Boerum Hill Historic District rowhouses at Hoyt and Bergen Streets, Brooklyn
Development Tracker — Boerum Hill

What's Being Built in Boerum Hill? A $3 Billion Jail, a Historic Church's Demolition & New Affordable Housing

Hush Street tracks what's changing in Boerum Hill, a landmarked brownstone neighborhood whose current story is dominated by a $2.959 billion jail rising on Atlantic Avenue as part of the city's plan to close Rikers Island, alongside a smaller wave of private residential filings and affordable-housing investment.
7
Projects Tracked
3
Under Construction
4
Pre-Construction
Oct. 2026
Updated
Watch → 1 $3B Jail Project
What’s Changing
→
Steel topped out on the $2.959 billion Brooklyn Borough-Based Jail at 275 Atlantic Avenue, with facade, cladding, and elevator installation now underway.Apr. 2026
→
A court-approved $28.25 million sale of 360 Schermerhorn Street — the fire-damaged Next Step Community Church site — was reported; the buyers plan to demolish the 1893-94 building for residential use.Aug. 2026
→
HPD designated the Fifth Avenue Committee to develop roughly 70 affordable homes plus a workforce center on the city-owned 153 Nevins Street parking lot.Aug. 2025
52 4th Ave. (The Eleanor) Financing$42M
32-40 4th Ave. Assemblage$6.5M
See recent property activity →

Hush Street is tracking what’s changing in Boerum Hill — a landmarked brownstone neighborhood squeezed between Downtown Brooklyn, Cobble Hill, Brooklyn Heights, Fort Greene, and Gowanus. Its story right now is dominated by one of the largest, most consequential civic construction projects in Brooklyn: a $2.959 billion jail rising on Atlantic Avenue as part of the city’s plan to close Rikers Island. Around it, a smaller but real wave of private residential filings and public affordable-housing investment is reshaping individual blocks.

Boerum Hill’s edges are genuinely blurry — real-estate marketing convention often stretches the name onto blocks that official geography places in Cobble Hill or Downtown Brooklyn, and we’ve drawn our own boundary from parcel-level city data rather than listing copy. Two nearby projects that press coverage sometimes associates with this corner belong to a neighboring Tracker instead: 120 Court Street (Downtown Brooklyn) and the Long Island University campus family (Downtown Brooklyn’s DeKalb Avenue core) — both explained further down.

ProjectLocationStatus
1275 Atlantic Avenue (Borough-Based Jail)Atlantic Ave.Under Construction
2360 Schermerhorn StreetSchermerhorn St. & 3rd Ave.Sale Approved / Pre-Demolition
3546 Pacific StreetPacific St., btw. 3rd & 4th Ave.Filed / Under DOB Review
4153 Nevins StreetNevins St.Designated / Pre-Development
5110 & 92 Boerum PlaceBoerum Pl., btw. Dean & Pacific St.Under Construction
6280 Bergen StreetBergen St., btw. Nevins & 3rd Ave.Under Construction
748 Hoyt StreetHoyt St. & Livingston St.Site Assembled / Plans Filed

The Projects Reshaping Boerum Hill

A borough-sized jail dominates the skyline; smaller filings and public affordable housing fill in around it.

1

A $3 Billion Jail Just Topped Out on Atlantic Avenue

Address/Location275 Atlantic Avenue
Developer/ApplicantNYC Department of Design and Construction (DDC); design-build team Tutor Perini Corporation/HOK
Project15-story, 712,150 sq ft borough-based jail, 1,040 beds, ~30,000 sq ft of community space
StatusUnder Construction
Latest UpdateStructural steel topped out April 22, 2026; facade/cladding installation and elevator work are underway as of this writing

One of Four Jails Meant to Replace Rikers Island

This is the Brooklyn piece of the city’s court-mandated plan to close Rikers Island by building smaller, borough-based jails in its place — one each in Manhattan, the Bronx, Queens, and here, replacing the old Brooklyn House of Detention that closed in 2020. At 15 stories and 712,150 square feet, it’s designed to hold 1,040 people, with more than 30,000 square feet of ground-level community space carrying its own separate entrances fronting Atlantic Avenue, two below-grade cellar levels, two loading berths, roughly 100 enclosed parking spaces, and an underground tunnel connecting to the adjacent courthouse.

