Inside the Plan to Turn the Watchtower Buildings Into 661 Brooklyn Heights Apartments

Renderings by Morris Adjmi Architects for CIM Group, published by New York YIMBY, showing the two expanded buildings from the water and a diagram of today’s structures against the proposed additions. YIMBY reports that the three low-rise buildings along Columbia Heights would keep their current rooflines. YIMBY wrote that, if everything is approved, construction could begin “early next year” and finish in 2029; no approval has been granted.Instagram · @yimbygram · posted Mar. 21, 2026

CIM Group wants to convert the century-old former Jehovah’s Witnesses world headquarters into 661 apartments — its third attempt to redevelop this waterfront site in a decade. This is a living dossier on what’s actually documented: the buildings, the money, the pitch, the process, and exactly how current “current status” really is.

Rezoning Filed — Environmental Review UnderwayFormal Public Review Not Yet StartedULURP application 2025K0150, filed Dec. 5, 2025; NYC Planning lists it as filed, not yet certified (checked Oct. 30, 2026)

Status checked October 30, 2026 against NYC Planning’s application record; the rest of this page was last fully verified August 28, 2026. See the Update Log at the bottom of this page.

Site25 and 30 Columbia Heights, Brooklyn Heights, plus frontage at 51-67 Furman Street
DeveloperCIM Group; designed by Morris Adjmi Architects
Homes661 total; 133–199 (20–30%) affordable, depending on the MIH option chosen
Size~925,000 gross sq ft per the ULURP filing; press often cites ~831,000
Zoning askM2-1 → M1-5A/R10A & M1-5A/R8A, plus a new Special Mixed-Use District
ApprovalULURP + CEQR Type I (Positive Declaration): a full environmental impact statement is required

The buildings at 25 and 30 Columbia Heights have already been three different things. They opened in the 1920s as a pharmaceutical plant. They spent nearly 50 years as the nerve center of a global religious publishing operation, marked by a red sign visible from half of Lower Manhattan. And for most of the past decade, they’ve been something closer to a real estate holding pattern — bought for $340 million, pitched as offices, abandoned as offices, and now pitched again, this time as apartments.

That third act is what this page tracks. CIM Group’s current proposal would add housing — a lot of it, 661 units — to two buildings that have sat mostly empty since a 2016 redevelopment plan fell apart. Getting there requires a full city land-use review. CIM filed its application in December 2025 and the environmental review is underway, but as of late October 2026 the formal public review, which starts with Community Board 2, had not begun.

Below: what’s actually known about the buildings and the site, who owns them and how that changed, what’s being proposed and how the pitch itself has shifted, where the approval process genuinely stands, and what’s been said — and not said — about it publicly.

The Buildings and the Site

A CIM Group photo of the complex under Curbed’s headline for Kim Velsey’s March 2026 story. Curbed notes that the red Watchtower sign was a Brooklyn landmark for nearly 50 years, and that the 700,000-square-foot complex, renovated for offices after the Jehovah’s Witnesses left, has stood largely vacant since.Instagram · @curbed · posted Mar. 24, 2026

What’s commonly described as “the Watchtower building” is really a complex of interconnected structures on two city blocks. The two named addresses — 25 Columbia Heights (12 stories) and 30 Columbia Heights (13 stories) — sit on four separate tax lots spanning two blocks, and the site’s footprint extends to frontage on Furman Street, one block over. Press coverage sometimes describes it as “five interconnected buildings,” consistent with that multi-lot layout. The two named towers are joined by a skybridge, which the current redevelopment plan would demolish.

The buildings predate the Jehovah’s Witnesses by more than 40 years. They were built in the 1920s as a manufacturing plant for the pharmaceutical company E.R. Squibb & Sons — designed by architect Russell G. Cory, with Walter M. Cory, and built by Turner Construction. The rooftop sign that would later become a Brooklyn Heights landmark originally read “Squibb,” not “Watchtower.”

That changed in 1969, when the Watchtower Bible and Tract Society — the Jehovah’s Witnesses’ publishing arm — acquired the buildings and made them a hub of the organization’s global printing and administrative operations. The sign was relettered, lit red, and remained a fixture of the Brooklyn and East River skyline for nearly 50 years, visible from Lower Manhattan and the Promenade alike.

