2 World Trade Center: American Express’s New 1,226-Foot Headquarters

The stalled 2 World Trade Center site, photographed May 2023  before vertical construction resumed in July 2026.
The stalled 2 World Trade Center site, photographed May 2023 — before vertical construction resumed in July 2026. Photo by Benoît Prieur via Wikimedia Commons, CC0.

After two decades of stalled and superseded designs, the last office tower planned for the World Trade Center site is rising at 200 Greenwich Street as the future global headquarters of American Express.

Financial District, Manhattan
Under Construction Office tower · Updated September 2026
Address200 Greenwich Street, New York, NY 10007
Height1,226 ft · 55 stories
Office spaceNearly 2 million sq ft
ArchitectFoster + Partners
Anchor tenantAmerican Express (sole occupant, up to 10,000 employees)
DeveloperSilverstein Properties
Review TrackOther / Unclear
From Hush Street’s project record, updated Sep. 1, 2026
Latest Update — September 2026
A ceremonial groundbreaking was held July 9, 2026 — nearly 25 years after the September 11 attacks — officially restarting vertical construction on 2 World Trade Center. American Express finalized its commitment as sole anchor tenant that February, locking in Foster + Partners’ current design: a 1,226-foot, 55-story tower with nearly 2 million square feet of office space, targeted for completion in 2031.

What Is 2 World Trade Center?

A rendering released by developer Silverstein Properties on the day American Express committed to the tower, looking up the facade at its planted terraces. Per the developer, the building will carry more than an acre of outdoor space across several terraces and gardens.Instagram · @silversteinproperties · posted Feb. 25, 2026

2 World Trade Center is the final office tower planned for the 16-acre World Trade Center site, rising at 200 Greenwich Street on the northeast corner of the complex, across from Santiago Calatrava’s Oculus and next to the Perelman Performing Arts Center. The Port Authority of New York and New Jersey owns the underlying land and ground-leases it to Silverstein Properties, which has held development rights to the site since a 2006 agreement reached in the aftermath of the September 11 attacks.

As designed today by Foster + Partners, the tower will stand 1,226 feet across 55 floors, with nearly 2 million square feet of office space arranged around a stepped composition of setback volumes and more than an acre of landscaped terraces. It’s being built as the future global headquarters of American Express, which plans to relocate roughly 10,000 employees here from its current home at 200 Vesey Street once construction is complete.

Location

200 Greenwich Street / 2 World Trade Center, via Google Street View. Google's own imagery date may not reflect current construction progress. — Imagery: Google Street View

2 World Trade Center sits at 200 Greenwich Street on the northeast corner of the World Trade Center site, across Church Street from the 9/11 Memorial and directly opposite the Oculus transit hub. View on Google Maps.

A Quarter-Century of Stalled and Superseded Designs

A rendering of the pre-American Express Foster + Partners scheme rising beside One World Trade Center and the Oculus, posted while the site was still on hold. New York YIMBY described that version as a 62-story, 1,230-foot tower, and noted that the unfinished base was then still covered in mural-painted construction sheds.Instagram · @yimbygram · posted Dec. 4, 2025

2 World Trade Center’s story is less about one building than about four different buildings proposed for the same site over twenty years, as market conditions and prospective tenants repeatedly changed. Foster + Partners was first hired in 2006 and unveiled a 78-story, 1,254-foot design topped by four sloping diamond-shaped pinnacles, angled specifically to avoid casting a shadow over the planned 9/11 memorial. Excavation began in 2008, and foundation work was substantially complete by 2013 — but the tower never rose above street level. No anchor tenant had been secured, and post-financial-crisis office demand didn’t justify going further. For roughly the next decade, the unfinished base sat behind construction sheds, a visible gap in an otherwise rebuilt skyline.

In 2015, Silverstein tried a different approach: Bjarke Ingels Group redesigned the tower as a stack of cantilevered glass cuboids, about 1,340 feet tall, tailored to the space and studio needs of prospective anchor tenants News Corp and 21st Century Fox. That plan collapsed too, when both companies withdrew their commitment in January 2016. Silverstein brought Foster + Partners back in January 2020, and the firm has designed every iteration of the tower since — including a 2022 hybrid version, developed with Deutsche Bank in mind as a potential anchor, that blended BIG’s stacked massing with a new staggered crown. That hybrid approach carried through once American Express finally signed on.

