Hush Street is tracking what’s changing in Crown Heights — a neighborhood whose development story has quietly shifted from a decade of contested, site-by-site rezoning fights to something new: a single, corridor-wide zoning change that’s now generating real construction activity along its western edge.
That change is the Atlantic Avenue Mixed-Use Plan, approved by the City Council in 2025. It replaced decades of industrial-only zoning along a 21-block corridor with rules that allow housing outright — no more one-site-at-a-time battles like the one that consumed 960 Franklin Avenue for half a decade. Just east of that corridor, though, two large individual rezonings (1720 Atlantic Avenue, 73-99 Empire Boulevard) had to go through exactly that kind of site-specific fight anyway, since AAMUP’s own boundary didn’t reach them.
Beyond the corridor and its neighbors, Crown Heights is also seeing its largest single private tower application in years, a state transit agency exploring housing on its own land, and a newly finished 259-unit building whose own neighborhood label is genuinely disputed.
Where a claim comes from a developer or agency’s own materials rather than independent reporting, we say so.
| Project | Location | Status |
|---|---|---|
| 1Atlantic Avenue Mixed-Use Plan | 1029 Dean St. & 1104 Pacific St. | Financed / Under Construction |
| 21720 Atlantic Avenue | 1720 Atlantic Avenue | Rezoned / Pre-Construction |
| 373-99 Empire Boulevard | 73-99 Empire Boulevard | Rezoned / Site Sold |
| 41550 Bedford Avenue | 1550 Bedford Avenue | ULURP Application Filed |
| 5MTA 1119 Pacific Street | 1119 Pacific Street | RFP Issued |
| 6Prosper Brooklyn | 1042 Atlantic Avenue | Completed / Leasing |
| 7The Arcadian | 975 Nostrand Avenue | Completed / Leasing |
| 8Bedford-Union Armory | 1101 & 1089 President Street | Completed |
| 9Botanic Heights (960 Franklin Ave.) | 960 Franklin Avenue | Completed / Leasing |
A Corridor-Wide Rezoning, and the Site-Specific Fights It Didn’t Replace
Nine anchors: a landmark zoning change now financing its first tower, two large individual rezonings just outside that corridor’s own boundary, the neighborhood’s biggest pending private tower application, a state transit agency testing whether its own land can become housing, a finished 259-unit building whose neighborhood label is itself disputed, another finished 328-unit rental, the last phase of a long-fought armory redevelopment, and a completed building whose own rezoning saga helped set the stage for the corridor-wide approach that followed it.
1
Atlantic Avenue Mixed-Use Plan
A Corridor, Not a Single Site
The Atlantic Avenue Mixed-Use Plan (AAMUP) replaced decades-old industrial zoning along Atlantic Avenue with rules that allow housing as of right. The rezoned area runs roughly 21 blocks, from Vanderbilt Avenue in Prospect Heights to Nostrand Avenue at the Crown Heights/Bedford-Stuyvesant line.
The City Council approved it in May 2025. City officials estimate it could ultimately bring up to 4,600 new apartments, with roughly 1,900 of them — about 40% — permanently affordable. Another $235 million was earmarked for community investments and infrastructure alongside the zoning change itself.
The First Site Breaks Ground
In April 2026, JLL Capital Markets arranged the $25.15 million sale of two Crown Heights properties inside the rezoned corridor — 1029 Dean Street and 1104 Pacific Street, together over 129,000 zoning square feet — to Brooklyn-based Castell Group and Montgomery Street Partners. The same month, the buyers closed $47.4 million in construction financing for a 10-story, 170-unit building on the combined site, targeting a mid-2027 opening. Hush Street’s Prospect Heights tracker covers that financing, and a real neighborhood-naming ambiguity in how it’s been reported, in more depth.
A second, larger transaction landed just across the neighborhood line: Avery Hall Investments, the Brodsky Organization, and Monadnock Construction paid a combined roughly $49 million for 962 Pacific Street and 863 Dean Street, on the Crown Heights/Prospect Heights border. That site’s former owner had proposed her own roughly 150-unit project there in the early 2020s — blocked by Council Member Crystal Hudson as the city moved toward the comprehensive rezoning instead. Hush Street covers that project in more depth in its Prospect Heights tracker.
