Brooklyn Marine Terminal: Inside the $3.5 Billion Plan to Remake Red Hook’s Waterfront
A working container port on the Red Hook waterfront is about to become one of the largest redevelopment sites in New York City — without ceasing to be a port. The $3.5 billion Brooklyn Marine Terminal plan pairs a modernized, all-electric terminal with 6,000 new apartments and 28 acres of public waterfront, approved only after the city cut its own housing count nearly in half to get it passed. Here’s what’s actually been decided, what’s still just a target date, and what happens next.
Last verified August 30, 2026. This page tracks the Brooklyn Marine Terminal specifically — for everything else being built across the neighborhood, see the Red Hook development tracker.
The Brooklyn Marine Terminal isn’t an empty lot waiting for a developer. It’s a working port — gantry cranes, container ships, a cruise terminal — that the city now wants to shrink, modernize, and build an entire neighborhood around.
That idea has existed in some form since May 2024, when the city took over operating the site from the Port Authority. It became a real, votable plan in September 2025, after a fight over how much housing was too much.
Below: what the approved plan actually builds, how it got cut down to get there, what happens to the port and the jobs tied to it, and exactly how far the city has — and hasn’t — gotten toward breaking ground.
The Plan: A Smaller Port, a New Neighborhood Around It
Strip away the acronyms and the plan is fairly simple to state. NYCEDC wants to shrink the working port’s footprint, rebuild what remains as an all-electric operation, and use the freed-up land for housing, open space, and a cruise terminal.
The port itself would shrink to a 60-acre, all-electric container and maritime terminal — part of the city’s Blue Highways push to move freight by barge and ferry instead of truck. Everything else in the 122-acre site gets split into two districts: BMT North, with new homes, open space, light-industrial and commercial space, and a public school; and Atlantic Basin, where a rebuilt Brooklyn Cruise Terminal, a 400-key hotel, and more open space would replace Piers 11 and 12’s current uses.
In total: 6,000 apartments, 28 acres of public open space, roughly 275,000 square feet each of commercial and discounted-rent industrial space, and 250,000 square feet of community space. A new public body, the Brooklyn Marine Terminal Development Corporation — a board of elected officials and community members — is meant to oversee construction and hold the city to its own commitments.
Of the 6,000 units, 40% (2,400) would be permanently affordable at an average of 60% of area median income, with 25% family-sized. NYCEDC projects 37,000 construction jobs and 2,000 permanent ones, and $418 million in city, state and federal funding is already committed toward the $3.5 billion total. The plan was drawn up by Buro Happold (planning), WXY (urban design and engagement) and SCAPE (landscape).
A Plan Cut in Half to Pass
The Vision Plan didn’t arrive at 6,000 apartments by design. It arrived there by negotiation, after opposition nearly killed the whole thing.
Earlier versions of the plan proposed roughly 12,000 units. Brooklyn Borough President Antonio Reynoso, an early and vocal opponent, argued that scale would overwhelm Red Hook’s transit, schools, and streets — and threatened to sink the vote. Time Out New York, citing the negotiation directly, reported that “negotiators reduced the housing count from 12,000 to 6,000 units” in exchange for more industrial space and stronger independent oversight, which is what became the Brooklyn Marine Terminal Development Corporation.
That trade — less housing for more industrial space and oversight — is also why the plan bypasses the city’s standard land-use review. Like Atlantic Yards two decades earlier, it moves through a state General Project Plan overseen by Empire State Development rather than the City Council’s Uniform Land Use Review Procedure (ULURP). NYCEDC remains the agency actually running the project day to day, but ESD’s board, not the Council, holds final sign-off — a real governance trade-off that both eased the plan’s path to approval and removed it from the city’s normal public-review track.
The Working Port Underneath the Plan
None of this starts from a blank site. The Red Hook Container Terminal has run for decades under an operator, and it doesn’t stop running while the plan moves through approvals.
When operational control shifted from the Port Authority to NYCEDC in May 2024, Red Hook Terminals got a five-year lease extension and $95 million in interim investment — pier repairs, a new electrified ship-to-shore crane, and early resiliency work — years before the Vision Plan existed in its current form. NYCEDC has since executed a further $18 million in maritime infrastructure contracts, including demolishing four decommissioned cranes and installing a new all-electric one.
What happens to that operation long-term is still an open question, not a settled one. The October 2025 RFEI is NYCEDC testing the market for how a modernized, smaller port should actually be configured and who should run it — a decision the city says it won’t make until the first operator RFP goes out, targeted for late 2026. NYCEDC’s own figures project 495 new and preserved maritime jobs in the finished plan, out of 2,000 total permanent jobs; the plan doesn’t frame this as a guarantee that every existing job or role survives the transition, only as its own forward-looking floor.
Free to embed with attribution and a link to Hush Street.
Getting There: Transportation and the Public Realm
Right now, Red Hook’s waterfront is largely inaccessible — walled off by an active industrial port with no public route along the water. The Vision Plan’s 28 acres of open space and nearly a mile of new waterfront access, including a greenway extension linking toward Brooklyn Bridge Park, are meant to change that directly.
