 5, 6, and the roof; $4.5 million in HVAC and mechanical work covering the same floors; $1.145 million in plumbing, sprinkler, and standpipe work, filed multiple times across different floors; and $240,000 in structural work. A separate, smaller build-out of floor 4 alone from 2022 appears to be getting superseded as part of this larger program — which suggests floor 4 is being folded into a single, larger footprint with floors 5 and 6, rather than treated as its own space.

The contractor of record matters here too. Structure Tone is a national commercial-interiors firm that specializes in large corporate office fit-outs — the kind of general contractor a company hires for a real headquarters-scale build, not a routine repair. That, combined with three full floors and a roof all moving through construction together, is what makes this read as one coordinated project rather than scattered maintenance.

What We Could Not Determine

We do not know who the tenant is. It doesn’t appear on Empire Stores’ own website, which lists the building’s current restaurant and retail tenants — West Elm, Time Out Market, Kith Kids, and others — none of whom show any sign of leaving. We found no lease announcement, no brokerage listing describing the space as newly let, and no press coverage of any kind.

We also checked whether this could involve Two Trees Management, DUMBO’s dominant developer, or the NYC Economic Development Corporation, which had a role in Empire Stores’ original public-private redevelopment — neither appears to be involved here. Ownership hasn’t changed; the building has remained under 55 Water LLC throughout, with only the individual authorized signatory on file changing over time. We found no record of new financing tied to the project either.

What the record does support, without naming a tenant, is scale and coordination: a real, current, multimillion-dollar office build-out is underway across the upper floors of one of DUMBO’s most visible buildings, and whoever it’s for hasn’t said so publicly yet. We’ll update this section the moment that changes.

Sources: NYC DOB permit records, full filing history (DOB NOW: Build); NYC Landmarks Preservation Commission permit records (LPC-26-06219, -07739, -08534, -08621, -10107, -10472)

2

DUMBO’s Design-District Leasing Boom

Address/LocationConcentrated at 45 Main St, 55 Washington St, and 20 Jay St
Developer/ApplicantTwo Trees Management (Jed Walentas)
ProjectA neighborhood-wide commercial leasing surge that led NYC to officially designate DUMBO a “Design District”
StatusActive / Ongoing
Latest UpdateDUMBO was officially crowned NYC’s “Design District” on May 21, 2026, the closing day of the NYCxDESIGN festival

More Than Half of Brooklyn’s Commercial Leasing, in One Neighborhood

Two Trees Management, which controls the largest share of DUMBO’s commercial real estate, closed 2025 with more than 380,000 square feet of new office leases and renewals — over 200 deals, accounting for more than half of all commercial leasing activity in Brooklyn that year. Residential occupancy across its buildings sits at 99%.

The two marquee deals of the period both involve architecture firms. Bjarke Ingels Group renewed its 50,000-square-foot headquarters lease at 45 Main Street, the largest DUMBO deal of the year. Snøhetta relocated its headquarters from Manhattan into 25,000 square feet at 55 Washington Street. Between those two anchors and the smaller firms following them, DUMBO buildings now house more than 150 architecture and design firms — reportedly the highest concentration of designers in any single New York City neighborhood.

That concentration is what earned DUMBO its official “Design District” designation on May 21, 2026, at the close of the annual NYCxDESIGN festival. Two Trees has leaned into the identity, adding new rooftop amenity spaces — designed by landscape architecture firm James Corner Field Operations, 8,500 to 11,000 square feet each — across three of its anchor office buildings.

A Cross-Neighborhood Note

Bjarke Ingels Group’s name comes up twice in Hush Street’s coverage right now — its DUMBO headquarters lease here, and separately, BIG’s architect of record on the storefront work at the St. George Tower wellness club in Brooklyn Heights. They’re unrelated projects for the same firm, not one story — but a small sign of how much of this specific pocket of Brooklyn one architecture practice currently touches.

Sources: Two Trees Management; Brooklyn Paper; NYREJ; Hoodline

3

Historic Street Restoration & Pearl Street Plaza

View of the Manhattan Bridge from a DUMBO street
The Manhattan Bridge overpass area, near where the new Pearl Street Plaza was built. Photo by Superbass via Wikimedia Commons, CC BY-SA 4.0.
Address/Location26 blocks across DUMBO, plus a new Pearl Street Plaza at the Manhattan Bridge archway
Developer/ApplicantNYC Department of Transportation, Department of Design and Construction, and Department of Environmental Protection
Project$108 million restoration of DUMBO’s historic Belgian-block streets, new storm sewers, protected bike lanes, and a new public plaza
StatusCompleted
Latest UpdateThe city celebrated the project’s completion on November 19, 2025, after a run that began in April 2019

A Six-Year Project, Finished

DUMBO’s cobblestone streets are part of what gives the neighborhood its identity, and they’re also more than a century old. Starting in April 2019, the city undertook a $108 million restoration across 26 blocks — Water, Plymouth, Front, Adams, and Main streets among them — replacing more than 800,000 individual Belgian-block stones while installing new stormwater sewers and protected granite bike lanes underneath and around them. The project wrapped in December 2025 and was formally celebrated on November 19, 2025.