A Separate Filing, Right Next Door
One block over, a different developer is moving on a different site inside the same rezoned area. Shimon Brach filed permits for an eight-story, 81-unit rental at 1027 Dean Street; the Department of Buildings issued a foundation-and-earthwork permit in late July 2026 and a sprinkler-system permit that August, both signs of active, not just filed, construction. It isn’t part of the Castell Group project next door — a reminder that AAMUP’s as-of-right zoning is drawing multiple, unrelated developers to build independently along the same blocks, rather than one master-planned buildout.
Sources: Brooklyn Borough President (ULURP application); 6sqft; JLL Capital Markets; Yield Pro (construction financing); Hoodline (962 Pacific St./863 Dean St.); New York YIMBY (1027 Dean St.); NYC DOB NOW permit records (job B01341355-I1)
2
1720 Atlantic Avenue
A Genuine Coverage Gap, Found This Pass
This project sat entirely outside Hush Street’s Crown Heights coverage until a Foundation QA reconciliation pass found it — a real, City Council-approved, 278-unit project on the same avenue the neighborhood’s central rezoning story runs through, simply not yet folded in. Bermuda Realty’s Jack Bawabeh is converting a one-story strip mall — currently leased to a pharmacy, a discount store, a grocery, coffee shops, a check casher, and a furniture store — into two connected towers rising 13 stories.
Its Own Rezoning, Not AAMUP’s
Unlike 1029 Dean Street or 962 Pacific Street, this site didn’t gain its development capacity from the area-wide Atlantic Avenue Mixed-Use Plan — the site sits east of Nostrand Avenue, beyond AAMUP’s own mapped boundary, so it required its own site-specific ULURP rezoning application, one of the last individual land-use reviews the city approved before shifting how it handles this kind of request. The Council approved it in December 2025, delivering 278 rental units with 70 set aside as permanently affordable, plus ground-floor retail and community-facility space along Atlantic Avenue. IMC Architecture’s renderings, released in March 2026, show a red-brick base with floor-to-ceiling retail windows and a loggia-balcony grid above.
Sources: Commercial Observer; Hoodline; New York YIMBY; IMC Architecture (project design)
3
73-99 Empire Boulevard
A Contested Spot Rezoning, Not the Corridor Plan
Also missing from Hush Street’s coverage until this pass: a second large, individually-rezoned Empire Boulevard project, genuinely opposed at the community-board level. Bridges Development Group’s proposal to rezone this Empire Boulevard site for a 261-unit building — 13 stories, 145 feet — cleared the City Planning Commission and, in June 2025, the City Council, but not without a fight: the local community board opposed the spot rezoning outright, and Brooklyn Borough President Antonio Reynoso backed it only on the condition that the developer work to reduce shadow impacts on nearby outdoor play areas.
A New Owner Takes It Forward
The rezoning alone doesn’t guarantee construction — but a real ownership change afterward is a stronger signal than the entitlement itself. In August 2025, CW Realty bought the site for $40 million, The Real Deal reported, a year after approval. No demolition or new-building permit had been filed as of this update; sources differ on the affordable-housing split, citing either 52 or 78 units under the Mandatory Inclusionary Housing program, a discrepancy Hush Street has not been able to resolve and is disclosing rather than picking one figure.
Sources: Brownstoner (CPC vote); Brownstoner (Borough President approval); DHC Legal; The Real Deal (site sale)
4
1550 Bedford Avenue
A Failed Hotel Site Becomes a Tower Application
The 19,200-square-foot lot at 1550 Bedford Avenue has sat vacant since developer Yoel Goldman won approval there for a luxury hotel that never got built. Avery Hall Investments bought the site out of Goldman’s bankruptcy for $10.1 million in August 2025.
Nearly a year later, Avery Hall filed a land-use application seeking zoning amendments to swap that commercial/hotel entitlement for a mix of residential and commercial use, plus a Mandatory Inclusionary Housing designation.
