520 Fifth Avenue: A 1,002-Foot Supertall Above Bryant Park

520 Fifth Avenue, viewed from above, January 2026.
520 Fifth Avenue, viewed from above, January 2026. Photo by BoringEdits via Wikimedia Commons, CC BY-SA 4.0.

Kohn Pedersen Fox’s 1,002-foot tower one block north of Bryant Park stacks boutique offices, 100 condominiums and the Moss private club on a slender Fifth Avenue corner.

Fifth Avenue, Midtown Manhattan
Under Construction Mixed-use supertall · Updated September 2026
Address520 Fifth Avenue, New York, NY 10036
Height1,002 ft (tallest residential building on Fifth Avenue)
ArchitectKohn Pedersen Fox
Program100 condos (floors 42–80); about 200,000 sq ft of offices (floors 9–34)
SalesMore than 95% sold
DeveloperRabina Properties, LLC (Mickey Rabina)
Review TrackAs-of-Right
From Hush Street’s project record, updated Sep. 1, 2026
Latest Update — September 2026
Construction at 520 Fifth Avenue substantially wrapped up in mid-to-late 2026, more than a year after the tower topped out at 1,002 feet. Residential closings have commenced, more than 95% of its 100 condominium units have sold, the first office tenants have signed leases, and the building’s private club, Moss, opened on the lower floors in November 2025.

What Is 520 Fifth Avenue?

A close look up the facade at the tower’s arched window frames, posted by architect Kohn Pedersen Fox when the building topped out in October 2024. KPF says the arches and step-backs are meant to echo Midtown’s classic prewar towers.Instagram · @kohnpedersenfox · posted Oct. 25, 2024

520 Fifth Avenue is a mixed-use supertall skyscraper at the northwest corner of Fifth Avenue and West 43rd Street, one block north of Bryant Park. Designed by Kohn Pedersen Fox for developer Rabina Properties, the tower rises 1,002 feet — Wikipedia records it at 76 floors, while KPF’s own project materials and several press accounts describe an 88-story building, a discrepancy that likely reflects different conventions for counting mechanical and cellar levels rather than one source correcting the other.

The building stacks three distinct programs: roughly 200,000 square feet of boutique office space across floors 9 through 34, 100 condominium residences from floors 42 to 80, and a private members’ club, Moss, occupying the lower floors alongside ground-level retail and dining.

KPF describes the design as “an 88-story vertical village,” using a pencil-thin profile (a roughly 15:1 height-to-width ratio), arched windows, fluted piers, and setback terraces inspired by prewar New York towers — among them the Fred F. French Building and the Century Association clubhouse a few blocks away.

Location

520 Fifth Avenue, via Google Street View. Google's own imagery date may not reflect current completion status. — Imagery: Google Street View

520 Fifth Avenue sits on Fifth Avenue at West 43rd Street, one block north of Bryant Park and the New York Public Library’s main branch. View on Google Maps.

Assembling the Site

The tower’s footprint combines three older parcels: 516 and 518 Fifth Avenue, both retail and office buildings, and a smaller office building at 520 Fifth Avenue itself, most recently a gift shop. In the 19th century the site held the Colored Orphan Asylum, which burned down during the 1863 New York City draft riots.

Developer Aby Rosen’s RFR Realty owned 516 and 518 Fifth Avenue before the 2008 financial crisis derailed an earlier redevelopment attempt. Thor Equities bought the buildings in 2012, then sold the assembled site to a Ceruzzi Properties/SMI USA joint venture for $325 million in 2015. Mickey Rabina bought the site for $205 million in 2019 and filed plans for the current tower in 2021.

Construction and Financing

The tower with its tower crane still attached and the Empire State Building beyond, in May 2025 as the final curtain wall panels went in. The B1M credits the construction images to photographer @skyalign and the facade work to Alubuild USA.Instagram · @theb1m · posted May 22, 2025

Construction began March 1, 2022, backed by an initial $110 million mortgage from Bank OZK and, later that year, $540 million in combined construction financing from Bank OZK and The Carlyle Group. The tower topped out at its full 1,002-foot height in October 2024, by which point roughly 60% of the condominium units were already sold.

Facade work continued through 2025, with cladding reaching the pinnacle around mid-year and the exterior largely complete by December 2025 — the same month Rabina secured a $640 million refinancing loan from Carlyle. Corcoran Sunshine Marketing Group has handled residential sales since the April 2024 launch, when units started at $1.7 million; a full-floor penthouse sale pushed the building past 85% sold by February 2025, and the highest penthouse sale on record closed at $12 million in May 2026.

The first office tenants, including JAB Holding Company (owner of Krispy Kreme) and Texas Capital Bank, signed leases in July 2025. By August 2026, New York YIMBY reported construction had substantially wrapped up.

Moss and the Building’s Amenities

Bar Babette inside Moss, the private members’ club on the tower’s lower floors, from a Surface magazine feature made with the club. Surface credits the interiors to Charles & Co.Instagram · @surfacemag · posted Mar. 9, 2026

Moss, a roughly 40,000-square-foot private members’ club spanning four of the building’s lower floors, opened in November 2025. It includes a restaurant (Babette), Turkish baths, lounges, and a pickleball court; condo residents receive two memberships to the club as part of their purchase.

The tower also carries a 500-ton tuned mass damper in its top five stories to counteract wind sway — a common feature on slender residential supertalls — along with three separate lobbies for its residential, office, and club programs, and operable windows in the office floors, an unusual amenity in a New York office tower built after 1961.

Timeline

Full timeline · 15 entries
1863
The Colored Orphan Asylum, which stood at the site, burns in the New York City draft riots

The earliest documented structure on the assembled site.

2012
Thor Equities buys 516 and 518 Fifth Avenue

Two of the three retail/office buildings later assembled for the tower site.

2015
A Ceruzzi Properties/SMI USA joint venture buys the assembled site for $325 million
2019
Mickey Rabina buys the site for $205 million
2021
Rabina files plans for an 88-story mixed-use skyscraper

Designed by Kohn Pedersen Fox.

2022-03-01
Construction begins

Alongside $540 million in combined construction financing from Bank OZK and The Carlyle Group.

2023-10
Facade installation is underway
2024-04
Residential sales launch

Apartments start at $1.7 million.

2024-10
The building tops out at 1,002 feet

60% of units are reported sold at the same milestone.

2025-02
85% of units sold

Following the sale of a full-floor penthouse.

2025-05 to 2025-06
Cladding reaches the tower's pinnacle
2025-07
First office tenants sign leases

Including JAB Holding Company and Texas Capital Bank.

2025-11
The Moss private club opens

A 40,000-square-foot members' club spanning four lower floors.

2025-12
The exterior nears completion; Rabina secures a $640 million refinancing loan from The Carlyle Group
2026-08
Construction substantially wraps up

Residential closings have commenced; more than 95% of units are reported sold.

Sources

Sources: Wikipedia; New York YIMBY (construction wrap-up); New York YIMBY (exterior completion); New York YIMBY (pinnacle); New York YIMBY (topping out); Kohn Pedersen Fox; New York Real Estate Journal; The Skyscraper Center.

By Updated Built from city filings and published reporting. About Hush Street

Leave a Reply