The most visible new addition is Pearl Street Plaza, a 2,500-square-yard public space built into the Manhattan Bridge archway with new lighting and seating — a genuinely new piece of public realm in a neighborhood that doesn’t get much of it. Excavation for the project also turned up roughly 2,800 historical artifacts, some dating to the 1600s, that the city recovered during the work.

Sources: NYC Department of Design and Construction; Brooklyn Eagle; 6sqft

4

27 Bridge Street (Vinegar Hill)

Address/Location27 Bridge Street — in Vinegar Hill, immediately adjacent to DUMBO, not DUMBO proper
Developer/ApplicantElectrify America LLC; general contractor DeSimone Builders LLC
ProjectConversion of a 1926 garage building to commercial use, with major new electrical infrastructure
StatusUnder Construction
Latest UpdateAll major construction permits currently show “Permit Issued” status, with expirations running from September 2026 through January 2027 — work is active now

A Neighboring Story Worth Including, Honestly Labeled

This one sits just across the neighborhood line, in Vinegar Hill rather than DUMBO itself — but the scale and specificity of what’s happening here made it worth tracking alongside DUMBO’s own projects rather than leaving out entirely.

City permit records lay out a clear, active construction sequence at this address, a two-story building constructed in 1926 as a garage: an underground storage tank was removed in April 2025; foundation, underpinning, and structural work followed; and a Support of Excavation permit specifically describes “new Con Edison vaults” being installed — a strong signal of substantial new electrical capacity being brought to the site.

The core filing, a General Construction permit worth just under $2.92 million, converts the building’s use “from factory building to business and low hazard storage.” Altogether, permits at this address total roughly $3.57 million. Electrify America LLC — the EV-charging subsidiary of Volkswagen — is the applicant and owner of record on every filing.

A Possible Connection We’re Not Confirming

In March 2022, Electrify America publicly announced a new “flagship” charging-station format — twenty 350-kilowatt fast chargers, a customer lounge, an EV showcase area, and event space — planned for several cities, Brooklyn included. That announcement never named a specific address.

The Con Edison vault work at 27 Bridge Street is exactly the kind of major electrical upgrade a bank of fast chargers would require, and the timeline — arriving a few years behind that 2022 announcement’s original target — isn’t hard to square with how large infrastructure projects tend to run late. It’s a plausible match. It is not a confirmed one: no source we found names this address as the flagship site, and the formal “business and low hazard storage” use description in the permit doesn’t specify a public charging facility over some other commercial use.

We’re presenting the connection as an open possibility, not a fact, and we’ll update this section if either Electrify America or a more detailed report confirms or rules it out.

Sources: NYC DOB permit records, full filing history (DOB NOW: Build); Electrify America press release, March 2022 (flagship charging-station design)

5

Clocktower Building Facade Work

The Clocktower Building at 1 Main Street in DUMBO, a converted 1914 warehouse
The Clocktower Building at 1 Main Street. Photo by Opencooper via Wikimedia Commons, CC0.
Address/Location1 Main Street
Developer/ApplicantSolstice Residential Group (managing agent); applicant Cosmo Veneziale
ProjectRestoration of original window and door openings on the building’s primary facades
StatusApproved
Latest UpdateLandmarks Preservation Commission approved a Certificate of Appropriateness for the facade work in August 2025

One of DUMBO’s most recognizable landmarks is having its facade restored. The 1914 building — originally a Robert Gair Company warehouse, converted to condominiums in 1998 by Two Trees — is protected under landmarks review, and the Commission approved a Certificate of Appropriateness in August 2025 for work restoring original window and door openings on the building’s primary facades. We found no press coverage describing the project’s exact scope, cost, or what prompted it now, beyond the general history of the building itself — it’s worth a place here on the strength of how visible the building is to the neighborhood, even with a thin public record behind the current work.