The former Watchtower complex at 25-30 Columbia Heights seen from across the East River in 2020, with its Welcome sign visible
The complex in 2020, four years into its stalled office-conversion era — its “Watchtower” sign already replaced by “Welcome.” Photo by Andre Carrotflower via Wikimedia Commons, CC BY-SA 4.0.

That sign came down in 2017, replaced by a new one reading simply “Welcome” — installed not because of the current redevelopment, but during the buildings’ earlier, ultimately abandoned office-conversion era (see “Ownership and Developer History,” below). The building’s next visible transformation, if this proposal moves forward, would be physical rather than symbolic: 25 Columbia Heights would grow from 12 to 17 stories, and 30 Columbia Heights from 13 to 14.

One preservation question worth stating plainly: the site is not within the LPC-designated Brooklyn Heights Historic District — the first historic district ever designated in New York City, in 1965. Brooklyn Eagle’s coverage says so directly, and the Landmarks Preservation Commission’s own building database agrees: it lists none of the site’s four tax lots (Block 204, Lot 1; Block 208, Lots 1, 2 and 12), either inside a historic district or as an individual landmark, although rowhouses farther south on the same block are inside the district. That matters for what kind of fight this can become: without landmark status, objections here run through zoning and land-use review, not a Landmarks Preservation Commission hearing.

Ownership and Developer History

Commercial Observer’s graphic for its story on CIM Group’s filing, set against the building under its former Watchtower sign. CO reports that CIM and LIVWRK bought the five-building complex at 25 and 30–58 Columbia Heights for $340 million in 2016. Read CO’s story.Instagram · @commercial_observer · posted Mar. 13, 2026

The Jehovah’s Witnesses sold 25-30 Columbia Heights in August 2016, part of a broader divestment of the organization’s Brooklyn Heights real estate as it relocated its headquarters to Warwick, New York. The buyer was a joint venture — CIM Group, LIVWRK Holdings, and Kushner Companies — paying $340 million, one of the largest Brooklyn real estate deals on record at the time.

That trio’s plan was not housing. From 2016 through roughly 2018, they pursued “Panorama Brooklyn,” a Gensler-associated conversion into creative office space and retail, with renderings that included public garden and terrace amenities unveiled around August 2019. Kushner Companies exited the venture in 2018, and the office plan was ultimately abandoned — not merely paused. CIM Group is the only developer remaining from the original 2016 purchase.

What “vacant” actually means hereReporting describes the buildings as largely vacant for roughly seven years. That’s broadly accurate, but not the whole picture: in mid-2025, CIM leased 45,000 square feet at the complex — still under the “Panorama Brooklyn” name — to The Beginning Clubhouse, a family-focused membership club, with an opening anticipated for summer 2026. CIM was pursuing a residential rezoning and leasing space under the old office/retail plan at the same time. (Hush Street hasn’t been able to locate the original announcement, so treat the details as reported rather than confirmed.)

Roughly eight months before formally filing for the residential rezoning, in April 2025, CIM signed a $245 million refinancing covering 25 Columbia Heights and the Furman Street frontage. PincusCo’s report, paywalled beyond its headline figures, doesn’t name the lender or the loan’s purpose, but the timing is notable: CIM refinanced the office-era asset before formally committing, on paper, to abandoning that plan for housing.

The current applicant of record is 25-30 Columbia Heights (Brooklyn), LLC, a Delaware entity controlled by CIM Group. The person representing the company publicly is David Wellspring, CIM’s Vice President of Development, who has described the goal as converting “largely vacant former industrial buildings into a thoughtful mixed-use residential community,” including permanently affordable housing.

What They’re Proposing

An aerial rendering by CIM Group and Morris Adjmi Architects, posted by the Brooklyn Eagle, showing the enlarged buildings against the Brooklyn Heights rowhouses behind them, with the “Welcome” sign still on the roof. The Eagle reports that the renderings were shown to Community Board 2 in June 2025, ahead of the formal filing. It is a proposal, not an approved design.Instagram · @bkeagle · posted Mar. 3, 2026

The current plan, designed by Morris Adjmi Architects, would add five stories to 25 Columbia Heights (12 → 17 stories) and one story to 30 Columbia Heights (13 → 14 stories). Together, the two buildings would hold 661 residential units — 392 at 25 Columbia Heights, above 14,850 square feet of ground-floor commercial and community-facility space, and 269 at 30 Columbia Heights, alongside commercial/community-facility space and residential parking.