What the Filing Describes
Crain’s New York Business reported the plan calls for an 18-story, roughly 173,000-square-foot building with 250 apartments, 75 of which would be affordable, plus ground-floor retail facing Bedford Avenue.
Like 1720 Atlantic Avenue and 73-99 Empire Boulevard above, this site required its own individual rezoning application rather than falling under AAMUP’s as-of-right district — the more traditional, site-specific route that Crown Heights projects have followed for years, including the neighboring 960 Franklin Avenue saga below. As of this update, the application has not yet reached the City Planning Commission for a formal vote.
Sources: Commercial Observer; Crain’s New York Business; The Real Deal (site acquisition)
5
MTA 1119 Pacific Street
A Different Kind of AAMUP Project: the Public Landowner
Another genuine gap this pass found: the MTA itself is trying to build housing here, using capacity AAMUP’s rezoning unlocked on land it already owns rather than land it’s selling to a private buyer. The RFP covers an underutilized lot the authority uses partly for vehicle and equipment parking, plus the air rights above the adjacent Franklin Avenue Shuttle right-of-way — a transit-oriented-development structure similar to what the MTA has pursued at stations elsewhere in the city.
Why Now
Governor Hochul’s March 2026 announcement ties the RFP to a 2023 executive order directing every state agency to review its own underutilized land for possible housing. Officials describe the project as roughly 300 units, with at least 75 permanently affordable, plus transit and public-realm improvements at the shuttle stop itself. Proposals were due in May 2026; as of this update, no winning developer or design has been announced, so this entry tracks a real, funded process rather than a specific building yet.
Sources: Office of Governor Kathy Hochul; Commercial Observer; New York YIMBY; Hoodline
6
Prosper Brooklyn
A Genuine Coverage Gap — and a Disputed Address
This 259-unit building had been leasing for over a year before Hush Street’s coverage caught it, surfaced during this Foundation QA pass while researching a similarly-named, similarly-developed building nearby. It’s a real oversight worth naming directly, not folding quietly into an existing section.
Independent sources are split on which neighborhood it belongs to. StreetEasy, New York YIMBY, and Brownstoner all describe 1042 Atlantic Avenue as Crown Heights; the developer’s own marketing site brands it “Prosper Prospect Heights” instead. Hush Street is following the majority of independent coverage and placing it here, while disclosing the disagreement rather than silently picking a side.
Two Towers, Built Ahead of the Corridor Rezoning
EMP Capital Group’s Elie Pariente developed two connected buildings — a 19-story Atlantic Tower and a shorter, 9-story Pacific Tower — totaling roughly 245,000 square feet and 259 apartments. Market-rate leasing began in June 2025, managed by MNS Real Estate; a lottery for 65 rent-stabilized studio, one-, and two-bedroom units, income-restricted, opened in February 2026. Notably, this project predates AAMUP’s own 2025 approval and secured its scale independently — a reminder that not every large Atlantic Avenue project traces back to the corridor-wide rezoning that now dominates this Tracker’s other sections.
Sources: Brownstoner; StreetEasy; NYREJ (leasing); Prosper Brooklyn (developer marketing)
7
The Arcadian
A 421-a Project Reaches Completion
Hudson Companies closed on a $135 million construction loan for 975 Nostrand Avenue in March 2024 — $85 million from Santander and $50 million from Related Fund Management, arranged by Cushman & Wakefield. The 421-a-financed building was designed by ODA Architecture as a nine-story, 328-unit rental with roughly 30% of units set aside as affordable, plus a ground-floor grocery store and community facility space.
The project hit its target completion window, opening in 2025 and now leasing as The Arcadian. It markets itself on proximity to Prospect Park, the Brooklyn Museum, and Grand Army Plaza rather than to the AAMUP corridor — a reminder that not every large project here is tied to the new rezoning.
What’s Actually There
The building’s studio-to-two-bedroom units include oversized windows with built-in solar shades and open onto landscaped courtyards and tiered gardens, per the developer’s own marketing. The available Street View coverage of the site still shows the building under construction behind green fencing — a genuine coverage lag rather than a wrong-location error, kept here as an honest “before” image rather than a current one.