The Current Project

A Foster + Partners rendering of the final design seen from the 9/11 Memorial plaza, with the Oculus at right, showing the stepped massing and staggered loggia terraces. YIMBY posted it after the July 9 groundbreaking, reporting that crews were already working around the building’s core.Instagram · @yimbygram · posted Jul. 18, 2026

Negotiations with American Express began in September 2024, and the company finalized its commitment as the tower’s sole anchor tenant and future sole occupant on February 25, 2026 — locking in the design, financing, and construction plans that had eluded the project for nearly two decades. A ceremonial groundbreaking followed on July 9, 2026, nearly 25 years after the September 11 attacks, restarting vertical construction on the last undeveloped office site at the World Trade Center. State officials estimate the project will generate more than 3,200 construction-era jobs and roughly $6 billion in combined economic impact for New York City and State.

Foster + Partners’ final design calls for a stepped tower with six staggered loggia terraces, metal paneling around its perimeter columns, and fully electric building systems pursuing LEED certification. Completion is targeted for 2031.

The Site’s First Construction Attempt

Early excavation-era construction at the 2 World Trade Center site, January 2011
The 2 World Trade Center site during its first construction attempt, January 2011 — work that stalled after foundations were completed around 2013. Photo by vincent desjardins via Wikimedia Commons, CC BY 2.0.

This photo, taken in January 2011, shows the site during the excavation phase of Foster + Partners’ original 2006 design — the design that never went beyond a foundation. It’s a useful reminder that “under construction” has been true of this site, on and off, for most of the last two decades.

Timeline

Full timeline · 14 entries
2003-02
Daniel Libeskind wins the WTC master plan competition

Establishes the overall site layout that later development, including 2 World Trade Center, would follow.

2004-07
A 65-story 2 World Trade Center is proposed

For the site's northeast corner, per the master plan then in progress.

2006-05
Norman Foster / Foster + Partners hired as design architect
2006-09
First Foster + Partners design revealed

An 78-story, 1,254-foot tower with a distinctive crown of four sloping diamond-shaped pinnacles, angled to cast no shadow on the planned 9/11 memorial.

2008
Excavation and site work begin
2013
Foundation work completed; construction stalls above street level

No anchor tenant secured and post-financial-crisis market conditions halted work above grade. The unfinished base sat behind construction sheds for roughly the next decade.

2015-05
Bjarke Ingels Group unveils a redesign

A stacked, cantilevered composition of glass-clad cuboid volumes, roughly 1,340 feet tall, developed at Silverstein's request to court prospective media-company tenants News Corp and 21st Century Fox.

2016-01
News Corp and 21st Century Fox withdraw

Ending BIG's tenant-driven design rationale and leaving the project without an anchor again.

2020-01
Silverstein announces a return to an updated Foster + Partners design
2022
Revised Foster + Partners renderings published

A hybrid design blending BIG's stacked-volume massing with a new staggered crown and landscaped terraces, developed with prospective anchor tenant Deutsche Bank in mind.

2024-09
Negotiations begin with American Express
2026-02-25
American Express finalizes its commitment as sole anchor tenant

Locking in the current design: 1,226 feet, 55 floors, nearly 2 million square feet, up to 10,000 employees.

2026-07-09
Ceremonial groundbreaking marks construction restart

Held nearly 25 years after the September 11 attacks; 2 World Trade Center is the final office tower to rise on the 16-acre World Trade Center site.

2031
Completion targeted

Sources

Sources: Wikipedia; Office of the Governor of New York (announcement, Feb 2026); Office of the Governor of New York (groundbreaking, Jul 2026); ConstructConnect; ArchDaily; Dezeen (2020 return to Foster); The Architect’s Newspaper (2015 BIG redesign); ABC News; NY1; Bisnow; YIMBY Forums (height/floor cross-check).