Affordable housing is required, but the exact final number isn’t yet fixed: the ULURP filing states a range of 133 to 199 units — 20 to 30% of the total — “pursuant to MIH depending on the option selected,” referring to the city’s Mandatory Inclusionary Housing program. Most press coverage has rounded that to a flat “25%, 165 units” figure, which is the range’s midpoint rather than a confirmed final commitment.

Parking is also part of the plan for the first time in any public account of this project: 188 residential spaces, totaling 61,000 square feet, housed at 30 Columbia Heights.

To build any of this, CIM needs the city to rezone the site — currently M2-1, a manufacturing district — to a split of M1-5A/R10A and M1-5A/R8A, within a newly created Special Mixed-Use District. That rezoning also requires a zoning text amendment establishing the new district and designating the project area as a Mandatory Inclusionary Housing area. None of this is as-of-right; it all depends on the land-use approval process described below.

What Changed

The most obvious change is the use itself: an office and retail conversion became a majority-residential one. But two smaller, more specific discrepancies are worth preserving rather than smoothing over, because they’re unresolved as of this writing, not because they’re dramatic.

Two different size figures, not yet reconciledThe ULURP filing itself states a total of approximately 925,000 gross square feet — 678,000 gsf residential, 186,000 gsf commercial/community-facility, and 61,000 gsf of parking. Multiple press accounts instead report roughly 831,000 or “over 800,000” square feet. It’s possible the press figure reflects an earlier version of the application, or an above-grade-only count — but no public document Hush Street has found settles which is current. This page uses the filing’s figure because it’s the primary source, but both numbers are in circulation.

The affordable-housing figure has a similar shape: what’s usually reported as a settled “25%” is, in the filing itself, a range tied to a choice CIM hasn’t yet made public. And the skybridge connecting the two towers — a physical feature preserved through the entire 2016-2019 office-conversion era — is now slated for demolition, which is as good a physical marker as any for how completely this plan departs from its predecessor.

The Approval Process — Where This Stands, and What Happens Next

This project needs a discretionary land-use approval, not an as-of-right permit, which means it moves through New York City’s Uniform Land Use Review Procedure: Department of City Planning review and environmental scoping, then Brooklyn Community Board 2, then the Brooklyn Borough President, then the City Planning Commission, then City Council hearings and a final vote. Because the rezoning triggers a full environmental review, the application also carries a CEQR Type I classification with a Positive Declaration — meaning a Draft Environmental Impact Statement is legally required, a materially more rigorous track than most as-of-right projects ever face.

Here’s what’s actually been documented, in order: the application was filed December 5, 2025. A public scoping meeting for the environmental review was held virtually on March 12, 2026. NYC Planning’s application record shows the latest filing step completed on April 13, 2026, and nothing since.

The single most important thing to know about “current status”Formal public review hasn’t started. NYC Planning lists the application as filed, not certified, and marks Community Board 2’s review and every later stage as not started (checked Oct. 30, 2026). That matches what the department told Gothamist in March: it looked forward “to this application starting public review in the future.” The most recent press coverage Hush Street has found dates from March 24, 2026. Until certification, there is no community board vote to report; once it happens, the board, the Borough President, the City Planning Commission and the City Council each get their turn. We’ll update this section when that changes.

If the review does proceed, DCP’s own environmental analysis projects the completed project would add roughly 1,446 residents to the area and remove roughly 1,752 workers by 2029 — the arithmetic of converting an office-era building back into housing. Multiple March 2026 press accounts, citing what was then described as a “typical” rezoning timeline of about seven months from filing, suggested construction could begin in early 2027 with completion targeted for 2029. With formal review not yet begun more than ten months after filing, that projected schedule should now be read as optimistic rather than on track.

Preservation and Community Response

A former Watchtower Bible and Tract Society building on Columbia Heights, Brooklyn Heights
The former Watch Tower Bible and Tract Society world headquarters on Columbia Heights. Photo by Sergio Herrera via Wikimedia Commons, CC BY-SA 2.0.

Hush Street hasn’t found organized opposition to this specific 2026 proposal — no petitions, formal objection letters or mobilized civic group — and won’t manufacture a fight that isn’t documented. What does exist is narrower and more specific than a blanket dispute.