Construction began in November 2024. Structural steel topped out on April 22, 2026, in a ceremony NYC’s Department of Design and Construction held with more than 100 construction workers on site. Facade panels started going up that March, and multiple passenger elevators were being installed across the project by spring 2026.

A Long Runway Still Ahead

The city’s own Department of Design and Construction puts the project’s cost at $2.959 billion and its target for substantial completion at spring 2029 — meaning that even with steel topped out, the building is roughly three more years from opening. (Some secondary coverage has rounded the cost to “$3 billion” and cited an earlier 2027 completion estimate; we’re going with DDC’s own, more recent figures.) The project sits directly across from the Brooklyn Heights Association’s own coverage area, and remains one of the most politically contested pieces of the citywide Rikers replacement plan.

Sources: NYC DDC; New York YIMBY; Brooklyn Paper; BKReader; NYC Borough-Based Jails Program

2

A 130-Year-Old Church, Fire-Damaged Twice, Is Headed for Demolition

Address/Location360 Schermerhorn Street, at 3rd Avenue
Developer/ApplicantTankhouse and Lonicera Partners (buyers, under contract)
ProjectDemolition of a fire-damaged Romanesque Revival church, residential redevelopment to follow
StatusSale Approved / Pre-Demolition
Latest UpdateA court approved the $28.25 million sale of the property, reported August 2026

Brooklyn’s Oldest Baptist Congregation, Twice Damaged by Fire

Next Step Community Church — formerly the First Baptist Church of Brooklyn, founded in 1823 and the oldest Baptist congregation in the borough — has occupied this Romanesque Revival building since 1893-94, rebuilt once already after a 1917 fire. A second fire in 2010 left the structure damaged, and it’s sat that way for roughly 15 years since.

Developers Tankhouse and Lonicera Partners are now under contract to buy the site for $28.25 million, with court approval of the sale reported in August 2026. Their stated plan is to demolish the fire-damaged structure and build new residential construction in its place.

An Earlier, Unbuilt Vision for the Site

Years before this sale, a feasibility study explored an entirely different path — preserving and building around the church rather than replacing it, with renderings showing the sanctuary expressed as transparent space open to the street, colored glass windows, or a glowing glass steeple marking the corner. That scheme was never confirmed to have a development partner or congregation sign-off, and nothing suggests it’s connected to Tankhouse and Lonicera’s current, demolition-bound plan — we’re noting it only as design history for a site whose future looked very different not long ago.

Sources: Brownstoner; Commercial Observer; Brooklyn Paper; CityRealty

3

A 16-Story Tower Files In Near Barclays Center

Address/Location546 Pacific Street, between 3rd and 4th Avenues
Developer/ApplicantChase Weber
Project16 stories, 180 feet, 86,519 sq ft (83,237 sq ft residential, 3,282 sq ft commercial)
StatusFiled / Under DOB Review
Latest UpdatePermits filed, reported August 2026

Permits have been filed for a 16-story, 180-foot residential building a few blocks from the Atlantic Avenue-Barclays Center subway hub, one of Brooklyn’s busiest transit interchanges. At roughly 86,500 total square feet — the large majority residential, with a smaller commercial component — it’s a mid-size addition rather than a megaproject, but a real, currently-filed one in a corridor that’s seen steady density growth for over a decade.

Sources: New York YIMBY

4

A City-Owned Parking Lot Becomes 70 Affordable Homes

Address/Location153 Nevins Street
Developer/ApplicantNYC Housing Preservation and Development (HPD); Fifth Avenue Committee (nonprofit developer); Brooklyn Workforce Innovations (workforce center operator)
Project100% affordable rental building, ~70 rent-stabilized homes, with a ground-floor workforce development center
StatusDesignated / Pre-Development
Latest UpdateHPD designated the nonprofit Fifth Avenue Committee to develop the site on August 14, 2025

This 11,500-square-foot, city-owned parking lot is becoming roughly 70 deeply affordable, rent-stabilized apartments — about 21 of them set aside for formerly homeless individuals and families, with the rest available through the city’s housing lottery. HPD designated the nonprofit Fifth Avenue Committee to lead the project in August 2025; Brooklyn Workforce Innovations will run a ground-floor workforce development center as part of the same building. Planned amenities include a community room opening onto a landscaped courtyard, an exercise room, laundry facilities, bike storage, and a backup generator. The site was part of a two-site HPD request for proposals covering publicly-owned Boerum Hill parcels — we haven’t independently confirmed the status of the second site and aren’t naming it without that confirmation.

