Brooklyn Marine Terminal: Inside the $3.5 Billion Plan to Remake Red Hook’s Waterfront

An NYCEDC rendering of the approved Vision Plan laid over an aerial view of Brooklyn, with new buildings and green space along the terminal’s waterfront. The agency posted it after the Task Force’s approval vote, presenting the plan as part of the city’s “Harbor of the Future” push to move more freight by water and fewer goods by truck. It shows the plan’s intent, not the site today.Instagram · @nycedc · posted Sept. 22, 2025

A working container port on the Red Hook waterfront is about to become one of the largest redevelopment sites in New York City — without ceasing to be a port. The $3.5 billion Brooklyn Marine Terminal plan pairs a modernized, all-electric terminal with 6,000 new apartments and 28 acres of public waterfront, approved only after the city cut its own housing count nearly in half to get it passed. Here’s what’s actually been decided, what’s still just a target date, and what happens next.

Vision Plan Approved — Environmental Review UnderwayConstruction Not Yet StartedSEQRA/CEQR review in progress; ESD targeting fall 2026 for General Project Plan adoption

Last verified August 30, 2026. This page tracks the Brooklyn Marine Terminal specifically — for everything else being built across the neighborhood, see the Red Hook development tracker.

Site122 acres of city-owned waterfront from Pier 7 (Atlantic Ave.) to Pier 12, in Red Hook and the Columbia Street Waterfront District
Cost$3.5 billion; $418M in city, state and federal funding already committed
Homes6,000 units, 40% (2,400) permanently affordable
Port60-acre modernized, all-electric container & maritime terminal
Open space28 acres, plus nearly 1 mile of new waterfront access
ApprovalState General Project Plan (SEQRA/CEQR) under Empire State Development — bypasses the city’s standard ULURP process; NYC Economic Development Corporation runs the project day to day

The Brooklyn Marine Terminal isn’t an empty lot waiting for a developer. It’s a working port — gantry cranes, container ships, a cruise terminal — that the city now wants to shrink, modernize, and build an entire neighborhood around.

That idea has existed in some form since May 2024, when the city took over operating the site from the Port Authority. It became a real, votable plan in September 2025, after a fight over how much housing was too much.

Below: what the approved plan actually builds, how it got cut down to get there, what happens to the port and the jobs tied to it, and exactly how far the city has — and hasn’t — gotten toward breaking ground.

The Plan: A Smaller Port, a New Neighborhood Around It

NYCEDC’s Vision Plan slides, posted two months before the Task Force vote. Beyond the housing, the agency described industrial space meant to grow local jobs, plus community facilities and cultural space within the mixed-use districts. These are planning graphics: no developer has been chosen, and the details are on NYCEDC’s project page.Instagram · @nycedc · posted July 9, 2025

Strip away the acronyms and the plan is fairly simple to state. NYCEDC wants to shrink the working port’s footprint, rebuild what remains as an all-electric operation, and use the freed-up land for housing, open space, and a cruise terminal.

The port itself would shrink to a 60-acre, all-electric container and maritime terminal — part of the city’s Blue Highways push to move freight by barge and ferry instead of truck. Everything else in the 122-acre site gets split into two districts: BMT North, with new homes, open space, light-industrial and commercial space, and a public school; and Atlantic Basin, where a rebuilt Brooklyn Cruise Terminal, a 400-key hotel, and more open space would replace Piers 11 and 12’s current uses.

In total: 6,000 apartments, 28 acres of public open space, roughly 275,000 square feet each of commercial and discounted-rent industrial space, and 250,000 square feet of community space. A new public body, the Brooklyn Marine Terminal Development Corporation — a board of elected officials and community members — is meant to oversee construction and hold the city to its own commitments.

Of the 6,000 units, 40% (2,400) would be permanently affordable at an average of 60% of area median income, with 25% family-sized. NYCEDC projects 37,000 construction jobs and 2,000 permanent ones, and $418 million in city, state and federal funding is already committed toward the $3.5 billion total. The plan was drawn up by Buro Happold (planning), WXY (urban design and engagement) and SCAPE (landscape).