Sources: The Real Deal; 6sqft; The Arcadian (developer marketing)
8
Bedford-Union Armory

A Decade-Long Fight Over a Century-Old Armory
The castle-like Bedford-Union Armory was built in 1903 and used by the Army until 2011. The city’s plan to redevelop it — first floated with market-rate condo towers — drew years of organized community opposition demanding more affordable housing and public recreation space before the current mixed-income plan was finalized.
BFC Partners, selected as developer, and Marvel Architects delivered a compromise: a 60,000-square-foot recreation center with a pool, basketball courts, and an indoor soccer field, plus 25,000 square feet of nonprofit space, alongside two new residential buildings.
Two Buildings, 415 Homes, Now Largely Complete
The Arch, the largest of the two buildings at 1101 President Street, delivered 323 units — 143 market-rate and 180 through an affordable lottery — with 15 stories designed by Marvel Architects. Leasing there launched in 2022. A second building at 1089 President Street added the remaining fully affordable units, with the last lottery phases opening through 2023.
Combined, the two buildings brought 415 apartments to the site, 250 of them affordable to households earning between roughly 30% and 60% of area median income. Together with the recreation center that opened in 2021, the project is now essentially complete — a rare Crown Heights example of a fully finished, multi-building redevelopment rather than one still in progress.
Sources: Wikipedia; BFC Partners; CityRealty (The Arch); 6sqft (community center opening)
9
Botanic Heights (960 Franklin Avenue)
The Fight That Set the Stage
Before there was an Atlantic Avenue Mixed-Use Plan, there was the “Spice Factory” fight at 960 Franklin Avenue — a proposal for two roughly 39-story towers that the City Planning Commission rejected in 2021 as “grossly out of scale.” What eventually got built instead, an as-of-right seven-story, 290-unit building called Botanic Heights, began leasing in April 2026.
Hush Street covers this project’s full five-year arc — the rejected towers, the site’s sale to YS Developers, and this year’s affordable housing lottery — in a dedicated Living Project Page. It’s worth noting here for what it says about the neighborhood’s development politics: a contested, years-long, site-specific rezoning fight like this one is part of what pushed the city toward the corridor-wide Atlantic Avenue approach instead of repeating the process lot by lot.
What We’re Watching Next
Three individual rezonings are now in the pipeline outside the AAMUP corridor’s own boundary: whether Avery Hall’s 1550 Bedford Avenue application clears the City Planning Commission, whether construction actually starts at 73-99 Empire Boulevard now that CW Realty owns the entitled site, and how quickly 1720 Atlantic Avenue moves from renderings to permits.
The MTA’s 1119 Pacific Street RFP is also unresolved — proposals were due in May 2026, and no developer selection has been announced as of this update. A handful of smaller Dean Street filings nearby (971 Dean Street’s 82-unit application among them) suggest the AAMUP corridor’s buildout is broader than the handful of projects large enough for their own section here.
Crown Heights borders Clinton Hill to the north and Prospect Heights to the west, both of which Hush Street also tracks.
Capital & Transactions
Money Moving in Crown Heights
A curated look at recent property sales and financing that help explain who’s buying, building, and lending in Crown Heights right now. Drawn from New York City’s public ACRIS property records, not a complete log of every filing — we include only transactions that say something real about the neighborhood’s direction, and leave out routine paperwork, internal transfers, and deals we can’t explain responsibly.
745 & 747 Franklin AvenueJun. 2026
A confirmed $11.9 million loan from Five Towns Funding to Ariel Sholomov for these two adjacent Franklin Avenue buildings, per PincusCo — not currently in Hush Street’s Crown Heights registry.
1 Sullivan PlaceJul. 2026
This completed (2019), 12-story rental tower cantilevering across from the Brooklyn Botanic Garden was refinanced for $21 million with Truist Bank and Goldman Sachs Bank USA — refinancing on an established building, not new construction.
995 President StreetJul. 2026
New York YIMBY confirms new permits filed in June 2026 for a 9-story mixed-use building at this site. This financing is consistent with construction/bridge funding for that filing.
Source: New York City’s public ACRIS property records. This module is reviewed and curated by Hush Street editors, not an automated feed, and will be updated as new, meaningful filings are confirmed.