Sources: NYC Landmarks Preservation Commission permit records (Socrata dpm2-m9mq)

6

Empire Fulton Ferry Structural Rehab

Fulton Ferry Landing in Brooklyn Bridge Park
Fulton Ferry Landing, part of the structure now undergoing repair. Photo by R.scholz via Wikimedia Commons, CC BY-SA 3.0.
Address/LocationEmpire Fulton Ferry & Fulton Ferry Landing, Brooklyn Bridge Park
Developer/ApplicantBrooklyn Bridge Park Corporation
ProjectStructural repair of the pier’s sheet pile, gravity wall, and pile encasements, plus removal of a transfer bridge at Pier 4
StatusPermitting
Latest UpdateA New York State environmental notice for the project closed its public comment period June 4, 2026; construction is targeted for spring 2026

Brooklyn Bridge Park is soliciting a marine contractor for structural repairs at Empire Fulton Ferry and Fulton Ferry Landing — the westernmost, most DUMBO-facing stretch of the park. The scope, per a New York State environmental notice, covers repair of sheet pile, the gravity wall, spalling and voids, and pile encasements, with fill for the work offset by the earlier removal of part of a transfer bridge at Pier 4. Construction is targeted for spring 2026. We found no reporting on total project cost, exact construction dates, or whether any part of the park will close during the work — those specifics don’t yet exist anywhere we could find, city record or press.

Sources: NYC city procurement record; New York State DEC environmental notice bulletin, May 20, 2026

7

A Former Watchtower Printing Building Gains 11 Floors

Address/Location175 Pearl Street
Developer/ApplicantWatermark Capital Group; architect S. Weider Architect
ProjectOffice-to-residential conversion, 8 stories plus an 11-story addition; ~200 homes, 25% affordable
StatusUnder Construction
Latest UpdateConversion and vertical expansion reported actively underway as of April 2026; completion targeted for late 2028

Part of the Old Watchtower Complex

This 1918 building was once part of DUMBO’s Jehovah’s Witnesses printing complex — connected to its neighbors via a skyway system, at the foot of the Brooklyn Bridge. Watermark Capital Group bought it from Cannon Hill Capital Partners in 2024 with a $50.6 million acquisition loan, then secured $125 million in construction financing in 2025.

The plan converts the existing eight floors to rental apartments and adds an 11-story condominium stack on top, bringing the building to 19 stories total and yielding nearly 200 homes, a quarter of them income-restricted, under the city’s newer 467-m tax program. Completion is targeted for late 2028.

Sources: New York YIMBY; Hoodline; Commercial Observer

8

A 15-Year-Vacant Plaza Becomes a Pickleball Hub

The fenced Anchorage Plaza lot under the Brooklyn Bridge, November 2024, before CityPickle's build-out. Not the site's current condition. — Imagery: Google Street View
Address/LocationAnchorage Plaza, at the foot of the Brooklyn Bridge between Old Fulton and Water streets
Developer/ApplicantCityPickle, under a 3-year license from NYC Parks & Recreation
Project60,000 sq ft recreation complex: 11 pickleball courts, food trucks, green space and seating, across three sub-areas
StatusUnder Construction
Latest UpdateA $1.1 million site-prep permit (retaining wall and fencing) was filed and issued in April 2026; the operator’s own site still lists the location as “Coming Soon,” past its original spring 2026 target

From Parking Lot to Public Plaza

Anchorage Plaza — the open space tucked under the Brooklyn Bridge’s Brooklyn-side approach — served as a public parking lot until 2009, then sat closed to the public for roughly 15 years, used mostly for city vehicle storage. In 2024, the NYC Department of Parks & Recreation put the site out for proposals.

CityPickle, a pickleball operator, won a three-year license agreement and unveiled plans in May 2025 for a 60,000-square-foot complex spanning the plaza’s three sections — Old Fulton Street Yard, Washington Street Yard, and the connecting Ash Alley — with 11 courts, food trucks, shaded seating, bike racks, and space for community programming.

Behind Schedule, Not Abandoned

City permit records show site-prep work — a $1.1 million timber retaining wall and fencing job — filed and issued in April 2026 under a Washington Street address matching the plaza’s footprint, consistent with the construction window reported at the time: permitting and building between fall 2025 and spring 2026.

That spring 2026 target has since passed without a confirmed opening. As of this writing, CityPickle’s own site still lists the Brooklyn Bridge location as “Coming Soon” with no firm date — a real schedule slip worth noting, not evidence the project has stalled.

Sources: Brooklyn Eagle; Commercial Observer; 6sqft; NYC DOB permit records (96 Washington Street filing); CityPickle

Have a tip on a DUMBO project we should be tracking? Let us know.

By Updated Built from city filings and published reporting. About Hush Street