A Plan Cut in Half to Pass

Posted by Council Member Alexa Avilés, who represents Red Hook, after she joined the group Voices of the Waterfront and constituents to protest the Task Force’s final vote. In the post she calls the vote rushed and argues the plan would add traffic and pollution, put thousands of homes in a flood zone without a resilience plan, and push gentrification that affects public-housing residents. Those are her objections; the Task Force approved the plan that month.Instagram · @nyc_council38 · posted Sept. 20, 2025

The Vision Plan didn’t arrive at 6,000 apartments by design. It arrived there by negotiation, after opposition nearly killed the whole thing.

Earlier versions of the plan proposed roughly 12,000 units. Brooklyn Borough President Antonio Reynoso, an early and vocal opponent, argued that scale would overwhelm Red Hook’s transit, schools, and streets — and threatened to sink the vote. Time Out New York, citing the negotiation directly, reported that “negotiators reduced the housing count from 12,000 to 6,000 units” in exchange for more industrial space and stronger independent oversight, which is what became the Brooklyn Marine Terminal Development Corporation.

A number that moved more than onceCoverage of the plan’s evolution isn’t fully consistent on the path between 12,000 and 6,000: some accounts cite an intermediate figure of roughly 7,700 units at an earlier negotiation stage. That number wasn’t independently traced to a primary NYCEDC or task force document in reporting this page — the clean, sourced endpoints are 12,000 (an earlier proposal) and 6,000 (what the task force actually approved in September 2025).

That trade — less housing for more industrial space and oversight — is also why the plan bypasses the city’s standard land-use review. Like Atlantic Yards two decades earlier, it moves through a state General Project Plan overseen by Empire State Development rather than the City Council’s Uniform Land Use Review Procedure (ULURP). NYCEDC remains the agency actually running the project day to day, but ESD’s board, not the Council, holds final sign-off — a real governance trade-off that both eased the plan’s path to approval and removed it from the city’s normal public-review track.

The Working Port Underneath the Plan

Del Bobish, chief operating officer of Red Hook Terminals, as NYCEDC identifies him, on the terminal’s new all-electric crane. NYCEDC says the crane will move goods to market faster, strengthen the city’s food supply and support hundreds of jobs over its lifetime. It is equipment for today’s working port, not part of the redevelopment, which has not broken ground.Instagram · @nycedc · posted Aug. 17, 2026

None of this starts from a blank site. The Red Hook Container Terminal has run for decades under an operator, and it doesn’t stop running while the plan moves through approvals.

When operational control shifted from the Port Authority to NYCEDC in May 2024, Red Hook Terminals got a five-year lease extension and $95 million in interim investment — pier repairs, a new electrified ship-to-shore crane, and early resiliency work — years before the Vision Plan existed in its current form. NYCEDC has since executed a further $18 million in maritime infrastructure contracts, including demolishing four decommissioned cranes and installing a new all-electric one.

What happens to that operation long-term is still an open question, not a settled one. The October 2025 RFEI is NYCEDC testing the market for how a modernized, smaller port should actually be configured and who should run it — a decision the city says it won’t make until the first operator RFP goes out, targeted for late 2026. NYCEDC’s own figures project 495 new and preserved maritime jobs in the finished plan, out of 2,000 total permanent jobs; the plan doesn’t frame this as a guarantee that every existing job or role survives the transition, only as its own forward-looking floor.