Getting people there without more car traffic is its own piece of the plan. NYCEDC’s framework calls for bus-priority lanes, expanded NYC Ferry service, an electric shuttle, and a push for a direct-to-Manhattan bus route through the MTA. Separately, DOT floated a “car-lite” concept in August 2026 for Van Brunt and Columbia Streets — forced turns, a bus- and truck-priority corridor, and a car-free plaza at Columbia and Hamilton — and a second NYC Ferry Homeport at Atlantic Basin is due to open in 2027, meant to serve a projected 6,000 new residents.
Both of those are explicitly downstream of construction actually starting on the larger plan, which the city itself says is still years off. They’re the clearest sign of what this project looks like once it’s more than a plan — not evidence that it’s imminent.
Where This Stands Now, and What Happens Next
Approved is not the same as done. As of this writing, the Vision Plan has cleared its task force vote and nothing else — no environmental impact statement has been finalized, no General Project Plan has been adopted, and no port operator has been selected.
The environmental review is the actual gate everything else waits behind. It runs under both the state’s SEQRA process and the city’s CEQR process, with the NYC Deputy Mayor’s Office for Housing, Economic Development and Workforce serving as lead agency and the consulting firm AKRF conducting the underlying studies. Draft scope of work meetings have been held; a full draft Environmental Impact Statement, plus a public hearing and comment period on both the EIS and ESD’s own initially adopted GPP, are still ahead.
Empire State Development is targeting fall 2026 to formally adopt the General Project Plan — the approval that actually lets construction begin. NYCEDC, in parallel, is aiming to release its first RFP for a long-term port operator by the end of 2026, following up on the RFEI responses it collected in December 2025. Neither of those is guaranteed to land on schedule; both are the city’s own stated targets, not commitments.
What isn’t yet public: an actual construction start date, a finalized site plan beyond the August 2026 BMT North/Atlantic Basin update, or which company will eventually operate the port. Hush Street will update this page as each of those resolves.
The All-Maritime Counter-Proposal
Timeline
Full timeline · 9 entries
NYCEDC assumes operational control of the full 100+-acre marine terminal. Red Hook Terminals gets a 5-year operator lease extension plus $95 million in interim pier repairs, crane replacement, and early resiliency work.
NYCEDC runs 34 task force meetings and office hours, 27 public workshops, 3 town halls, and 9 sessions specifically with NYCHA’s Red Hook Houses — engaging a reported 4,265 people before any vote.
The BMT Task Force delays its vote on the Vision Plan five separate times over congestion, transparency, and port-jobs concerns — and, per Brooklyn Borough President Antonio Reynoso’s own account, over the housing count itself.
The Task Force approves the $3.5 billion plan after negotiators cut the housing count from roughly 12,000 units to 6,000 and added more space for industry and independent oversight.
NYCEDC releases a Request for Expressions of Interest (RFEI) to gauge market appetite for running the modernized port. Six respondent groups, including Ports America and Carrix/SSA Marine, submit interest by the Dec. 15, 2025 deadline.
The project enters formal SEQRA/CEQR review, with the NYC Deputy Mayor’s Office for Housing, Economic Development and Workforce as lead agency and AKRF conducting the Environmental Impact Statement. Public meetings on the draft scope of work follow.
NYCEDC holds a public information session sharing more specific BMT North and Atlantic Basin site-plan details — circulation, urban design, and open-space layout — for the first time.
Empire State Development is targeting this window to adopt the GPP, after a public hearing and comment period on the draft Environmental Impact Statement — the last formal approval standing between the Vision Plan and construction.
NYCEDC aims to move from the RFEI to an actual Request for Proposals for a long-term port operator — the step that would put a real company in charge of running the future 60-acre terminal.
Primary Documents and Sources
- GovernmentNYCEDC — Brooklyn Marine Terminal project page
- GovernmentEmpire State Development — BMT Redevelopment Project page
- GovernmentNYCEDC — Brooklyn Marine Terminal Vision Plan Fact Sheet, Nov. 2025
- GovernmentNYCEDC — Task Force approval press release, Sept. 2025
- GovernmentNYCEDC — Port operator RFEI press release, Oct. 2025
- GovernmentGovernor’s office — Port Authority handoff announcement, May 2024
- GovernmentGovernor’s office — Vision Plan passage announcement, Sept. 2025
- ReportingNY1
- ReportingCrain’s New York Business
- ReportingTime Out New York
- ReportingGothamist
- ReportingNew York YIMBY
- ReportingThe Architect’s Newspaper — design team
- ReportingStreetsblog NYC
- ReportingThe Maritime Executive
- ReferenceRed Hook Terminals — current operator
Update Log
This Spotlight expands on Hush Street’s Brooklyn Marine Terminal coverage in the Red Hook development tracker, which links here for the fuller story. Full source list and research notes: internal registry, available on request.
By Hush Street Editorial Updated Built from city filings and published reporting. About Hush Street