Sources: New York YIMBY; Brownstoner; NYC HPD

5

Two Small Condos on the Street Boerum Hill Is Named For

Boerum Hill Historic District rowhouses at Hoyt and Bergen Streets, Brooklyn
The Boerum Hill Historic District at Hoyt and Bergen Streets — general neighborhood context, not the Boerum Place sites themselves. Photo by Dmadeo via Wikimedia Commons, CC BY-SA 3.0.
Address/Location110 Boerum Place and 92 Boerum Place, between Dean and Pacific Streets
Developer/Applicant110: Avdoo & Partners/Aksoy Holding. 92: Eliat Realty Corp (Farhad Bokhour)
Project110: 6-story, 21-unit condo. 92 (aka 237 Pacific St): 6-story, 6-unit mixed-use, ~15,700 sq ft
StatusUnder Construction
Latest Update110 Boerum Place topped out May 2025, targeting 2026 occupancy; 92 Boerum Place’s excavation and below-grade work was progressing as of April 2026

Both sites sit on Boerum Place, the street the neighborhood takes its name from, one block apart. 110 Boerum Place is a 6-story, 21-unit condo designed by Brent Buck Architects for Avdoo & Partners and Aksoy Holding, structurally topped out in May 2025 and targeting 2026 occupancy. Around the corner, 92 Boerum Place — also addressed as 237 Pacific Street — is a smaller, 6-unit mixed-use building designed by StudiosC Architecture for Eliat Realty Corp, with excavation and below-grade work still active as of this spring. Real estate coverage sometimes markets both addresses as “Cobble Hill,” but city parcel data places them on the Boerum Hill side of the Atlantic Avenue boundary — a geography call, not a quality judgment.

Sources: data/project-registry/cobble-hill.json research (Avdoo & Partners/Aksoy Holding, Brent Buck Architects; StudiosC Architecture/Eliat Realty Corp), independently reused per Hush Street’s own prior verification

A note on two nearby projects we’re not duplicating here: 120 Court Street, the former Walgreens site at Court and Atlantic, is widely reported as “Brooklyn Heights” but its canonical home is Downtown Brooklyn — see that tracker’s own section. And the Long Island University campus family (75 & 89 DeKalb Avenue, The Willoughby, Brooklyn Paramount) sits firmly within Downtown Brooklyn’s DeKalb Avenue core, not Boerum Hill, despite LIU’s campus reading as a single institutional footprint from a distance — we’re flagging it here rather than building it out, since it belongs to a Tracker we’re not editing this session.

6

A 450-Unit Rezoning’s First Phase Is Now in the Ground

The former manufacturing block at Bergen and Nevins streets, December 2022, before redevelopment. Not the site's current condition. — Imagery: Google Street View
Address/Location280 Bergen Street, between Nevins Street and Third Avenue
Developer/ApplicantFischer Rasmussen Whitfield and Goose Property Management
ProjectFirst phase of a 450-unit rezoning: 3 buildings, 297 rental units, ~302,000 sq ft, ground-floor supermarket
StatusUnder Construction
Latest UpdateExcavation was underway as of April 2026, financed with a $166 million loan; completion is targeted for winter 2028

The Last Manufacturing Block in Boerum Hill

This site — a former screen-printing plant and surrounding parking lots on the block bounded by Nevins, Bond, Wyckoff, and Bergen streets — was the last manufacturing-zoned block in Boerum Hill. In December 2022, the City Council approved a rezoning, nearly unanimous, converting it to residential use with a Mandatory Inclusionary Housing designation attached.