Brooklyn Marine Terminal, By the NumbersSix figures that show what this plan actually trades, builds, and still hasn’t done.
A .5 billion redevelopment plan covers 122 acres of Red Hook waterfront, approved September 2025, with a projected 8 billion-plus economic impact.
The approved Vision Plan is a .5 billion redevelopment of 122 acres of Red Hook's working waterfront.
View full sizeDownload PNG
Copy embed code
Chart: the Brooklyn Marine Terminal redevelopment plan for the Red Hook waterfront was cut from 12,000 proposed apartments in an earlier version to 6,000 in the plan approved in September 2025, with 2,400 units, or 40 percent, permanently affordable.
Negotiators cut the Brooklyn Marine Terminal plan's housing count from 12,000 proposed apartments to the 6,000 approved in September 2025 -- 40% of which are permanently affordable.
View full sizeDownload PNG
Copy embed code
Chart: the Brooklyn Marine Terminal plan keeps a 60-acre modernized, all-electric working port on site, preserving or creating 495 maritime jobs.
The plan keeps a 60-acre, all-electric working port on site rather than replacing it with housing.
View full sizeDownload PNG
Copy embed code
Chart: the Brooklyn Marine Terminal plan is projected to generate 37,000 construction jobs during the build-out and 2,000 permanent jobs once complete.
NYCEDC projects 37,000 construction jobs during the build-out and 2,000 permanent jobs once it's built.
View full sizeDownload PNG
Copy embed code
Chart: the Brooklyn Marine Terminal plan includes 28 acres of new public open space and nearly a mile of new public waterfront access, plus 250,000 square feet of community space.
The plan adds 28 acres of public open space and nearly a mile of new waterfront access.
View full sizeDownload PNG
Copy embed code
Chart: Empire State Development is targeting fall 2026 to adopt the Brooklyn Marine Terminal's General Project Plan, with NYCEDC aiming to release its first port-operator RFP by late 2026.
Fall 2026 is the state's own target to adopt the General Project Plan -- the approval construction actually depends on.
View full sizeDownload PNG
Copy embed code

Free to embed with attribution and a link to Hush Street.

Getting There: Transportation and the Public Realm

An earlier NYCEDC video on waterfront access. It proposed more than 5,000 linear feet of waterfront, 30-plus acres of public open space and a new greenway for bikes and pedestrians. The approved plan settled on 28 acres of open space, so read this as an earlier proposal rather than the final design.Instagram · @nycedc · posted May 16, 2025

Right now, Red Hook’s waterfront is largely inaccessible — walled off by an active industrial port with no public route along the water. The Vision Plan’s 28 acres of open space and nearly a mile of new waterfront access, including a greenway extension linking toward Brooklyn Bridge Park, are meant to change that directly.

Getting people there without more car traffic is its own piece of the plan. NYCEDC’s framework calls for bus-priority lanes, expanded NYC Ferry service, an electric shuttle, and a push for a direct-to-Manhattan bus route through the MTA. Separately, DOT floated a “car-lite” concept in August 2026 for Van Brunt and Columbia Streets — forced turns, a bus- and truck-priority corridor, and a car-free plaza at Columbia and Hamilton — and a second NYC Ferry Homeport at Atlantic Basin is due to open in 2027, meant to serve a projected 6,000 new residents.

Both of those are explicitly downstream of construction actually starting on the larger plan, which the city itself says is still years off. They’re the clearest sign of what this project looks like once it’s more than a plan — not evidence that it’s imminent.

Where This Stands Now, and What Happens Next

Approved is not the same as done. As of this writing, the Vision Plan has cleared its task force vote and nothing else — no environmental impact statement has been finalized, no General Project Plan has been adopted, and no port operator has been selected.

The environmental review is the actual gate everything else waits behind. It runs under both the state’s SEQRA process and the city’s CEQR process, with the NYC Deputy Mayor’s Office for Housing, Economic Development and Workforce serving as lead agency and the consulting firm AKRF conducting the underlying studies. Draft scope of work meetings have been held; a full draft Environmental Impact Statement, plus a public hearing and comment period on both the EIS and ESD’s own initially adopted GPP, are still ahead.

Empire State Development is targeting fall 2026 to formally adopt the General Project Plan — the approval that actually lets construction begin. NYCEDC, in parallel, is aiming to release its first RFP for a long-term port operator by the end of 2026, following up on the RFEI responses it collected in December 2025. Neither of those is guaranteed to land on schedule; both are the city’s own stated targets, not commitments.