“It’s one of the most famous views in the world, and we want to make sure that any development on this site has no impact on the view plane.”Lincoln Restler, NYC Councilmember, ahead of the March 12, 2026 scoping meeting

Restler’s position is more conditional support than either cheerleading or opposition. In the same appearance, he argued for activating a site that’s “essentially sat vacant for six or seven years” amid a citywide housing shortage — but he specifically flagged the Brooklyn Bridge view corridor from the Promenade as something any approval needs to protect. Separately, at least one outlet has reported general resident concern about the scale of the proposed height increase, though without naming anyone, so treat it as a report rather than a confirmed quote.

There’s a deeper institutional backstory worth knowing, even though it doesn’t connect directly to this proposal: the Brooklyn Heights Association has a documented history of opposing earlier Watchtower-era construction on this general site decades ago, including a blocked 30-story tower proposal and unsuccessful opposition to a Jehovah’s Witnesses dormitory. Nothing Hush Street has found ties BHA’s historical opposition to any current position on the 2026 residential plan — it’s context, not evidence of an active fight.

The honest summary: the loudest documented reaction so far is a local Councilmember’s specific, narrow condition about protecting a skyline view — not a preservation battle, not organized resident opposition, and not the kind of fight this site has seen before. Whether that changes once formal public review begins is one of the open questions this page exists to track.

Timeline

Full timeline · 12 entries
1920s
Built as a Squibb pharmaceutical plant

Constructed for E.R. Squibb & Sons, designed by architect Russell G. Cory with Walter M. Cory, built by Turner Construction Company. The rooftop sign originally read “Squibb.”

1969
Jehovah’s Witnesses acquire the complex

The Watchtower Bible and Tract Society buys the buildings; the rooftop sign is relettered “Watchtower” and becomes a fixture of the Brooklyn/East River skyline.

Aug. 2016
Sold for $340 million

Jehovah’s Witnesses sell the complex as part of relocating their headquarters to Warwick, NY. Buyer: a joint venture of CIM Group, LIVWRK Holdings, and Kushner Companies.

2016–2018
“Panorama Brooklyn” office conversion pursued

The venture pursues a Gensler-associated creative-office and retail conversion. Public garden/amenity renderings are unveiled around August 2019.

2017
“Watchtower” sign replaced with “Welcome”

The nearly 50-year-old red sign comes down; a new sign reading “Welcome” goes up in its place.

2018
Kushner Companies exits

Kushner Companies leaves the joint venture; the office conversion plan is ultimately abandoned. CIM Group remains, alongside LIVWRK.

Apr. 2025
$245 million refinancing

CIM refinances 25 Columbia Heights and 51-67 Furman Street — roughly eight months before formally filing for a residential rezoning.

~Jun. 2025
Informal presentation to CB2

CIM and Morris Adjmi Architects informally present the residential-conversion concept to Community Board 2, ahead of any formal filing.

Dec. 5, 2025
ULURP application filed

Application 2025K0150 is formally filed with the NYC Department of City Planning.

Mar. 12, 2026
DCP public scoping meeting

A virtual environmental-review scoping meeting is held. Councilmember Lincoln Restler speaks in favor of activating the vacant site while raising a specific concern about the Brooklyn Bridge view plane.

Apr. 13, 2026
Latest application step recorded

NYC Planning’s application record marks its most recent filing step complete. No later step is recorded.

Not yet started
Formal public review

Once City Planning certifies the application, it goes to Community Board 2, the Borough President, the City Planning Commission and the City Council. As of Oct. 30, 2026, NYC Planning lists every one of those steps as not started.

Primary Documents and Sources

Update Log

Oct. 30, 2026
Correction: earlier versions said Community Board 2’s land use committee discussed this application on March 18, 2026, and that the full board was scheduled to vote on April 9. The minutes cited for that were from Queens Community Board 2 and concerned a different application. NYC Planning’s record shows formal public review, including the community board stage, has not started; the status, timeline and approval sections now say so. Also confirmed the site’s landmark status against LPC’s building database, and redesigned the page’s opening.
Aug. 28, 2026
First published. Reporting drew on NYC City Planning and NYSDEC environmental review filings, ACRIS and LEI ownership records, and press coverage through March 2026, with a second look at community response and later status.

This Spotlight expands on and supersedes the Watchtower entry in Hush Street’s Brooklyn Heights development tracker, which links here.