As approved, the full site allows roughly 450 apartments across four structures — two 9-story buildings and two 3-story, 3-unit townhomes — with half the units (225) permanently affordable: about three-quarters at 60% of area median income, the rest at 80%. One building is planned for seniors, another for low-income families. It was the first NYC rezoning to include a racial impact study, and Community Board 2 initially voted against an earlier version of the plan over height and unit-count concerns before the final, larger affordability package won City Council approval.

The First Phase, Now Excavating

Fischer Rasmussen Whitfield and Goose Property Management are building the project’s first phase: three abutting structures totaling 297 rental units (studios to two-bedrooms) and about 9,700 square feet of ground-floor retail, reported as a supermarket replacing the block’s prior grocery tenant. Excavation was underway as of April 2026, backed by a $166 million construction loan, with completion targeted for winter 2028.

The 297-unit, three-building phase now under construction is a subset of the full 450-unit rezoning envelope approved in 2022 — we haven’t found reporting reconciling exactly how the remaining units (including the two smaller townhome structures) fit into this same construction phase or a later one, and aren’t guessing.

Sources: Brooklyn Paper; 6sqft; New York YIMBY; Hoodline; NYC Planning ZAP

7

A Six-Lot Assemblage Becomes a 99-Unit Building

The existing storefronts at 42-50 Hoyt Street, November 2024, before redevelopment. Not the site's current condition. — Imagery: Google Street View
Address/Location48 Hoyt Street (42-50 Hoyt St. & 208 Livingston St.)
Developer/ApplicantWatermark Capital Group, via Hoyt Complex LLC
Project99-unit residential building on a 6-lot assemblage
StatusSite Assembled / Plans Filed
Latest UpdatePlans for the 99-unit building were filed with the city in December 2024, following the ground-lease signing that September

A Long-Term Lease, Not a Sale

Watermark Capital Group took control of six tax lots spanning 42-50 Hoyt Street and 208 Livingston Street through a 99-year ground lease valued at $10.1 million, signed with the property owner in September 2024. Plans for a 99-unit residential building followed that December.

Real estate trade coverage (PincusCo, Marketproof) places the site in Boerum Hill, matching NYC PLUTO parcel data (Community District 302, the same district used to resolve the nearby 110/92 Boerum Place boundary case above); some other sources label the same block “Downtown Brooklyn.” We haven’t found a confirmed demolition permit or construction start for the existing buildings on the assembled lots as of this writing.

Sources: PincusCo; Marketproof; NYC PLUTO parcel data (Socrata 64uk-42ks)

Capital & Transactions

Money Moving in Boerum Hill

A curated look at recent property sales and financing that help explain who’s buying, building, and lending in Boerum Hill right now. Drawn from New York City’s public ACRIS property records, not a complete log of every filing — we include only transactions that say something real about the neighborhood’s direction, and leave out routine paperwork, internal transfers, and deals we can’t explain responsibly.

Permanent Financing$42M

52 4th Avenue — “The Eleanor”Sep. 2026

A $42 million financing on a completed, leasing 9-story mixed-use building — consistent with a construction-to-permanent takeout loan now that the building (permits originally filed 2020) is finished and renting.

Borrower: 52 4th Ave Holdings LLC · Lenders: Alliant Credit Union, Counterpointe-MassMutual Mortgage Lending LLC · ACRIS record ↗ · Hush Street Deal record →

Site Assemblage Financing$6.5M

32-40 4th Avenue / 544-548 Pacific StreetAug. 2026

This Tracker already covers 546 Pacific Street as a filed 16-story, 180-foot development (Section 3, above) but reports only the DOB permit filing. This ACRIS record — spanning 32 & 40 4th Avenue and 544, 546 & 548 Pacific Street, the exact footprint of the filing — is the first confirmed detail of the underlying site assemblage and its financing.

Assembler: 32 4th Avenue LLC / 544 Pacific St LLC · Lender: S3 SB Real Estate Credit A Trust · ACRIS record ↗

Source: New York City’s public ACRIS property records. This module is reviewed and curated by Hush Street editors, not an automated feed, and will be updated as new, meaningful filings are confirmed.

Have a tip on a Boerum Hill project we should be tracking? Let us know.

By Updated Built from city filings and published reporting. About Hush Street