What isn’t yet public: an actual construction start date, a finalized site plan beyond the August 2026 BMT North/Atlantic Basin update, or which company will eventually operate the port. Hush Street will update this page as each of those resolves.

The All-Maritime Counter-Proposal

The Brooklyn Eagle’s report on an alternative from City Club of New York trustee Tom Fox: an “all-maritime” Blue Highway hub with no housing, at roughly $1 billion in public investment, about a third of the approved plan’s cost. It is an outside proposal with no official standing. The image is credited to NYCEDC and does not depict Fox’s plan.Instagram · @bkeagle · posted Feb. 2, 2026

Timeline

Full timeline · 9 entries
May 2024
City takes over the port from the Port Authority

NYCEDC assumes operational control of the full 100+-acre marine terminal. Red Hook Terminals gets a 5-year operator lease extension plus $95 million in interim pier repairs, crane replacement, and early resiliency work.

2024–2025
A two-year public planning process

NYCEDC runs 34 task force meetings and office hours, 27 public workshops, 3 town halls, and 9 sessions specifically with NYCHA’s Red Hook Houses — engaging a reported 4,265 people before any vote.

2025
Five postponed votes

The BMT Task Force delays its vote on the Vision Plan five separate times over congestion, transparency, and port-jobs concerns — and, per Brooklyn Borough President Antonio Reynoso’s own account, over the housing count itself.

Sept. 22, 2025
Vision Plan approved, 17–8

The Task Force approves the $3.5 billion plan after negotiators cut the housing count from roughly 12,000 units to 6,000 and added more space for industry and independent oversight.

Oct. 2, 2025
Port-operator search opens

NYCEDC releases a Request for Expressions of Interest (RFEI) to gauge market appetite for running the modernized port. Six respondent groups, including Ports America and Carrix/SSA Marine, submit interest by the Dec. 15, 2025 deadline.

Early 2026
Environmental review begins

The project enters formal SEQRA/CEQR review, with the NYC Deputy Mayor’s Office for Housing, Economic Development and Workforce as lead agency and AKRF conducting the Environmental Impact Statement. Public meetings on the draft scope of work follow.

Aug. 2026
Site-plan details go public

NYCEDC holds a public information session sharing more specific BMT North and Atlantic Basin site-plan details — circulation, urban design, and open-space layout — for the first time.

Fall 2026 (targeted)
General Project Plan adoption

Empire State Development is targeting this window to adopt the GPP, after a public hearing and comment period on the draft Environmental Impact Statement — the last formal approval standing between the Vision Plan and construction.

Late 2026 (targeted)
First port-operator RFP

NYCEDC aims to move from the RFEI to an actual Request for Proposals for a long-term port operator — the step that would put a real company in charge of running the future 60-acre terminal.

Primary Documents and Sources

Update Log

Oct. 29, 2026
Added photos and video embedded from public Instagram posts by NYCEDC, Council Member Alexa Avilés and the Brooklyn Eagle. No reporting changed.
Aug. 30, 2026
First publication of this Spotlight. Built on Hush Street’s Aug. 29, 2026 Red Hook development tracker reporting, expanded with a targeted current-status pass: NYCEDC’s Nov. 2025 Vision Plan Fact Sheet, the Empire State Development and NYCEDC project pages, the Oct. 2025 port-operator RFEI, and reporting on the Aug. 2026 BMT North/Atlantic Basin public information session. Adds the environmental-review status, the RFEI/RFP timeline, and jobs/open-space figures not previously published on Hush Street. The intermediate ~7,700-unit figure in the plan’s negotiation history remains unresolved to a primary source — see “A Plan Cut in Half to Pass.”

This Spotlight expands on Hush Street’s Brooklyn Marine Terminal coverage in the Red Hook development tracker, which links here for the fuller story. Full source list and research notes: internal registry, available on request.